13.55 George Wachtel

download 13.55 George Wachtel

of 25

Transcript of 13.55 George Wachtel

  • 8/10/2019 13.55 George Wachtel

    1/25

    OMV Aktiengesellschaft

    Impact of the BP Macondo

    Blowout on ME Operations

    Gas Arabia 2011

  • 8/10/2019 13.55 George Wachtel

    2/25

    2 SB Presentation Macondo

    Disclaimer

    This Presentation is based on information available to the public from various sources at the time of this

    presentation , The OMV Sustainability:HSSE department provides no assurance for the accuracy and correctness of

    the information in the Presentation and the consequences being a result of using the information herein.

    The information opinions and analysis contained herein are based on sources believed to be reliable but no

    representation, expressed or implied, is made as to its accuracy, completeness or correctness.

    The opinions contained herein reflect my current judgment and are subject to change without notice and are

    therefore probably worth less .

  • 8/10/2019 13.55 George Wachtel

    3/25

    3 SB Presentation Macondo

    Setting the Scene

    Deepwater Horizon 5th generation semi-submersible deepwater rig -

    contract with BP since 2001.

    Completed seven years without a Lost-Time-Incident.

    Contractor had a proven track record in GoM.

    Close finishing the well when the blowout occurred.

  • 8/10/2019 13.55 George Wachtel

    4/25

    4 SB Presentation Macondo

    The Deepwater Horizon and its BOP

  • 8/10/2019 13.55 George Wachtel

    5/25

    5 SB Presentation Macondo

    The BP Investigation Report

    astonishing lapses in safety management

    storm of m istakes mechanical failures and design faults led to the accident

    eight critical factors went wrong simultaneously; if just one of them had been eliminated the outcome of the

    Deepwater Horizon tragedy would have been either prevented or reduced in severity

    Financial Times, 9.9.2010)

  • 8/10/2019 13.55 George Wachtel

    6/25

    6 SB Presentation Macondo

    The BP Investigation ReportKey Findings Annulus Cement

    Mechanical Barriers inside Casing

    Pressure Integrity Testing

    Well Monitoring

    Well Control Responses

    BOP Emergency Operation

    Source: BP Report May 24 2010

  • 8/10/2019 13.55 George Wachtel

    7/25

    7 SB Presentation Macondo

    1. The annulus cement barrier did not isolate the hydrocarbons.

    2. The shoe track barriers did not isolate the hydrocarbons.

    3. The negative-pressure test was accepted although well integrity had not been established.

    4. Influx was not recognized until hydrocarbons were in the riser.

    5. Well control response actions failed to regain control of the well.

    6. Diversion to the mud gas separator resulted in gas venting onto the rig.

    7. The fire and gas system did not prevent hydrocarbon ignition.

    8. The BOP emergency mode did not seal the well.

    8 Key Findings.

  • 8/10/2019 13.55 George Wachtel

    8/25

    8 SB Presentation Macondo

    The first minutes after

  • 8/10/2019 13.55 George Wachtel

    9/25

    9 SB Presentation Macondo

    The first minutes later

  • 8/10/2019 13.55 George Wachtel

    10/25

    10 SB Presentation Macondo

    Several hours later

  • 8/10/2019 13.55 George Wachtel

    11/25

    11 SB Presentation Macondo

    The Well Kill Operation

  • 8/10/2019 13.55 George Wachtel

    12/25

    12 SB Presentation Macondo

    Largest Offshore Effort in History

  • 8/10/2019 13.55 George Wachtel

    13/25

    13 SB Presentation Macondo

    The Barrier Philosophy

    Most operators define a dual mechanical barrier principle for their operations i.e. requiring a minimum of two

    physical means of separation between the reservoir pressure and the surface.

    In the Macondo case, those would have been (1) the blowout preventer and (2) the casing cemented into the well

    bore.

    While the cemented casing had been pressure tested, the results were incorrectly interpreted by the rig crew,

    subsequently allowing hydrocarbons to enter the well.

  • 8/10/2019 13.55 George Wachtel

    14/25

    14 SB Presentation Macondo

    Accidents and incident investigation:

    the Swiss Cheese Model (1)

    From: James Reason, Managing the Risks of Organizational Accidents, 1997, p9

  • 8/10/2019 13.55 George Wachtel

    15/25

    15 SB Presentation Macondo

    The Swiss Cheese Model (2)

  • 8/10/2019 13.55 George Wachtel

    16/25

    16 SB Presentation Macondo

    Deep Water Horizon

  • 8/10/2019 13.55 George Wachtel

    17/25

    17 SB Presentation Macondo

    The Bow Tie: Defenses in depth

    Barriers to

    prevent

    threat release

    Recovery

    preparedness

    measures

    Control of

    Escalation

    factors

    Control of

    Escalation

    factors

    Pre-event Post event

    How it failed?

