MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the...

32
MITSUBISHI HEAVY INDUSTRIES, LTD. 16-5, KONAN 2-CHOME, MINATO-KU TOKYO, JAPAN September 11, 2008 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Attention: Mr. Jeffrey A. Ciocco Docket No. 52-021 MHI Ref: UAP-HF-08170 Subject: MHI's 2 nd Response-to NRC's Request for Additional Information on US-APWR Topical Report MUAP-07010-P, Non-LOCA Methodology Mitsubishi Heavy Industries, Ltd. ("MHI") transmits to the U.S. Nuclear Regulatory Commission ("NRC") the document entitled "MHI's 2 nd Response to NRC's Request for Additional Information on US-APWR Topical Report MUAP-07010-P, Non-LOCA Methodology." The enclosed materials provide MHI's remaining responses to the NRC's "Request for Additional Information ("RAI") on US-APWR Topical Report MUAP-07010-P, Non-LOCA Methodology," dated July 16, 2008. The first response was previously provided to the NRC by MHI letter UAP-HF-08141, dated August 22, 2008. In accordance with the agreement reached during the June 26, 2008 conference call, the remaining RAI responses (numbers 2.1-16, 3.2-2, 3.2-7, 3.2-10, and 5.5-2) are included in the enclosed document. As indicated in the enclosed material, this document contains information that MHI considers proprietary, and therefore should be withheld *from public disclosure pursuant to 10 C.F.R. § 2.390 (a)(4) as trade secrets and commercial or financial information which is privileged or confidential. A non-proprietary version of the document is also being submitted in this package (Enclosure 3). In the-non-proprietary version, the proprietary information, bracketed in the proprietary version, is replaced by the designation "[]". This letter includes a copy of the proprietary version of the RAI response (Enclosure 2), a copy of the non-proprietary version of the RAI response (Enclosure 3), and the Affidavit of Yoshiki Ogata (Enclosure 1) which identifies the reasons MHI respectfully requests that all material designated as "Proprietary" in Enclosure 2 be withheld from disclosure pursuant to 10 C.F.R. § 2.390 (a)(4). Please contact Dr. C. Keith Paulson, Senior Technical Manager, Mitsubishi Nuclear Energy Systems, Inc., if the NRC has questions concerning any aspect of this submittal. His contact information is provided below. Sincerely, Yoshik$Ogata General Manager-APWR Promoting Department Mitsubishi Heavy Industries, Ltd.

Transcript of MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the...

Page 1: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MITSUBISHI HEAVY INDUSTRIES, LTD.16-5, KONAN 2-CHOME, MINATO-KU

TOKYO, JAPAN

September 11, 2008

Document Control DeskU.S. Nuclear Regulatory CommissionWashington, DC 20555-0001

Attention: Mr. Jeffrey A. CioccoDocket No. 52-021

MHI Ref: UAP-HF-08170

Subject: MHI's 2 nd Response-to NRC's Request for Additional Information on US-APWRTopical Report MUAP-07010-P, Non-LOCA Methodology

Mitsubishi Heavy Industries, Ltd. ("MHI") transmits to the U.S. Nuclear Regulatory Commission("NRC") the document entitled "MHI's 2 nd Response to NRC's Request for AdditionalInformation on US-APWR Topical Report MUAP-07010-P, Non-LOCA Methodology." Theenclosed materials provide MHI's remaining responses to the NRC's "Request for AdditionalInformation ("RAI") on US-APWR Topical Report MUAP-07010-P, Non-LOCA Methodology,"dated July 16, 2008. The first response was previously provided to the NRC by MHI letterUAP-HF-08141, dated August 22, 2008. In accordance with the agreement reached during theJune 26, 2008 conference call, the remaining RAI responses (numbers 2.1-16, 3.2-2, 3.2-7,3.2-10, and 5.5-2) are included in the enclosed document.

