BC_AN_CPM 2016.pdf

download BC_AN_CPM 2016.pdf

of 16

Transcript of BC_AN_CPM 2016.pdf

  • 8/15/2019 BC_AN_CPM 2016.pdf

    1/16

    RMK 252 – PRINCIPLES OF

    PROJECT MANAGEMENT

    PROJECT MANAGEMENT TECHNIQUES TOOLS

    -BAR CHARTS, ARROW DIAGRAM CRITICAL PATH METHOD

    MARCH 6

    TH

    2008

      ARMAN ABDUL RAZAK

  • 8/15/2019 BC_AN_CPM 2016.pdf

    2/16

    WHY THE NEED FOR PM TECHNIQUES & TOOLS?

    faster comprehension of data;

    easier interface for control and

    monitoring;

    better representation of analyzed

    facts and figures; entire framework/outline of the

    project can be viewed easier.

  • 8/15/2019 BC_AN_CPM 2016.pdf

    3/16

    BAR CHARTS

     A bar chart, also known as a bar graph, is a chart with

    rectangular bars of lengths proportional to that value that they

    represent. Bar charts are used for comparing two or more

    values. The bars can be horizontally or vertically oriented.

  • 8/15/2019 BC_AN_CPM 2016.pdf

    4/16

    HISTOGRAMS

     A histogram is a graphical display of tabulated frequencies. A histogram isthe graphical version of a table that shows what proportion of cases fall

    into each of several or many specified categories. The histogram differs

    from a bar chart in that it is the area of the bar that denotes the value, not

    the height, a crucial distinction when the categories are not of uniformwidth. The categories are usually specified as non-overlapping intervals of

    some var iab le . The categor ies or bars must be ad jacent .

  • 8/15/2019 BC_AN_CPM 2016.pdf

    5/16

    PARETO CHART

     A Pareto chart is a special type of bar chart where the values beingplotted are arranged in descending order. The graph is accompanied by a

    line graph which shows the cumulative totals of each category, left to

    right.

  • 8/15/2019 BC_AN_CPM 2016.pdf

    6/16

    ARROW DIAGRAM

     Also called: activity network diagram, network diagram, activitychart, node diagram, CPM (critical path method) chart

    Variation: PERT (program evaluation and review technique)

    chart

    The arrow diagram shows the required order of tasks in a project orprocess, the best schedule for the entire project, and potential

    scheduling and resource problems and their solutions. The arrow

    diagram lets you calculate the “critical path” of the project. This is the

    flow of critical steps where delays will affect the timing of the entireproject and where addition of resources can speed up the project.

  • 8/15/2019 BC_AN_CPM 2016.pdf

    7/16

    ARROW DIAGRAM

    When to Use an Arrow Diagram

    When scheduling and monitoring tasks within a complex

    project or process with interrelated tasks and resources.

    When you know the steps of the project or process, their

    sequence and how long each step takes.

    When project schedule is critical, with serious

    consequences for completing the project late or

    significant advantage to completing the project early.

  • 8/15/2019 BC_AN_CPM 2016.pdf

    8/16

    ARROW DIAGRAM

  • 8/15/2019 BC_AN_CPM 2016.pdf

    9/16

    ARROW DIAGRAM

    Start

    Finish

    Conductinterviews

    Investigate

    other 

    systems

     Analyse

    requirements

    Investigatepackages

    Investigate

    hardware

    Producereport

    Network diagram (activity-on-arrow format)

  • 8/15/2019 BC_AN_CPM 2016.pdf

    10/16

    Start

    Finish

    Conductinterviews

    Investigate

    other 

    systems

     Analyse

    requirements

    Investigatepackages

    Investigate

    hardware

    Producereport

    8

    4

    3

    8

    5

    5

    CRITICAL PATH

    METHOD (CPM)

    Network diagram with durations & critical path added

  • 8/15/2019 BC_AN_CPM 2016.pdf

    11/16

    The CPM Diagram

    • “ Tasks” are Arrows • “ Events” are Circles

    • “ Dummy Tasks” are Dashed Arrows

    • “ Critical Tasks” are Thick Arrows

  • 8/15/2019 BC_AN_CPM 2016.pdf

    12/16

    CRITICAL PATH

    METHOD (CPM)

  • 8/15/2019 BC_AN_CPM 2016.pdf

    13/16

    1. Specify the Individual Activit ies: From the work breakdown structure, a listing

    can be made of all the activities in the project. This listing can be used as the basis

    for adding sequence and duration information in later steps

    2. Determine the Sequence of the Activities: Some activities are dependent onthe completion of others. A listing of the immediate predecessors of each activity is

    useful for constructing the CPM network diagram.

    3. Draw the Network Diagram: Once the activities and their sequencing have

    been defined, the CPM diagram can be drawn. CPM originally was developed asan activity on node (AON) network, but some project planners prefer to specify the

    activities on the arcs.

    4. Estimate Activity Completion Time: The time required to complete each

    activity can be estimated using past experience or the estimates of knowledgeable

    persons. CPM is a deterministic model that does not take into account variation in

    the completion time, so only one number is used for an activity's time estimate

    5. Identi fy the Critical Path: The critical path is the longest-duration path through

    the network. The significance of the critical path is that the activities that lie on it

    cannot be delayed without delaying the project. Because of its impact on the entireproject, critical path analysis is an important aspect of project planning

    CRITICAL PATH

    METHOD (CPM)

  • 8/15/2019 BC_AN_CPM 2016.pdf

    14/16

    The critical path can be identified by determining the four parameters for

    each activity. The four parameters are Earliest Start, Earliest Finish, Latest

    Finish and Latest Start.

    Earliest Start: The earliest time at which the activity can start given that its

    precedent activities must be completed first.

    Earliest Finish: This is equal to the earliest start time for the activity plus the

    time required to complete the activity i.e. Earliest Start + Duration

    Latest Finish: The latest time at which the activity can be completed without

    delaying the project.

    Latest Start: It is equal to the latest finish time minus the time required to

    complete the activity i.e.Latest Finish - Duration

    CRITICAL PATH

    METHOD (CPM)

  • 8/15/2019 BC_AN_CPM 2016.pdf

    15/16

    Critical Path: The critical path is the path through the project network in which none

    of the activities have slack, that is, the path for which ES=LS and EF=LF for all

    activities in the path.

    Dummy arrows are used where required to avoid giving the same numbering to two

    activities as one of the rules for constructing network is that each activity must be

    unique. Suppose two activities "a" and "b" have to start from the same event and end

    at some other but same event then both "a" and "b" can't be given the same number

    so one is taken as a dummy activity and is represented by dotted lines.

    There are two important types of Float or Slack:

    Total Float is the spare time available when all preceding activities occur at the

    earliest possible times and all succeeding activities occur at the latest possible times.Total Float = Latest Start - Earliest Start

     Activities with zero Total float are on the Critical Path

    Free Float is the spare time available when all preceding activities occur at the

    earliest possible times and all succeeding activities occur at the earliest possibletimes.When an activity has zero Total float, Free float will also be zero.

    CRITICAL PATH

    METHOD (CPM)

  • 8/15/2019 BC_AN_CPM 2016.pdf

    16/16

    IN CLASS EXERCISE

    ACTIVITY DURATION (week) PREDECESSOR

    A

    B

    C

    D

    E

    F

    G

    H

    4

    3

    2

    4

    2

    3

    1

    2

    -

    A

    A

    B,C

    C

    D,E

    E

    F,G