V-4- Pv Home-draft 23-07-13_2

download V-4- Pv Home-draft 23-07-13_2

of 39

Transcript of V-4- Pv Home-draft 23-07-13_2

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    1/39

    German Pakistan Financial Cooperation

    Development of Hydropower & Renewable Energy (HRE)Project Khyber-Pakhtunkhwa

    (Phase-I)

    TECHNICAL GUIDELINES & REPORTS

    VOLUME 4: DESIGN OF PV COMMUNITY SYSTEMS

    JULY 2013

    DRAFT

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    2/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 1 -

    Table of Content

    1 Basic Features 21.1 Cluster __________________________________________________________ 21.2 Demand _________________________________________________________ 21.3 Solar Radiation ___________________________________________________ 21.4 Sizing ___________________________________________________________ 31.5 Supply Voltage ___________________________________________________ 4

    2 System Lay-Out 52.1 Modules _________________________________________________________ 52.2 Batteries _________________________________________________________ 52.3 Wiring __________________________________________________________ 52.4 House installations ________________________________________________ 5

    3 ANNEXES 7

    INTEGRATION Environment & Energy Ltd.Bahnhofstr. 991322 Graefenberg / Germanywww.integration.org

    Ulrich Frings

    July 2013

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    3/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 2 -

    1 Basic Features

    The solar street/home lighting systems (SSLS) are foreseen to supply clusters of houses withbasic electricity for lighting and cooling (fan) purposes. The supply of single houses is notforeseen.

    1.1 Cluster

    In order to limit design works the supply systems have been grouped into 4 clusters containing 5,10, 15 and 20 houses. For each group standard designs for all equipment are made available tothe POs. Additional design works per site is thus limited to adjustment of foundation, fencing plan

    and wiring.

    1.2 Demand

    Considered appliances are compiled in Annex 1 and summarized in Table 1. A typical daily loadschedule for winter and summer is presented in Figure 1 for a 5-house cluster. Power for lightingis required during early morning and evening. Main consumer is the fan during summer.

    Table 1: Recommended Appliances per houseItem Amount Total Watt Remarks

    Room lighting 2 22 1 bulb of 11 W

    Fan 1 75

    Street lighting 0.2 4 1 per 5 householdsMobile charging 0.2 1 1 per 5 households

    Total 104Source:PPAF

    Figure 1: Load Schedules Cluster 1: 5 householdsDaily load Summer Daily load Winter

    Source: Annex 1.1

    1.3 Solar Radiation

    Monthly solar radiation for North Pakistan is shown in Figure 3. As expected, radiation is at peakduring summer and at minimum during winter months. An exceptional case is in August wheredue to the monsoon rains and the accompanying higher cloudiness the radiation values arecomparable lower.

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    4/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 3 -

    Figure 2: Monthly Solar Radiation

    Source: HOMER Software

    1.4 Sizing

    The systems shall provide the demanded basic electricity throughout the year. As mentionedabove critical period will be the month of August where comparable lower radiation meets theannual peak demand. A typical situation in beginning of August is presented in Figure 3.

    Figure 3: Capacity shortage in August

    Source: Own calculations; HOMER Simulation Software;

    Shortage starts at 2nd

    of August evening after batteries are discharged to its maximum 70%.During 3rdof August PV power is just enough to supply the daily demand; battery recharge is

    Battery state of charge (%)

    Inverter Output (load)

    PV Power (Generator)

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    5/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 4 -

    marginal. During 4

    th

    of August batteries are partly recharge (part of which is used during theevening and night. Recharge continues during 5thand 6thof August.

    However, a zero capacity shortage would require extraordinary large systems in terms ofmodules and batteries which would considerable increase costs which seems not economicalfeasible, the more that a high percentage of installed capacity would remain unused for most ofthe year.

    The system sizing is therefore based on an allowable power shortage factor of max. 1% and apeak reserve of 5.

    In order to minimize negative impacts on electricity supply during these days, the POS shall

    introduce respective measures to the community. Such measures might include: Reduction of load during these days (e.g. street lighting, mobile charging)

    Load shedding

    Reduction of fan hours.

    1.5 Supply Voltage

    The supply voltage depends mainly on the distance from generator to consumer and the relatedvoltage losses along the line. In addition, appliances are available at 230 V AC, 50HZ or for 12 VDC voltage, whereby the latter are more expensive and not always available compared to the ACdriven appliances).