As indicated in the enclosed material, this document contains information that MHI considersproprietary, and therefore should be withheld *from public disclosure pursuant to 10 C.F.R.§ 2.390 (a)(4) as trade secrets and commercial or financial information which is privileged orconfidential. A non-proprietary version of the document is also being submitted in this package(Enclosure 3). In the-non-proprietary version, the proprietary information, bracketed in theproprietary version, is replaced by the designation "[]".

This letter includes a copy of the proprietary version of the RAI response (Enclosure 2), a copyof the non-proprietary version of the RAI response (Enclosure 3), and the Affidavit of YoshikiOgata (Enclosure 1) which identifies the reasons MHI respectfully requests that all materialdesignated as "Proprietary" in Enclosure 2 be withheld from disclosure pursuant to 10 C.F.R.§ 2.390 (a)(4).

Please contact Dr. C. Keith Paulson, Senior Technical Manager, Mitsubishi Nuclear EnergySystems, Inc., if the NRC has questions concerning any aspect of this submittal. His contactinformation is provided below.

Sincerely,

Yoshik$OgataGeneral Manager-APWR Promoting DepartmentMitsubishi Heavy Industries, Ltd.

Page 2: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

Enclosures:

1. Affidavit of Yoshiki Ogata2. MHI's 2nd Response to NRC's Request for Additional Information on US-APWR Topical

Report M UAP-0701 O-P, Non-LOCA Methodology (proprietary)3. MHI's 2 nd Response to NRC's Request for Additional Information on US-APWR Topical

Report MUAP-0701 O-P, Non-LOCA Methodology (non-proprietary)

CC: J. A. CioccoC. K. Paulson

Contact Information

C. Keith Paulson, Senior Technical ManagerMitsubishi Nuclear Energy Systems, Inc.300 Oxford Drive, Suite 301.Monroeville, PA 15146E-mail: [email protected]: (412) 373-6466

Page 3: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

ENCLOSURE 1Docket No. 52-021

MHI Ref: UAP-HF-08170

MITSUBISHI HEAVY INDUSTRIES, LTD.

AFFIDAVIT

I, Yoshiki Ogata, being duly sworn according to law, depose and state as follows:

1. I am General Manager, APWR Promoting Department, of Mitsubishi Heavy Industries, Ltd.("MHI"), and have been delegated the function of reviewing MHI's US-APWRdocumentation to determine whether it contains information that should be withheld from

.disclosure. pursuant to 10 C.F.R. § 2.390 (a)(4) as trade secrets and commercial, orfinancial information which is privileged'or confidential.

2. In accordance with my responsibilities, 1 have reviewed the enclosed document entitled"MHI's 2nd Response to NRC's Request for Additional Information on US-APWR Topical

.Report MUAP-07010-P, Non-LOCA Methodology," dated September 2008, and havedetermined that the document contains proprietary information that should be withheldfrom public disclosure. Those pages containing proprietary information are identifiedwith the label "Proprietary" on the top of the page and the proprietary information hasbeen bracketed with an open and closed bracket as shown here "[ ]". The first page ofthe document indicates that all information identified as "Proprietary" should be withheldfrom public disclosure pursuant to 10 C.F.R. § 2.390 (a)(4).

3. The basis for holding the referenced information confidential is that it describes the uniquedesign of the safety analysis, developed by. MHI (the "MHI Information").

4. The MHI Information is not used in the exact form by any of MHI's competitors. Thisinformation was developed at significant cost to MHI, since it required the performance of

research and development and detailed design for its software and hardware extendingover several years. Therefore public disclosure of the materials would adversely affectMHI's competitive position.

5. The referenced information has in the past been, and will continue to be, held inconfidence by MHI and is always subject to suitable measures to protect it fromunauthorized use or disclosure.

6. The referenced information is not available in public sources and could not be gatheredreadily from other publicly available information.

7. The referenced information is being furnished to the Nuclear Regulatory Commission("NRC") in confidence and solely for the purpose of supporting the NRC staff's review ofMHI's application for certification of its US-APWR Standard Plant Design.

