13v129g OK

10
Diagnostics of Production Blasts in a Deep Underground Mine B. Mohanty 1 , D. Zwaan 1 , and F. Malek 2 1 Lassonde Institute of Mining, University of Toronto, Toronto, ON, Canada 2 Vale Inc., Copper Cliff, ON, Canada Abstract An extensive blast monitoring program has been carried out to study explosive performance and the effectiveness of blast designs in production blasts in a deep underground mine. Comprehensive monitoring of blasting vibrations through multi-station high-capacity high-frequency accelerometers, and borehole deformation history have been the main tools of such analysis. The mining activity involves relatively unstressed stopes as well as highly stressed stopes. More than 30 production blasts have been monitored, and the respective vibrations from close-range as well as distant seismic stations have been analyzed, and the vibration parameters (amplitude and frequency) have been correlated with explosive charge weight in the holes. It is found that the correlation between blasting rounds and the corresponding vibration amplitudes often have poor correlation for a very significant portion of the blasts. These point to either explosive charge malfunction in those specific blast holes, or inadequate blast design, or the effect of high in-situ stresses, or any combination thereof. This paper analyzes these variables and their effect on the overall blasting operation at the mine. Keywords: blasting vibrations, accelerometer, explosive energy, deep mines INTRODUCTION Misfires or any other type of malfunction in a surface blast, be it construction, quarrying, or large open pit operation, is easily detectable. Once the source has been identified, remedial action can be taken to ensure productivity and safety (Farnfield, 1966; Segarra et al, 2009). However, the situation in an underground operation is very different, especially in stope blasting or any other mass mining operations. In such cases, fan drilling and vertical retreat mining (VRM) are the usual methods employed. The boreholes in this case could have a single column of explosives or incorporate several explosive decks with various delays. Any missing or mis-fired holes in this case are extremely difficult to detect after the blast, because it is not possible to identify uniquely the source of a poor blast. In such cases, presence of oversize fragments cannot be ascribed to the blast in question. Standard blast monitoring through commercially available vibration monitoring is sometimes employed to monitor some of these blasts, but for reasons explained in this paper, it is not possible to carry out a truly diagnostic analysis of such blasts and identify any particular malfunctioning blast hole. EXPERIMENTAL PROGRAM The study was carried out at a deep underground mine. A typical cross section of a stope blast design at the mine is shown in Fig. 1. The borehole diameter was 162 mm, with varying depths as shown. A booster-sensitive packaged water-gel slurry explosive with a 1 of 10 Copyright © 2013 International Society of Explosives Engineers 2013G - Diagnostics of Production Blasts in a Deep Underground Mine

Transcript of 13v129g OK

Page 1: 13v129g OK

Diagnostics of Production Blasts in a Deep Underground Mine

B. Mohanty1, D. Zwaan1, and F. Malek2

1Lassonde Institute of Mining, University of Toronto, Toronto, ON, Canada 2Vale Inc., Copper Cliff, ON, Canada

Abstract An extensive blast monitoring program has been carried out to study explosive performance and the effectiveness of blast designs in production blasts in a deep underground mine. Comprehensive monitoring of blasting vibrations through multi-station high-capacity high-frequency accelerometers, and borehole deformation history have been the main tools of such analysis. The mining activity involves relatively unstressed stopes as well as highly stressed stopes. More than 30 production blasts have been monitored, and the respective vibrations from close-range as well as distant seismic stations have been analyzed, and the vibration parameters (amplitude and frequency) have been correlated with explosive charge weight in the holes. It is found that the correlation between blasting rounds and the corresponding vibration amplitudes often have poor correlation for a very significant portion of the blasts. These point to either explosive charge malfunction in those specific blast holes, or inadequate blast design, or the effect of high in-situ stresses, or any combination thereof. This paper analyzes these variables and their effect on the overall blasting operation at the mine. Keywords: blasting vibrations, accelerometer, explosive energy, deep mines INTRODUCTION Misfires or any other type of malfunction in a surface blast, be it construction, quarrying, or large open pit operation, is easily detectable. Once the source has been identified, remedial action can be taken to ensure productivity and safety (Farnfield, 1966; Segarra et al, 2009). However, the situation in an underground operation is very different, especially in stope blasting or any other mass mining operations. In such cases, fan drilling and vertical retreat mining (VRM) are the usual methods employed. The boreholes in this case could have a single column of explosives or incorporate several explosive decks with various delays. Any missing or mis-fired holes in this case are extremely difficult to detect after the blast, because it is not possible to identify uniquely the source of a poor blast. In such cases, presence of oversize fragments cannot be ascribed to the blast in question. Standard blast monitoring through commercially available vibration monitoring is sometimes employed to monitor some of these blasts, but for reasons explained in this paper, it is not possible to carry out a truly diagnostic analysis of such blasts and identify any particular malfunctioning blast hole. EXPERIMENTAL PROGRAM The study was carried out at a deep underground mine. A typical cross section of a stope blast design at the mine is shown in Fig. 1. The borehole diameter was 162 mm, with varying depths as shown. A booster-sensitive packaged water-gel slurry explosive with a