    Voltage drops as function of diameter of cable and cable length are compiled in Annex 2.Maximum voltage drop along the distribution line should not exceed 10-25%. As can be takenfrom Annex 2 even for the 5 households cluster a distance of 40 m would require already 35mm cable. The same cross section would reach only about 10 m in case of the 20 householdscluster. Additional voltage losses are to expected at loosening cable connections and joints overthe years.

    Consequently, a 12 V DC supply is only feasible for single house supplies or in extraordinarycases where houses are located very close together. It is therefore recommended to base thesystems on 230 V AC voltage which ensures:

    - Sufficient voltage level within the houses to run the appliances- metering with common power meters (if required)- operation of common appliances available at lower cost- Reduced cost for wiring due to lower cable sizes- More buffer against weak and ageing installations with accompanying growing resistivity

    and related growing voltage losses- Optimization of generator location (distances of up to 100 m from generator to house are

    possible).

    The operation at 220 V AC requires a DC/AC inverter which parallel acts as charge controller forthe batteries. The minimum design requirements are compiled in Table 2.

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    6/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 5 -

    Table 2: Design AspectsItem Minimum lifetime Others

    Battery 7-8 years Maintenance free, sealed gel solar batteries to minimizerequirements on battery storage and to minimize risks ofhazards and environmental pollution

    Module 20 years Crystalline systems

    bulbs 10 Years (20,000 hrs) Energy saving bulbs or LEDS

    Street light 10 years LED (15,000 hrs)

    Supply voltage 220 V ACSource: own compilations; Annex 3

    2 System Lay-OutThe sub-project comprises of a centralized PV generator including batteries, charge controller andinverter, the distribution lines to the houses, and the supply of the street lights. Householdappliances are to be purchased by the customers themselves1.

    With respect to in-house appliances basic technical features should be given to the customersand communities in order to ensure that power demand is kept in the envisaged limits2.

    2.1 Modules

    Modules will be installed on iron supports which could be local made. The supports are fixed in R/fconcrete strip foundations. A standard lay-out is shown in Annex 3.1. Close to the module area, abattery room including all necessary control devices is erected. The entire area should beprotected (fences, walls) in such a way that the modules are prevented against damaging.

    2.2 Batteries

    Batteries are placed in a battery room. The room should be insulated in such a way that theminimum and maximum temperatures of the batteries are always (-20C +45C) and optimaltemperatures (+15C - +35C) are met during most of the time.

    2.3 Wiring

    Wiring should be done by using XLPE 2 core, double insulated (outer and inner shield) Al cable of0.6 to 1kV nominal voltage. The diameter depends on the distances from the generator to thehouses and needs to be adjusted to the local conditions. Fixing of cables could be done at wallsby using appropriate tools and at 5-7m steel or wooden poles.

    2.4 House installations

    House installation is not part of the project. However, prior to connection the house installationshould be inspected and certified by the PO in order to ensure minimum safety and qualitystandards. With respect to the comparable low demand, installation of meters is not essential.However, MCBS and RCBOs should be installed in each house for safety purposes.

    1Technical specifications and lists of recommended equipment should be provided by the POS to the communities and customers

    2PV systems are very sensitive against overload. Thus, the community should be able and willing to control installed appliances and

    power consumption

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    7/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 6 -

    System sizing

    Simulation of power generation and consumption have been conducted for each cluster by usingHOMER Software. The results are compiled in Annex 4 and summarized in Table 3.

    The simulation is based on the given summer and winter load schedules (Figure 1 and 2), thesolar radiation figures (Figure 3) and the following parameter:

    Operating reserve 5%

    Permissible capacity shortage:

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    8/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 7 -

    3 ANNEXES

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    9/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 8 -

    Annex 1: Appliances

    Annex 1.1: Cluster 1 5 households

    NumberofTargetHouses 5 Nos

    S.No Description Nos Appliance

    s

    1 Avergagehousesize

    (rooms) 2 10

    2 AirCooling

    Fan 1 5

    3 StreetLighting 1 1

    4 MobilChargingfacility 1 1

    S.No Appliance(DCPower) Units Wattage

    (Watts)

    Total

    Wattage

    Daily

    Operation

    Hours

    Total

    Energy

    (Wh)

    1 Room

    Lighting

    (ES) 10 11 110 6 660

    3 StreetLights(ES) 1 20 20 10 200

    4 AirCoolingFan(AC) 5 75 375 10 3.750

    5 MobileCharger 1 5 5 3 15

    ActualDailyEnergyDemand 0 0 510 4.625

    6 1.388

    6.013

    TheFudgeFactor@30%(SystemLossesforDCpowerPVsystem)