8. Public disclosure of the referenced information would assist competitors of MHI in theirdesign of new nuclear power plants without the costs or risks associated with the design-and testing of new systems'and components. Disclosure of the information identified asproprietary would therefore have negative impacts on the competitive position of MHI in

Page 4: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

the U.S. nuclear plant market.

I declare under penalty of perjury that the foregoing affidavit and the matters stated thereinare true and correct to the best of my knowledge, information, and-belief.

Executed on this 11th day of September, 2008.

Yoshiki Ogata,General Manager-APWR Promoting DepartmentMitsubishi Heavy Industries, LTD.

Page 5: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

Enclosure 3

UAP-HF-08170.Docket No. 52-021

September 2008

MHI's 2 nd Response to NRC's Request-for Additional Information onUS-APWR Topical Report MUAP-07010-P, Non-LOCA Methodology

(Non-Proprietary)

Page 6: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

RAI 2.1-16A reactor coolant pump model has been added to MARVEL during the evolution to MARVEL-M. Has this model been tested against pump vendor test data? If so, please provide thecomparisons.

ResponseThe reactor coolant pump (RCP) characteristics incorporated into MARVEL-M are based onthe RCP unit test data that MHI has performed. MHI has also compared the calculated coastdown curve with the test data for a 4-loop Japanese plant in order to confirm the validity of theMARVEL-M RCP model. Figures 2.1-16.1 and 2.1-16.2 compare the measured coast down4-loop plant data to the MARVEL-M calculation results. Figure 2.1-16.1 shows a test of a twopump coast down (Partial Loss of Forced Reactor Coolant Flow) and Figure 2.1-16.2 shows atest of a four pump coast down (Complete Loss of Forced Reactor Coolant Flow). Both thecalculations and the measurements were performed at hot zero power initial conditions. Ascan be seen from the figures, the calculated values from MARVEL-M show excellentagreement with the measured values. Therefore, the reactor coolant pump model inMARVEL-M is valid for both uniform and non-uniform RCS flow conditions.

Mitsubishi Heavy Industries, LTD.1

Page 7: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

Figure 2.1-16.1 RCS Flow Comparison between a Typical 4-Loop Plant and MARVEL-M(Partial Loss of Forced Reactor Coolant Flow)

Mitsubishi Heavy Industries, LTD.2

Page 8: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

Figure 2.1-16.2 RCS Flow Comparison between a Typical 4-Loop Plant and MARVEL-M(Complete Loss of Forced Reactor Coolant Flow)

Mitsubishi. Heavy Industries, LTD.3

Page 9: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (R0)Non-LOCA Methodology UAP-HF-08170-NP (RO)

RAI 3.2-2The TWINKLE code as approved for use by Westinghouse needs to be shown to provideacceptable results when used by MHI. This becomes more important when the code has alsobeen modified. The comparisons in Section 3.2.1 show reasonable agreement with ANC forreactor conditions of interest in rod ejection accident analysis. However, no information isgiven to show how well TWINKLE-M models steady state power and reactivity measurementsat an operating PWR, as well as how it models neutron kinetics. Please provide additionalinformation.which helps validate the code as used at MHI.

ResponseMHI was introduced to the TWINKLE code by Westinghouse and has been using TWINKLE-Min domestic licensing analyses for many years, as described in MUAP-07010 Section 2.2. Theadditional comparisons provided in this RAI response supplement the extensive verificationand validation activities already performed by MHI for the TWINKLE-M code.

Figures 3.2-2.1 and 3.2-2.2 compare the radial power distributions of two typical 3-loopoperating plants -to the TWINKLE-M calculations. These comparisons show good agreementand demonstrate the accuracy of the three-dimensional (3D) steady state calculation usingTWINKLE-M.