1 of 10

Copyright © 2013 International Society of Explosives Engineers

2013G - Diagnostics of Production Blasts in a Deep Underground Mine

Page 2: 13v129g OK

Fig. 1 Typical ring blast layout

2 of 10

Copyright © 2013 International Society of Explosives Engineers

2013G - Diagnostics of Production Blasts in a Deep Underground Mine

Page 3: 13v129g OK

density of 1.15 g/cc was used throughout. The quoted effective RWS (i.e. gas expansion up to 100 MPa) by the manufacturer of this product was 96, with a VOD of up to 4900 m/s. Each explosive column is bottom initiated with a 450 g Pentolite booster. Blast monitoring at the mine is usually carried out with a commercially available monitor (Instantel Minimate) employing 3-component geophones. The first step in this study was to ascertain the adequacy of this vibration monitor in assessing the production blasts at the mine. For this purpose, a comparative study was carried out with high-frequency accelerometers placed side by side with Minimate. The usual precautions were taken in mounting the geophones and the accelerometers (Farnfield, 1996) on to the surface of the rock underground. The accelerometers had an upper frequency range in excess of 10 kHz and the usual acceleration limit was 100g. The placement of the two types of monitors (i.e. geophones and accelerometers) is shown in Fig.2. The data for the accelerometer recording was carried out with both an analog data acquisition system with a bandwidth of DC to 45 kHz, and a digital data acquisition system with a sampling rate of 1MHz.

#1 Geophone : 9.3 m West of Ring 8 (Vale Inco & U of T)

#2 Geophone : 3.0 m North of Safety Stn. (Vale Inco & U of T)

#3 Geophone : 11 m West of Safety Stn. (U of T Geophone only)

#1

#3

#2

6000 N

4500 E

4000 E

11.0 m

3.0

m

9.3 m

Crtn 4263 Stope @ 6600 Level

Near Field Blast Monitoring

Fig. 2 Placement of vibration monitors (i.e. geophones and accelerometers) in Stope 4263 at 6600 level for comparison of blast records ANALYSIS A typical vibration record obtained with the geophones (i.e. Minimate) along longitudinal, transverse and vertical directions is shown in Fig. 3. Individual delay rounds are clearly seen in the vibration record, despite the usual scatter in firing times. The highly unequal

3 of 10

Copyright © 2013 International Society of Explosives Engineers

2013G - Diagnostics of Production Blasts in a Deep Underground Mine

Page 4: 13v129g OK

particle velocity amplitudes among the delay rounds are clearly evident. The data highlights the need for multi-axial recording of vibrations, but the pronounced variations along each axis can be attributed only partly to the varying charge weights in the holes.

Fig.3 Particle velocity records obtained with geophones from a production blast A more diagnostic comparison between high-frequency accelerometer recordings and those by geophones is illustrated in Fig. 4 for the same blast. Closer examination of the two records, i.e. particle velocity records from the geophones and integrated accelerometer data, from the same blast shows only a qualitative agreement between the two types of recordings. The peak particle velocity values obtained by integration of the accelerometer data show consistently higher amplitudes than those obtained with direct geophone recordings, despite both geophones and accelerometers placed in the same location. The difference between the two types of recordings is further amplified when one examines the frequency content of the individual wavelets corresponding to each delay round. The respective frequency spectra of particle velocity from the geophone and accelerometer recordings are shown in Fig. 5, for a single delay round. Whereas, the energy content in the geophone recording is seen to be confined below 300 Hz, the same particle velocity values obtained from integration of accelerometer data shows the maximum amplitude closer to 1kHz or higher. Furthermore, in most cases the peak particle velocity derived from accelerometer data greatly exceeds those obtained by geophone recordings.