    Why it failed?

  • 8/10/2019 13.55 George Wachtel

    18/25

    18 SB Presentation Macondo

    Analogies in the ME 2

    The Nowruz oil field, in Iran, was the site of several 1983 oil spills.One spill was initially caused by a tanker hitting a platform.

    The platform was attacked by Iraqi helicopters and the spill caught fire. The Iran-Iraq war prevented capping of the well until

    September 1983. Eleven people were killed during the capping

    A separate spill occurred when Iraqi helicopters attacked a nearby platform in March 1983. The well was capped in May, 1985.

    Nine men were killed during the capping. Approximately 733,000 bblof oil were spil led because of this incident

  • 8/10/2019 13.55 George Wachtel

    19/25

    19 SB Presentation Macondo

    Analogies in the ME 1A firefighter tries to extinguish an oil well fire on Aug. 9, 1991, at the Greater Burgan oil field in Kuwait.

  • 8/10/2019 13.55 George Wachtel

    20/25

    20 SB Presentation Macondo

    Key Issues

    Water Depth

    The Macondo incident was in itself not a function of water depth, deep water only made the subsequent recovery from the disas ter

    more difficult.

    Staff Competency / People

    There have been several early warning signs (especially during the last hour before the explosion) that if properly detected and

    reacted to could have controlled the incident.

    Company Standards / Doing it Wrong

    The Macondo incident did not occur because BP or Transocean had insufficient standards but because the rig crew did not fully

    comprehend what was happening in the well and did not follow existing Standards.

    Regulatory Environment

    US regulatory framework is less stringent than UK/Norway/AUS/NZ.

  • 8/10/2019 13.55 George Wachtel

    21/25

    21 SB Presentation Macondo

    Lessons from the Gulf Spill

    The biggest immediate lesson is the need for a step change in safety and environment performance, which is

    practical and economically feasible.

    This can be achieved by:

    Combining regulatory regimes with prescriptive and performance-based regulations

    Addressing technical, human and organizational factors,

    Applying an integrated risk model,

    Allowing for full communication between operator, contractor and regulator, as well as determining clear roles and

    responsibilities and having a shared performance monitoring and decision making

  • 8/10/2019 13.55 George Wachtel

    22/25

    22 SB Presentation Macondo

    Impact on ME OperationsAbu Dhabi

    Abu Dhabis economic development will significantly

    increase natural gas demand over the next decade

    UAEs proven natural gas reserves of 214Tcf (AD ~ 198

    Tcf) is the sixth largest natural gas reserves in the world

    AD gas demand will increase to 12 Bcf/day by 2015 from

    the current level of 7 Bcf/day

    However most of Abu Dhabis gas is sour and some

    located in most sensitive and ecological important area

    under UNESCO Biosphere reserve.

    Reducing the impact on the sensitive environment is a

    major concern for ADNOC.

    Need to deal with hydrogen sulfide complicates gas field

    developments

  • 8/10/2019 13.55 George Wachtel

    23/25

    23 SB Presentation Macondo

    Impact on ME OperationsWay Forward

    Ensuring the continuing safety of oil & gas operations is a collaborative process that involves our industry with national and

    regional legislators, executive bodies, regulators and other stakeholders

    In order to restore confidence in hazardous drilling (deepwater, sour gas environment) companies must

    Develop a new containment response system

    Commit to financing the initial investments in specially-designed equipment.

    To help ensure that the results of the Macondo enquiries are incorporated into industry practice and government

    regulations, the ME operating companies should establish an Industry Response Group (IRG) similarly established by

    International Association of Oil & Gas Producers (OGP), which is closely liaising with United States industry groups and

    other industry associations around the world

  • 8/10/2019 13.55 George Wachtel

    24/25

    24 SB Presentation Macondo

    Operators Initiative to reduce Operational Risk

    The Mitigation of Major Accidental Events (MAE), Objectives:

    To identify operating assets with the potential to cause a major accident event that could jeopardize the longevity of a comp any.

    To review the effectiveness of the management systems in place that prevent and control a major accident event occurring.

    To review the effectiveness of emergency response management systems to minimise the residual risks if a major accident event

    occurs.

    To identify areas for improvement in the management of major accident hazards and emergency response at our high risk

    operational sites.

    To share best practice in high performing sites with all operational sites.

  • 8/10/2019 13.55 George Wachtel

    25/25

    25 SB Presentation Macondo

    Thank you for your attention