As a verification of the transient capability of TWINKLE-M, the OECD rod ejection 3D transientbenchmark problem was performed. This benchmark problem is designed to confirm theability of various kinetics code solution methods to give common core fuel burnup, crosssections, rod cluster control assembly (RCCA) macroscopic cross sections, fuel properties,and several core physics parameters important to transient calculations. Figures 3.2-2.3through 3.2-2.5 compare the results calculated using TWINKLE-M to the OECD referenceproblem solution for the case where one rod is ejected from the bottom of the core at hot zeropower initial conditions. These comparisons show good agreement between TWINKLE-M andthe reference solution, which demonstrates the validity of the neutron kinetics models used inthe TWINKLE-M code.

References:1. NEACRP-L-335(Revision 1), H. Finnemann and A. G. Galati, "NEACRP 3-D LWR Core

Transient Benchmark," Final Specifications, October 1991 (January 1992).2. NEA/NSC/DOC(93)25, H. Finnemann, H. BauerL A. Galati, and R. Martinelli, "Results of

LWR Core Transient Benchmarks," October 1993.3. Proc. Joint Int. Conf. Mathematical Methods and Supercomputing for Nuclear Applications,

Saratoga Springs, N.Y., American Nuclear Society, 1,302-313 (1997). M. P. Knight and P.Bryce, "Derivation of a refined PANTHER solution to the NEACRP PWR rod-electiontransients."

Mitsubishi Heavy Industries, LTD. 4

Page 10: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

Figure 3.2-2.1 Radial Power Distribution Comparison between aTypical 3-loop Operating Plant (Unit-A) and TWINKLE-M

Mitsubishi Heavy Industries, LTD.5

Page 11: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI .onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

Figure 3.2-2.2 Radial Power Distribution Comparison between aTypical 3-loop Operating Plant (Unit-B) and TWINKLE-M

Mitsubishi Heavy Industries, LTD.6

Page 12: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (R0)Non-LOCA Methodology UAP-HF-08170-NP (R0)

-I

Figure 3.2-2.3 Average Power FractionOne Rod Ejection at HZPComparison between TWINKLE-M and OECD Reference Solution

Mitsubishi Heavy Industries, LTD.7

Page 13: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (110)

Figure 3.2-2.4 Doppler Effective Fuel Temperature at Hot SpotOne Rod Ejection at HZPComparison between TWINKLE-M and OECD Reference Solution

Mitsubishi Heavy Industries, LTD.8

Page 14: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

J

Figure 3.2-2.5 Radial Power Distribution at Maximum PowerOne Rod Ejection at HZPComparison between TWINKLE-M and OECD Reference Solution

Mitsubishi Heavy Industries, LTD.9

Page 15: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

RAI 3.2-7Finite difference codes were originally meant to have mesh sizes on the order of a transportmfp. The mesh spacing used in the comparisons to ANC is 11 cm in all directions. In order tounderstand why the coarse mesh 2x2 results are in agreement with the 4x4 results pleaseaddress the following: Is the ejected rod worth calculated for each case (Table 3.2.2-1) or isthe worth for one case fixed somehow to be in agreement (within 5 pcm) of the other case?What is the maximum fuel enthalpy (or temperature) for the two cases? It is assumed that themaximum hot channel factor is for an entire assembly. Please provide a comparison ofadditional hot channel factors (at a minimum for the assemblies surrounding the ejected rod).What would be the result if the axial mesh were also changed?

Response

1. Eiected Rod WorthThe ejected control rod worth (in MUAP-07010-P Table 3.2.2-1) is calculated for both the 2x2mesh case and the 4x4 mesh case without any adjustment. These values are almost identicalbecause the same cross-section data is used and the power distribution for each case isadjusted to agree with the power distribution of the static design code (ANC). Note that for thesafety analysis in Chapter 15 of the Design Control Document, the ejected control rod worth isadjusted to the design limit determined by the ANC calculation because this parameter iscritical for the rod ejection analysis and therefore should be conservative. The comparison ofthe nuclear power transient for the two mesh sizes shown in Figure 3.2.2-1 of MUAP-07010-Pwould be closer to each other if such an adjustment were performed for those cases.