4 of 10

Copyright © 2013 International Society of Explosives Engineers

2013G - Diagnostics of Production Blasts in a Deep Underground Mine

Page 5: 13v129g OK

Fig. 4 Comparison of geophone recording with that of accelerometer recording for the same blast (note: accelerometer recordings have been integrated to yield particle velocity) These differences have serious implications when one compares the resultant particle velocity reocords obtained by the two modes of recording. This is illustrated in Fig. 6, which shows the comparison between the resultant particle velocity for the geophone and accelerometer recordings, for a typical production blast with pyrotecnic delays. The scatter in firing times between the delay rounds is obvious but to be expected. Similarly, the varying particle velocity amplitudes observed with both geophone recording and accelerometer recording among the events is to be expected, but due only partly to varying charge weights and the travel paths for the seismic waves, and related geological factors. The more serious observation is the fact that for the same charge weight per delay and distance, the peak particle velocity obtained from accelerometer recording is often greater than by a factor of two compared to peak particle velocity obtained with geophone recording.

5 of 10

Copyright © 2013 International Society of Explosives Engineers

2013G - Diagnostics of Production Blasts in a Deep Underground Mine

Page 6: 13v129g OK

Fig. 5 Comparison of frequency spectra of particle velocity obtained with geophone recording vs. accelerometer recording at same location along three orthogonal directions for the same production blast (all accelerometer data integrated to yield particle velocity)

Fig. 6 Comparison of resultant particle velocity from vibration record obtained from a typical production blast from both geophone and accelerometer stations at same location

6 of 10

Copyright © 2013 International Society of Explosives Engineers

2013G - Diagnostics of Production Blasts in a Deep Underground Mine

Page 7: 13v129g OK

For example, the event at ~300 ms shows the resultant particle velocity to be 80 mm/s, whereas the data derived from the accelerometer station at same location shows it be 190 mm/s. Similarly, the event arriving at 500 ms, the geophone data yields resultant particle velocity of 90 mm/s compared to 220 mm/s for the corresponding aceelerometer recording. This difference cannot be explained away simply because of charge weight differences or the geological factors involved, as both accelerometer recording and geophone recordings corrrespond to identical charge weights, geological conditions, and seismic travel paths. Particle Velocity Amplitudes and Explosive Energy The recorded vibration amplitudes can also be related to the explosive energy yield at the source, as the radiated energy can be shown to be proportional to the square of the amplitude of the particle velocity. Throughout this analysis it is assumed that the seismic energy (i.e. blast vibration energy) is directly related to the total explosive energy released in the borehole. This is a valid argument so long as the source function remains unchanged, i.e. there is no change in the type of explosive used, or the decoupling condition in the borehole is changed, or there is a significant change in the initiation mode employed in the blast that would result in a drastic change in the energy partitioning between shock and gas energy from the explosive (Mohanty, 2009). On this basis, the energy yield from the various explosive loads for the blast in question with accelerometer data is shown against designed delay times is shown in Fig. 7.

Fig. 7 Calculation of normalized explosive energy (i.e. energy in arbitrary units/kg of charge) in a production blast against the delay. The radii of the circles are scaled with respect to the maximum value of derived energy for any explosive charge weight in the blast in question

7 of 10

Copyright © 2013 International Society of Explosives Engineers

2013G - Diagnostics of Production Blasts in a Deep Underground Mine

Page 8: 13v129g OK

For a true comparison of energy levels, the derived energy values have been linearly scaled (i.e. normalized) with the corresponding charge weight for each delay round, as in earlier works (Mohanty et al, 1997). The effect of varying distances to the corresponding explosive charges on the amplitude of the particle velocity is considered minor in this case because of the relatively large distances involved between the stope blast and the monitoring stations.Therefore, the energy yield values shown in Fig. 7 would represent the actual specific energy estimates from each of the explosive columns in the blast, i.e. specific energy per kg of charge. The radius of each circle in Fig. 7 represents the relative specific energy/kg with respect to the maximum value obtained for selected blasts, irespective of the delay time recorded. If each explosive charge in the blast were to yield the same specific energy (i.e. MJ/kg), as expected, all the circles shown in the figure should have had the same radius, since there were no variations in explosive type or its diameter or its mode of intiation. However, as the figure shows there is considerable variation in specific energy release from the various explosive charges, with values ranging from 100% to total failure.