    Clusterof5houses

    Rational

    1lightperroom

    A.Data

    1fan

    Per

    house

    1streetlightperclusterof5

    houses

    InBuiltMobileCharger(s)

    B EnergyDemand

    NETDailyEnergyDemand(Wh)

    Daily load summer Daily load winter

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    10/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 9 -

    Annex 1.2: Cluster 2 10 households

    NumberofTargetHouses 10 Nos

    S.No Description Nos Appliance

    s

    1 Avergagehousesize

    (rooms) 2 20

    2 AirCoolingFan 1 10

    3 OutsideLighting 1 2

    4 MobilChargingfacility 2 2

    S.No Appliance(DCPower) Units Wattage

    (Watts)

    Total

    Wattage

    Daily

    Operation

    Hours

    Total

    Energy

    (Wh)

    1 RoomLighting(ES) 20 11 220 6 1.320

    3 StreetLights

    (ES) 2 20 40 10 400

    4 AirCoolingFan(AC) 10 75 750 10 7.500

    5 MobileCharger 2 5 10 3 30

    ActualDailyEnergyDemand 0 0 1020 9.250

    6 2.775

    12.025

    InBuiltMobileCharger(s)

    Clusterof5houses

    A.Data

    Rational

    1lightperroom

    1fanPerhouse

    1street

    light

    per

    cluster

    of

    5

    houses

    B EnergyDemand

    TheFudgeFactor@30%(SystemLossesforDCpowerPVsystem)

    NETDailyEnergyDemand(Wh)

    Daily load summer Daily load winter

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    11/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 10 -

    Annex 1.3: Cluster 3:- 15 households

    NumberofTargetHouses 15 Nos

    S.No Description Nos Appliance

    s

    1 Avergagehousesize

    (rooms) 2 30

    2 AirCoolingFan 1 15

    3 OutsideLighting 1 3

    4 MobilChargingfacility 2 2

    S.No Appliance(DCPower) Units Wattage

    (Watts)

    Total

    Wattage

    Daily

    Operation

    Hours

    Total

    Energy

    (Wh)

    1 RoomLighting(ES) 30 11 330 6 1.980

    3 Stre etLights(ES) 3 20 60 10 600

    4 AirCoolingFan(AC) 15 75 1125 10 11.250

    5 MobileCharger 2 5 10 3 30

    ActualDailyEnergyDemand 0 0 1525 13.860

    6 4.158

    18.018

    InBuiltMobileCharger(s)

    Clusterof5houses

    A.Data

    Rational

    1lightperroom

    1fanPerhouse

    1streetlightperclusterof5

    houses

    B EnergyDemand

    TheFudgeFactor@30%(SystemLossesforDCpowerPVsystem)

    NETDailyEnergyDemand(Wh)

    Daily load summer Daily load winter

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    12/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 11 -

    Annex 1.4: Cluster 4 20 households

    NumberofTargetHouses 20 Nos

    S.No Description Nos Appliance

    s

    1 Avergagehousesize

    (rooms) 2 40

    2 AirCoolingFan 1 20

    3 OutsideLighting 1 4

    4 MobilChargingfacility 3 3

    S.No Appliance(DCPower) Units Wattage

    (Watts)

    Total

    Wattage

    Daily

    Operation

    Hours

    Total

    Energy

    (Wh)

    1 RoomLighting(ES) 40 11 440 6 2.640

    3 StreetLights(ES) 4 20 80 10 800

    4 AirCoolingFan(AC) 20 75 1500 10 15.000

    5 MobileCharger 3 5 15 3 45

    ActualDailyEnergyDemand 0 0 2035 18.485

    6 5.546

    24.031

    InBuiltMobileCharger(s)

    Clusterof5houses

    A.Data

    Rational

    1lightperroom

    1fanPerhouse

    1streetlightperclusterof5

    houses

    B EnergyDemand

    TheFudgeFactor@30%(SystemLossesforACpowerPVsystem)

    NETDailyEnergyDemand(Wh)

    Daily load summer Daily load winter

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    13/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 12 -

    Annex 2: Voltage Drops in Cables

    Annex 2.1: Cluster 1 5 households

    MaxLoad 500 W

    SystemVoltage 12 V

    SystemCurrent: 42 A

    cable(mm): 0,75 1 1,5 2,5 4 6 10 16 20 25 35

    distanceto

    house(m)