2. Fuel TemperatureThe Doppler effective fuel temperature at the hot spot for the 2x2 and 4x4 mesh calculationsgenerally agree with each other, as shown in Figure 3.2-7.1, although the 2x2 mesh solutionconservatively results in a slightly higher maximum effective fuel temperature.

3. Hot Channel FactorsThe maximum hot channel factor is calculated for a single mesh. Figures 3.2-7.2 through3.2-7.5 show the time-varying assembly-wise radial power distribution at the axial height of FQfor the RCCA ejection transient for the 2x2 and 4x4 mesh calculations. This sequence offigures indicates that the power transient in assemblies around the ejected rod is in goodagreement between the 2x2 and 4x4 mesh transient calculations.

4. Axial Mesh SensitivityA sensitivity study analysis was performed using(L Jin the axial direction in the activecore region compared to the[ ]that were utilized in the cases shown in Section 3.2.2 ofMUAP-0701 0-P. For these comparisons, the mesh division in the radial direction is 2x2 meshper assembly, unless* otherwise noted. The results of the axial mesh division sensitivity studyare shown in Table 3.2-7.1 and Figure 3.2-7.6 throughr Figure Q.2-7.8. Figure 3 2-7.6compares the average axial power distribution for thel Jcalculation, the [ ]calculation, and the ANC calculation for three dferent c~re conditions. The comparisons,indicate that the axial power distributiors of the[ j calculations are generally closer tothe ANC calculations than thel ' Jcalculations, buf that the differences are not significant.Note that the axial power distributions shown in Figure 3.2-7.6 are calculated by TWINKLE-Mwithout any adjustment of the diffusion coefficients in the reflector region.

-The comparisons shown in Figure 3.2-7.7 and Figure 3.2-7.8 indicate that the difference

Mitsubishi Heavy Industries, LTD.10

Page 16: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

between the[ )calculations has little impact on the nuclear power transient.Note that the diffusion coefficients in the reflector for both cases are adjusted for the transientcalculation so that the .axial power distribution matches the ANC power distribution,.as was shown in Figuye 3.2.1-5 of M L4AP-070 10-P. The difference in the nuclear powergradient between thel jcases is caused by the difference in the ejected rodworth, which is shown in Table 3.2-7.1.

In summary, the[ division in the axial direction is sufficient for the non-LOCA safetyanalyses of the US-APWR.

Mitsubishi Heavy.Industries, LTD.11

Page 17: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

Table 3.2-7.1 Calculation Conditions and Results of the RCCA Ejection

Initial power (fraction of nominal) 10-9Average coolant temperature (OF) 557 Same as leftRCS pressure (psia) 2250

Ejected worth (pcm) 600 594

Delayed neutron fraction (%) 0.44 Same as left

Neutron lifetime (microseconds) 8.0 Same as left

Maximum core power (fraction of nominal) 3.12 2.97

Maximum hot channel factor 27.5 27.2

Mitsubishi Heavy Industries, LTD.12

Page 18: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (R0)

Non-LOCA Methodology UAP-HF-081 70-NP (RO)

C)4.

E

4.

.)

Cu

aw0.F.0

Figure 3.2-7.1

0.5

Time (s)Doppler Effective Fuel Temperature at Hot SpotRCCA Ejection at EOC HZPComparison between 2x2 and 4x4 Mesh in TWINKLE-M

Mitsubishi Heavy Industries, LTD.13

Page 19: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

Figure 3.2-7.2 Assembly-wise Radial Power Distribution at Axial Height of FQ,RCCA Ejection at 0.0 second, EOC HZP in TWINKLE-M

Mitsubishi Heavy Industries, LTD.14

Page 20: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

r-

Figure 3.2-7.3 Assembly-wise Radial Power Distribution at Axial Height of FQ,RCCA Ejection at 0.1 second, EOC HZP in TWINKLE-M

Mitsubishi Heavy Industries, LTD.15

Page 21: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

J

Figure 3.2-7.4 Assembly-wise Radial Power Distribution at Axial Height of FQ,RCCA Ejection at 0.2 second, EOC HZP in TWINKLE-M

