GATE LNG RECEIVING TERMINAL MAASVLAKTE ROTTERDAM · 2018. 5. 22. · GATE LNG RECEIVING TERMINAL...
Transcript of GATE LNG RECEIVING TERMINAL MAASVLAKTE ROTTERDAM · 2018. 5. 22. · GATE LNG RECEIVING TERMINAL...
-
GATE LNG RECEIVING TERMINAL GATE LNG RECEIVING TERMINAL MAASVLAKTE ROTTERDAMMAASVLAKTE ROTTERDAM
BETONVAKDAGEN 29/09/2009BETONVAKDAGEN 29/09/2009
Dennis Dennis SommeijerSommeijer –– WerkvoorbereiderWerkvoorbereiderCFE LNG vofCFE LNG vof
-
PROJECT
> Import terminal voor LNG
> LNG = Vloeibaar gas bewaard op -160°C.
> 3 Tanks van elk 180.000 m3 vloeibaar gas
> Diameter van de tanks is 86m. – hoogte 50m.
-
BETROKKEN PARTIJEN
> Opdrachtgever: GATE (Vopak en Gasunie)
> Hoofdaannemer D&C: Internationaal ConsortiumTechint / Sener / Entrepose / Vinci
> Onderaannemer Civiele werken LNG tanks: CFE LNG vof.
-
PROJECTLOCATIE MAASVLAKTE ROTTERDAM
-
Part I. - CONSTRUCTION OF THE GATE LNG RECEIVING TERMINAL
-
SCOPE VAN CFE LNG vof.
> Bodemverbetering> Fundatievloeren> Wanden> Voorspanning van de wanden ( horizontaal & verticaal. )> Dak> Dak platform> Dak waterdichte laag> Civiele werken in de tank
-
CIVIELE WERKEN - BOUWMETHODEN
WERKVLOER MET FOLIE
-
CIVIELE WERKEN - BOUWMETHODEN
FUNDERINGSVLOEREN
-
CIVIELE WERKEN - BOUWMETHODEN
FUNDERINGSVLOEREN – RANDKIST PERI TRIO
-
CIVIELE WERKEN - BOUWMETHODEN
FUNDERINGSVLOEREN
-
CIVIELE WERKEN - BOUWMETHODEN
WANDEN
-
CIVIELE WERKEN - BOUWMETHODEN
WANDEN
-
CIVIELE WERKEN - BOUWMETHODEN
WANDEN
-
CIVIELE WERKEN - BOUWMETHODEN
WANDEN – BEKISTING PERI CB 240 MET VARIO GT24
-
CIVIELE WERKEN - BOUWMETHODEN
WANDEN
-
07CIVIELE WERKEN - BOUWMETHODEN
-
CIVIELE WERKEN - BOUWMETHODEN
WANDEN
-
CIVIELE WERKEN - BOUWMETHODEN
WANDEN
-
CIVIELE WERKEN - BOUWMETHODEN
WANDEN
-
CIVIELE WERKEN - BOUWMETHODEN
WANDEN
-
CIVIELE WERKEN - BOUWMETHODEN
BETON STORTEN
-
CIVIELE WERKEN - BOUWMETHODEN
AFWERKEN BETON
-
21CIVIELE WERKEN - BOUWMETHODEN
-
CIVIELE WERKEN - BOUWMETHODEN
VOORSPANNING
-
CIVIELE WERKEN - BOUWMETHODEN
TIJDELIJKE DEUREN
-
Mechanical Work
Assembly of Roof
Bottom Liner PlateAnnular Plate
Stairway Center Support
Outer Support Outer Support
From Crane From Crane
Top RingRoof Rafter
Ground Level
STAALBOUWKUNDIGE WERKEN
-
MECHANICAL WORKS
-
MECHANICAL WORKS
-
MECHANICAL WORKS
-
MECHANICAL WORKS
-
31 Mechanical Work
Assembly of Suspended Deck
Outer Support Outer Support
Roof
Suspended Deck
Suspended Rod
Temporary Support
Ground Level
-
MECHANICAL WORKS
-
34 Mechanical WorkRoof Air Raising
Roof
Suspended Deck
Ground Level
-
Bottom Insulation and Plate
Opening
Roof Concrete
Inner Shell Plate Inner Shell Plate
“H”
Bottom Slab
Perlite ConcreteFoam GlassInner Bottom Plate(9&Ni)
Secondary Bottom Plate(9%Ni)
Detail of “H”
Ground Level
Bottom Liner Plate(C.S.)
-
Inner Shell Plate
Opening
Roof Concrete
Turning Table
Inner Shell Plate
Inner Shell PlateInner Shell Plate
Inner Shell Plate
Ground Level
-
Hydrostatic, Vacuumand Pneumatic Test
Inner Shell Plate
Pump Column
Inner Stairway
Hydrostatic Test Level
PRV
Ground Level
-
Dome Space Insulation & Perlite Powder Filling
Inner Shell Plate
Pump Column
Inner Stairway
PRV Nozzle
Platform
Staircase
Suspended Deck
Walkway
Perlite Filling Nozzle
Perlite Powder
Perlite Powder
Glass Wool or Perlite Powder
Perlite Filling Pipe
Ground Level
-
CIJFERS
Totaal hoeveelheden voor 3 tanks :
> Beton : 50.000 m3
> Wapening : 10.000 ton
> Voorspan staal : 1.750 tons
> Dak oppervlak:19500 m2
> Klimbekisting:5850 m2