Fig. 8 Specific explosive energy (i.e. seismic energy) distribution in a production blast from various explosive rounds For this study, a very conservative criterion of specific energy release is applied, i.e. 0% to 20% of the expected energy release (with respect to the normalized maximum particle velocity amplitude) considered a failure, >20% to <40% considered a partial energy release, and >40% to 100% considered full energy release. On that basis, only three holes in the blast appeared to release full energy, six only partial energy, and seven holes with negligible energy. Another way of illustrating the specific energy release figures for a number of regular stope blasts is shown in Fig. 8. It shows twentyeight blast holes to

8 of 10

Copyright © 2013 International Society of Explosives Engineers

2013G - Diagnostics of Production Blasts in a Deep Underground Mine

Page 9: 13v129g OK

release less than 20% of the expected explosive energy, and only twentytwo blast holes yield nearly the full energy (ie.e. 40% to 100% of the expected energy). DISCUSSION AND CONCLUSION There is considerable data available in open literature on measurement and analysis of blasting vibrations from mining and quarrying operation. Much of this information however relates to estimation of damage potential to civil structures and to a lesser extent, to pit slope stability and blast-induced damage to rockmass, and detecting obvious misfires or firing time deviations in a blasting round. In contrast, near-field vibration measurements and their diagnostic use in examining explosive performance and blast design has received much less attention (Mohanty, 1997; Fleetwood et al, 2009). The results of this study show that there is significant discrepancy between the expected vibration amplitudes in terms of specific vibration energy released and that actually measured in the stope blasts under investigation, all other conditions remaining the same. In this case, aside from the usual firing time deviations with pyrotechnic detonators, typically more than a third of the blast holes release very little energy in the form of transmitted seismic energy over multiple accelerometer stations. As is well known, low vibration amplitudes can be caused by a variety of causes such as varying geology (Fleetwood and Villaescusa, 2011), poor loading practice, hole deviation resulting in dislodgement of or damage to explosive charges in adjacent blast holes, or the quality of the explosive products itself. However, these apparent blast malfunctions cannot be attributed to the above causes in the great majority of the production blasts in question, especially since the blasts were monitored at multiple accelerometer stations. Although none of the above factors can be ruled out in some individual cases, the widespread malfunctions exemplified in this study point to a more systemic cause for these apparent failures such as lithologic factors. The effect of the latter is evident from wide-scale blast hole deformation due to high ambient stresses that are characteristic in some of the stopes at this deep mine, and is part of the continuing investigation. The study also aims to provide not only superior blast diagnostics but also improved blast designs to counter these defficiencies. Acknowledgement The authors are grateful for the financial assistance provided by the National Science and Engineering Research Council of Canada (NSERC) and Vale Canada Inc. during the course of this research. In addition, the extensive assistance provided by Vale for field monitoring of vibrations in one of their underground mines is also gratefully acknowledged. References Farnfield, R.,1996,”So you think you are monitoring peak particle velocity”; Proc. 12

th

Symp. on Ann. Symp. on Explosives and Blasting Res.; Int. Soc. of Explosives Engrs.;

9 of 10

Copyright © 2013 International Society of Explosives Engineers

2013G - Diagnostics of Production Blasts in a Deep Underground Mine

Page 10: 13v129g OK

p. 13-20. Fleetwood, K.G., Villaescusa,E., Li, J. and Varden, R.; 2009,“Comparison of traditional

near-field vibration prediction models with three-dimensional vibration scaling and blast wave energy”; Proc. 9th Int. Symp. on Rock Fragmentation by Blasting (FRAGBLAST 9), Sanchidrian, J.A.;ed.; CRC Press, p. 579-588. Fleetwood, K.G. and Villaescusa, 2011, “Measured results of the influence of of a large- scale fault on blasting vibrations in sub-level open stoping”; Proc. 37

th Ann. Conf. on Explosives and Blasting Tech.; Int. Soc. Explosives Engrs., ISEE, p. 1-13. Mohanty, B. and Yang,R.,1997, “Blasting vibrations and explosives performance”; Proc. 13th Ann. Symp. on Explosives and Blasting Res., Int. Soc. Explosives Engrs.,ISEE, p.15-28. Mohanty, B.;2009, “Intra-hole and inter-hole effects in typical blast designs and their implications on explosives energy release and detonator delay time—A critical review”; Proc. 9

th Int. Symp. on Rock Fragmentation by Blasting (FRAGBLAST 9); Sanchidrian, J.A; ed., CRC Press, p.23-31. Segarra, P, Sanchidrian, J.A., Lopez, J.M.; Querol, E. and Guiterrez, J., 2009, “Assessment of the error of blast vibration measurements”; Proc. 9

th Int. Symp. on Rock Fragmentation by Blasting (FRAGBLAST 9); Sanchidrian, J.A; ed., CRC Press, p.551-560.

10 of 10

Copyright © 2013 International Society of Explosives Engineers

2013G - Diagnostics of Production Blasts in a Deep Underground Mine