Mitsubishi Heavy Industries, LTD.16

Page 22: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

Figure 3.2-7.5 Assembly-wise Radial Power Distribution at Axial Height of FQ,RCCA Ejection at 0.3 second, EOC HZP in TWINKLE-M

Mitsubishi Heavy Industries, LTD.17

Page 23: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (R0)Non-LOCA Methodology UAP-HF-08170-NP (R0)

1:0 . 1.0 . 1.0

0.9 0.9 09

0.8 0.8 0. -

0.7 0.7 0.7

0.6 0.6 0.6

0.5 0.5 0.5

0.4 0.4 0.4

0.3 0.3 0.3

0.2 AN 0.2 F 0.2

0.1 0.1 0.1

0.0 0.0 0.00 I 2 0 1 2 3 4 0 1 2 3 4

Relative Power Relative Power Relative Power

Case 1 Case 2 Case 3BOC HFP EOC HZP EOC HZP

All ReCAs Out RCCA at Insertion limit One RCCA Ejected

Figure 3.2-7.6 Average Axial Power DistributionComparison between ANC and Axial Mesh Sensitivity Cases(No adjustment of the diffusion coefficient of the reflector region)

Mitsubishi Heavy Industries, LTD.18

Page 24: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (R0)

E0

0r-

0

a.

z

10 1

10 0

10-1

10"2

10-3

10-4

1 05

10-6

10-7

10-8

100.00.1 0.2 0.3

Time (second)

0.4 0.5

Figure 3.2-7.7

0

U-

Figure 3.2-7.8,

Nuclear Power, RCCA Ejection at EOC HZPComparison between ANC and Axial Mesh Sensitivity Cases

0.5

Time (second)

Hot Channel Factor, RCCA Ejection at EOC HZPComparison between ANC and Axial Mesh Sensitivity Cases

Mitsubishi Heavy Industries, LTD.19

Page 25: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

RAI 3.2-10Please provide discussion of the effect of axial mesh size on the axial power distribution.

ResponseSee the response to RAI 3.2-7.

Mitsubishi Heavy Industries, LTD.20

Page 26: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

RAI 5.5-2Arethe calculated results for the feedwater system pipe break sensitive to the assumed mixingfactors, and have any sensitivity calculations been performed? If so, please provide thecomparisons.

ResponseThe extent of reactor plenum inlet mixing has an effect on events characterized by non-uniform loop behavior, in particular, events resulting in the heatup or cooldown of a singlereactor coolant loop. Among the events that result in a non-uniform loop heatup, thefeedwater system pipe break event is the most extreme. A sensitivity study was performed toconfirm the effect of the assumed mixing factors for this event. Two different cases wereanalyzed: the first case assumes a vessel inlet mixing factor that is 10% less than the basecase (Case 1) and the second case assumes a vessel inlet mixing factor that is 10% morethan the base case (Case 2). The results of the sensitivity study of the vessel inlet mixingfactor for the feedwater system pipe break are shown in Figure 5.5-2.1 through Figure 5.5-2.12.The two cases with modified mixing factors are compared to the base case for variousparameters. For these parameters, the effect of the change in the inlet mixing factor isnegligibly small. These results demonstrate that the effects of changes to the vessel inletmixing factor are small for the feedwater system pipe break event.

Mitsubishi Heavy Industries, LTD.21

Page 27: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (R0)Non-LOCA Methodology UAP-HF-08170-NP (RO)

1.2

cc

E

0.4-

0C0C--S

4-UM

a0

090Y

1.0

0.8

0.6F

Base case---- Case 1

Case2

0.4

0.2

n II . . .. . . . . . . .. . . .

100 101 102 103 104

Figure 5.5-2.1

3000

cu 2800

(D)

•2600-

U3)

S24000a-Uof 2200

2000 '100

Figure 5.5-2.2

Time (seconds)Reactor Power versus TimeFeedwater System Pipe Break

101 102 103

Time (seconds)RCP Outlet Pressure versus TimeFeedwater System Pipe Break

104

Mitsubishi Heavy Industries, LTD.22

Page 28: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

/-l.t It II I£.JI JI Jr

3*JNNfl

a,

3500

3000E

0 2500

-- Base case-.-.-. Case 1

TalrsrzCase 2Total Pressurizer Volume

......................................................................