    1 17 13 9 5 3 2 1 1 1 1 05 87 66 44 26 16 11 7 4 3 3 2

    10 175 131 87 52 33 22 13 8 7 5 4

    15 262 197 131 79 49 33 20 12 10 8 6

    20 349 262 175 105 66 44 26 16 13 10 7

    25 437 328 218 131 82 55 33 20 16 13 9

    30 524 393 262 157 98 66 39 25 20 16 11

    35 611 459 306 183 115 76 46 29 23 18 13

    40 699 524 349 210 131 87 52 33 26 21 15

    45 786 590 393 236 147 98 59 37 29 24 17

    50 874 655 437 262 164 109 66 41 33 26 19

    CalculationoflossesinAlcable

    Cluster1:5households

    Deltau(%)

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    50

    1 5 10 15 20 25 30 35 40 45 50

    Deltau(%)

    Voltagedropalongcable

    0,75 1,0mm 1,5mm 2,5mm 4 6 10 16 20 25 35

    distanceinm

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    14/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 13 -

    Annex 2.2: Cluster 2 10 households

    MaxLoad 1020 W

    SystemVoltage 12 V

    SystemCurrent: 85 A

    cable(mm):

    0,75 1 1,5 2,5 4 6 10 16 20 25 35

    distanceto

    house(m)

    1 36 27 18 11 7 4 3 2 1 1 1

    5 178 134 89 53 33 22 13 8 7 5 4

    10 356 267 178 107 67 45 27 17 13 11 8

    15 535 401 267 160 100 67 40 25 20 16 11

    20 713 535 356 214 134 89 53 33 27 21 15

    25 891 668 445 267 167 111 67 42 33 27 19

    30 1069 802 535 321 200 134 80 50 40 32 23

    35 1247 936 624 374 234 156 94 58 47 37 27

    40 1426 1069 713 428 267 178 107 67 53 43 31

    45 1604 1203 802 481 301 200 120 75 60 48 34

    50 1782 1336 891 535 334 223 134 84 67 53 38

    CalculationoflossesinAlcable

    Cluster2:10households

    Deltau(%)

    0

    5

    10

    15

    20

    25

    30

    35

    40

    1 5 10 15 20 25 30 35

    Deltau(%)

    Voltagedropalongcable

    1,5mm 2,5mm 4 6 10 16 20 25 35

    distanceinm

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    15/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 14 -

    Annex 2.3: Cluster 3 15 households

    MaxLoad 1525 W

    SystemVoltage 12 V

    SystemCurrent: 127 A

    cable(mm): 0,75 1 1,5 2,5 4 6 10 16 20 25 35

    distanceto

    house(m)

    1 53 40 27 16 10 7 4 2 2 2 1

    5 266 200 133 80 50 33 20 12 10 8 6

    10 533 400 266 160 100 67 40 25 20 16 11

    15 799 599 400 240 150 100 60 37 30 24 17

    20 1066 799 533 320 200 133 80 50 40 32 23

    25 1332 999 666 400 250 167 100 62 50 40 29

    30 1599 1199 799 480 300 200 120 75 60 48 34

    35 1865 1399 932 559 350 233 140 87 70 56 40

    40 2131 1599 1066 639 400 266 160 100 80 64 46

    45 2398 1798 1199 719 450 300 180 112 90 72 51

    50 2664 1998 1332 799 500 333 200 125 100 80 57

    CalculationoflossesinAlcable

    Cluster3:15households

    Deltau(%)

    0

    5

    10

    15

    20

    25

    30

    35

    40

    45

    1 5 10 15 20 25

    Deltau(%)

    Voltagedropalongcable

    1,5mm 2,5mm 4 6 10 16 20 25 35

    distanceinm

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    16/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 15 -

    Annex 2.4: Cluster 4 20 households

    MaxLoad 2035 W

    SystemVoltage 12 V

    SystemCurrent: 170 A

    cable(mm): 0,75 1 1,5 2,5 4 6 10 16 20 25 35

    distanceto

    house(m)

    1 71 53 36 21 13 9 5 3 3 2 25 356 267 178 107 67 44 27 17 13 11 8

    10 711 533 356 213 133 89 53 33 27 21 15

    15 1067 800 533 320 200 133 80 50 40 32 23

    20 1422 1067 711 427 267 178 107 67 53 43 30

    25 1778 1333 889 533 333 222 133 83 67 53 38

    30 2133 1600 1067 640 400 267 160 100 80 64 46

    35 2489 1866 1244 747 467 311 187 117 93 75 53

    40 2844 2133 1422 853 533 356 213 133 107 85 61

    45 3200 2400 1600 960 600 400 240 150 120 96 69

    50 3555 2666 1778 1067 667 444 267 167 133 107 76

    CalculationoflossesinAlcable

    Cluster4:20households

    Deltau(%)