I-

N

2000F

1500

1000-

500 I

U10 0

101 102 10 3 1o4

Figure 5.5-2.3Time (seconds)

Pressurizer Water Volume versus TimeFeedwater System Pipe Break

t r~ r~CO

(D0,

CO

(D

CO

0a,

a,L4-

N

C/)C/)

S.-

•J t.# %#

400k

300-

Base case.---- Case 1

Case2

200F

100r

I.'

100 101 10 2 103 104

Figure 5.5-2.4Time (seconds)

Pressurizer Safety Valve Flow Rate versus TimeFeedwater System Pipe Break

Mitsubishi Heavy Industries, LTD.23

Page 29: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

U)L..

(D

0.

E(D1-U)

(D

L.U)

C/)

10 101 102 103 104

Figure 5.5-2.5Time (seconds)

RCS Average Temperature versus TimeFeedwater System Pipe Break

1.21

cc

0CU

t-0

Ca)0CU

0HL

00-

1'0

0.8

0.6

-- Base case---- Case 1- - Case 2

0.4

0.2

r~ I~I

100

Figure 5.5-2.6

101 102 103 104

Time (seconds)RCS Total Flow versus TimeFeedwater System Pipe Break

Mitsubishi Heavy Industries, LTD.24

Page 30: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

LL

CUa.)Q.

Ea)I--

10o 101 102 103 104

Figure 5.5-2.7

700

650LL0

600LC

E0)I-

Time (seconds)Temperature of Faulted Loop versus TimeFeedwater System Pipe Break

10o 101 102 103 104

Figure 5.5-2.8Time (seconds)

Temperature of Intact Loop without EFW versus TimeFeedwater System Pipe Break

Mitsubishi Heavy Industries, LTD.25

Page 31: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

700

650LL

Q.

EI-

600

Saturati~in ii• •

C old leg

Base case.... Case 1

Case2

550

500-

100 101 102 103 104

Figure 5.5-2.9Time (seconds)

Temperature of Intact Loop with EFW versus TimeFeedwater System Pipe Break

1400Intact SG

cln0r

U)5

CL,

a-

0

Ea)

U)U)CD

1200[

1000

800-

-- Base case.. .Case 1

•Case 2

Intact SG

600-

400 I

200 kFaulted SG

0100 101 102 103 104

Figure 5.5-2.10Time (seconds)

Steam Generator Pressure versus TimeFeedwater System Pipe Break

Mitsubishi Heavy Industries, LTD.26

Page 32: MITSUBISHI HEAVY INDUSTRIES, LTD. · MHI Ref: UAP-HF-08170 Subject: ... calculations and the measurements were performed at hot zero power initial conditions. As can be seen from

MHI's Response to NRC's RAI onTopical Report MUAP-07010-NP (RO)Non-LOCA Methodology UAP-HF-08170-NP (RO)

300000

(D,

0

T

C-

(D

E

C/)

250000k

200000

150000

Base case.... Case 1I ..Case 2 I '

Intact SGwith EFW

Faulted SG wIntact SG. . .. .... . .. 1 .. . . "• ._., without EFW

100000

5000OF

0100 101 102 103

Figure 5.5-2.11Time (seconds)

Steam Generator Water Mass versus TimeFeedwater System Pipe Break

I UUUU1o

(o

a,_o

0

Lu

m

a)

aUt"-

a)

._1

a)LL

8000-

6000-

Base as I.. .Case1

Case 2

4000k

20001

II...................... .........".........' . . ..

100

Figure 5.5-2.12

101 102 103 104

Time (seconds)Feedwater Line Break Flow Rate versus TimeFeedwater System Pipe Break

Mitsubishi Heavy Industries, LTD.27