    0

    10

    20

    30

    40

    50

    60

    1 5 10 15 20 25

    Deltau(%)

    Voltagedropalongcable

    1,5mm 2,5mm 4 6 10 16 20 25 35

    distanceinm

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    17/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 16 -

    Annex 3: Technical Specif ication of Main Equipment

    1 Inverter with integrated Charge Controller

    Inverter with integrated battery controller for the erection of 1- and 3-phase isolated

    supply systems. Without transformer including current sensitive residual current

    monitoring and tripping; including cooling/ventilation concept; single and three-phase

    feed in including modular extension; including 2 seperate MPP-tracker for seperate

    strings; multi-cluster operation. High efficiency, intelligent battery management to

    optimize battery lifetime, calculation of battery load, high overlad capacity; with

    integrated display and control unit; compatible to offered solar batteries; the inverter

    must be suitableand fully compatbile to the offered solar modules;

    Input (DC)

    maximum DC output at cosphi = 1

    max input voltage range 1,000 V

    MPP- input voltage range 360 800 V

    maximum input current 33 / 11 A

    nominal output at 230 V

    maximum AC appearent output

    Battery Input

    maximum DC output at cosphi = 1

    rated input voltage 48 V

    Input voltage range 41 V 63 V

    max. battery charging current 110 A

    DC rated charging current 90 A

    DC rated de-charging current 103 A

    Battery type gel battery

    battery capacity range 100 AH 10.000 Ah

    method of charge control

    IUoU-charge with automatic full

    charge and equalization charge

    Oputput (AC)

    Nominal AC voltage: 3 / N / PE 230 V / 415 V

    Nominal AC voltage range 160 V .. 280 V

    rated power frequency 50 Hz

    rated power frequency range (adjustable) 45 Hz 65 Hz

    Rated output power at nominal voltage and rated power frequency 25C / cosphi=1)

    peak AC power at rated voltage and rated frequency at 25C for 30 min / 5 min / 3 sec

    rated current

    peak current

    harmonic factor output voltage

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    18/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 17 -

    Standards

    GeneralIEC 62103; IEC 60521; IEC

    60721

    Conformity CE or equivalent

    General Data

    Dimensions (W/H/D) describe

    Weight describe

    Operating temperature range -25C +60C

    protection class (IEC 62103) I

    protection class of connection area (IEC 60529) 3K6

    Climatic category ( IEC 60721) IP54

    Features

    multifunction relay 2

    3-phase systems /parallel connection yes / yes

    integrated bypass

    multicluster operation yes

    calculation of charge condition / full / equalization charge yes / yes / yes

    integrated soft start yes

    generator support yes

    battery temperature sensor yes

    communication port, bluetooth yes / yesguarantee > 5 years

    certificates and approvals describe

    brand name and type name and model name describe

    assembly describe

    integrated graphic display yes

    suitable for in- and outdoor installation yes

    DC plug conncetors including DC load breaker yes

    number of parallel strings minimum 5

    Acce ssoires describe

    2 Solar ModulesSolar Modules with crystaline solar cells, of high reliability with guaranteed 0/+5Wp

    peak power classification; with IEC certificate; modul voltage, current and plug

    connection; c onnection must fit to the offered Inverters; frame out of anodized

    aluminium; frame with holow chamber profile and drainage opening; front made of

    special hardened, high t ransparent glass, antireflective coated; weather proofed

    terminal box at the rear; including necessary modul connectors made of flexible

    copper isolated cables with connectors

    Electric Data

    rated power at standard temperature conditions

    peak Power (Pmax)

    peak voltage (Vmax)

    peak sys tem voltage (VSmax)

    Peak current (Imax)

    short curcuit current (ISC)

    no load voltage (VOC)

    A/C-diagram

    temperature coefficient; voltage (V/C)

    temperature coefficient; power (%/C)

    nominal cell operation temperature (NOCT)

    U-I functions at 25C and other temperatures and radiation

    General Data

    minimum operational t emperature -40C +80C

    minimum ambient temperature -40C +45C

    Standards

    connection terminal DIN VDE 0126-5

    Wiring, plug connector EN 50521

    Modules generalIEC 61215; IEC 61730;IEC

    61701; IEC 61721; EN 50380

    Certificates

    Modules IEC 61215; IEC 61730

    test report by a certified and licensed laboratory IEC/IEC 17025

    product certification unit/authority acc. to EN 45011

    CE conformity (or equal) yes

    Guarantee

    product guarantee 5 years for product

    output guarantee 12 y ears,; minimum power output (% of nominal power) >90%

    output guarantee 25 y ears; minimum power output (in % of nominal power)

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    19/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 18 -

    3 Support StructuresSupport structures acc ording to attached drawing no1 as support for the offered solar

    modulesdescribe

    4 OPZV Solar batterymaintenance free sealed lead-acid gel battery; sulphuric acid as electrolyte stabilized

    as gel; including pole screws with isolated screw head and possibility to measure

    voltage; including necessary connectors made of flexible isolated copper suitable for

    maximum voltage and current; including end connectors with protection c over;

    environmental friendly and full recyc lable

    nominal voltage 2V

    Min imum capac it y: C10, @ T=20C: 3050Ah; C100, @ T=20C: 3540 A h 3050 A h / 3540 Ah

    Minimum Cycles at 80% / 50% Depth of Discharge (DoD): 1600 / 3000

    operational temperature (minimum, maximum, optimum)

    operation characteristic diagram

    charge limit voltage including temperature dependancy

    permissible c harge and -discharge current

    permissible discharge depth

    charge and discharge efficiency

    self discharge in % per month

    low voltage threshhold as function of disc harge current

    Protectionintegrated Overvoltage yes

    over current yes

    short circuit yes

    reverse polarity yes

    Standards

    General

    IEC 60896-21; IEC 61427 or

    similar

    conformity CE or similar

    Guarantee

    product guarantee 5 years

    cost free replacement at installation side in case the minimum output ratings fall shortyes

    Features

    Brand, Type, Model describe

    dimensions (L / W / H) describe

    modul dimensions (L / W / H) describe

    weigth describe

    characteristics of electrodes; construction, weave alloy describe

    display of battery voltage describe

    5 Batter ie supportfully isolated steel support suitable for the offered batteries; installation in strings per

    support; if required in two lay ersdescribe

    6 Documentations (for every component)description of component yes

    connection plans yes

    installation manual yes

    commissioning regulations and procedures yes

    operation manual yes

    maintenance manual yes

    failure analysis and proposals for measures to be undertaken yes

    complete documentation in English and Urdu langauage 5 hard copies and 2 soft copies

    7 After Sales Service

    service point in District including description of experience available at service point;

    services offered; available wear and spare partsdescribe

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    20/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 19 -

    Annex 4.1: System Report 5 households

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    21/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 20 -

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    22/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 21 -

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    23/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 22 -

    Battery maximum discharge power Inverter Output Power

    Battery max.

    discharge power

    Inverter Output Power

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    24/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 23 -

    Excess Power PV Power Generation

    Battery Charge Unmet Load

    PV Power

    Excess Power

    Battery Stateof Charge

    Unmet Load

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    25/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 24 -

    Annex 4.2: System Report 10 households

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    26/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 25 -

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    27/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 26 -

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    28/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 27 -

    Battery maximum discharge power Inverter Output Power

    Battery max.

    dischargepower

    Inverter OutputPower

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    29/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 28 -

    Excess Power PV Power Generation

    Battery Charge Unmet Load

    PV Power

    Excess Power

    Battery Stateof Charge

    Unmet Load

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    30/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 29 -

    Annex 4.3: System Report 15 households

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    31/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 30 -

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    32/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 31 -

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    33/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 32 -

    Battery maximum discharge power Inverter Output Power

    Battery max. discharge power

    InverterOutput Power

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    34/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 33 -

    Excess Power PV Power Generation

    PV Power

    Excess Power

    BatteryState ofCharge

    Unmet load

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    35/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 34 -

    Annex 4.4: System Report 20 households

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    36/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 35 -

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    37/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 36 -

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    38/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Hydropower Implementation Aspects - 37 -

    Battery maximum discharge power Inverter Output Power

    Excess Power PV Power Generation

    Battery max. discharge power

    Inverter OutputPower

  • 8/12/2019 V-4- Pv Home-draft 23-07-13_2

    39/39

    Development and Usage of Hydropower and Renewable Energies inKhyberPakhtunkhwa, Pakistan

    Technical Guidelines & ReportsVolume 4: Design of PV Community Systems

    Battery Charge Unmet Load

    Battery Stateof Charge

    Unmet Load

    PV Power

    Excess Power