1999 Shuttle Ar

68
SPACE SHUTTLE P ROGRAM 1999 ANNUAL REPORT

Transcript of 1999 Shuttle Ar

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 1/68

SPACE SHUTTLE PROGRAM

1999 ANNUAL REPORT

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 2/68

Fly Safely Meet theManifest

ImproveMission

Supportability

Improvethe

System

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 3/68

CONTENTS

S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

General In format ionPART 1

Message from theProgram Manager .................1

SSP Goals .........................2

Space ShuttleProgram Major Sites ...............3

Space ShuttleFlights to Date ...................4

Space ShuttleHardware Flow .................5

Organization andPersonnel ..........................6

Program Safety ..................7

Resource Management .......8

Space Flight Operations Contract ...9

Shuttle Development .............111

Mission Summaries .............14

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 4/68

1999 was a productive and challenging year forthe Space Shuttle Program (SSP). We have continued tostrive to meet our Program goals to fly safely, to meetthe manifest, to improve mission supportability, and toimprove the system. We accomplished four safe andsuccessful missions. On STS-95, a research flight, wereturned John Glenn to space and obtained keyscientific data on the similarities between the effects ofmicrogravity and the aging process. We successfullylaunched the first and second flights of the InternationalSpace Station (ISS), beginninga new era in space exploration.We deployed the ChandraObservatory, the world’s mostpowerful X-ray telescope, on amission led by the first female

Shuttle commander.We delivered the 100thExternal Tank (ET); had the100th flight of the solid rocketbooster (SRB); and look forwardto the 100th Space Shuttle flightin mid 2000. Our most experi-enced Orbiter, the Space ShuttleColumbia, completed its 26th spaceflight and has beenferried to Palmdale, California, for major modifications,while Space Shuttle Atlantis completed its major modifi-

cation in 1999, outfitted with a newly designed glasscockpit.

The SSP will always maintain the highest vigilancetoward safety of flight. Therefore, improving the safetyand reliability of our flight systems is the highest priority.To accomplish this, we are exploring: the use ofElectric Auxiliary Power Units (EAPUs) to eliminate thehazards associated with existing hydrazine APUs; theuse of a Space Shuttle Main Engine (SSME) AdvancedHealth Monitoring System to enable real-time vibra-tional and optical plume monitoring; and more durablethermal protection to reduce damage in critical areas.We are continuing to aggressively identify improve-ments in the propulsion systems that result in increasedreliability and safety.

We continue to look to a bright future. During thispast year we continued to identify and implementupgrades to the Shuttle systems that will enable us tocontinue to safely fly the Shuttle well into the next

millennium. Up-to-date ground support facilities arekey to this plan. We supported plans to develop anext-generation spacecraft, and continue to look at newways of developing hardware to shorten the develop-ment cycle without compromising safety.

The SSP continues to make great strides in improv-ing safety for all of our employees. We have seen adecrease in safety incidents in our ground facilities andan increase in the overall safety awareness across theProgram.

Reinvention is a key activity aswe continue to improve the sys-tem, implementing efficienciesthat not only make the Programbetter but result in lower operat-ing costs. We have embarked

on a path to further reduce theflight preparation template,allowing greater flexibility tofuture Space Shuttle customers.Efficiencies in processing andvehicle turnaround will continueto be aggressively pursued.

A Space Shuttle ProgramCouncil has been established, composed of senior levelproject and element managers, to address criticalprogrammatic issues, develop strategy, and plan for

the future. Additionally, a Chief Engineer’s Council wasformed to increase our focus on manufacturing, produc-tion, and process control. We conducted two programmanager’s reviews where the entire NASA and con-tractor team focused on safety and on process control.

Our personnel continued to remain involved incommunity education and outreach activities byparticipating in Open House, Inspection Day,Space Camp Exhibits, Engineering Week, andstudent mentoring.

Throughout the SSP it is evident that

the key to success lies in our people. It is the talentand dedication of the Space Shuttle Team that hasenabled us to be so successful in the past, and willserve us well into the future. The accomplishmentsdescribed in this report are their accomplishments,and it is because of their commitment to excellencethat we can proudly say, ”We’re ready to launch intothe 21st century.” y

Message from the Program Manager: 

S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

1

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 5/68

2S PACE SH U T T L E P RO GRAM 1999 AN N U A L RE PO RT2

Space Shuttle Program Goals 

The Program goals are derived from both the mission ofNASA and the Human Exploration and Development ofSpace (HEDS) Enterprise. The SSP’s four goals providethe foundation for operating the Program.

FLY SAFELY is the SSP’s number one goal! Flying safe-ly is paramount above anything else that is accom-plished. This is attained through a combination of reli-able hardware and an excellent team, and by findingproblems before they occur. The commitment to achievethis goal is tied directly to the unique, human factor ofour mission. Safety aspects include safety of the public,the flight crews, the workers, and the assets.

MEET THE MANIFEST encompasses the challenge tofly on schedule, achieve 100 percent mission success,

and provide the flexibility and responsiveness to mani-fest and mission problems.

IMPROVE MISSION SUPPORTABILITY focuses onmanifest flexibility and responsibilities, customer satisfac-tion and responsiveness, and hardware availability.

IMPROVE THE SYSTEM emphasizes reinvention,exploration, and quantum leaps. Making the systembetter will, in turn, reduce costs. This goal includesimproving the support and the flight system.

THE STRENGTH OF THE SPACE SHUTTLEPROGRAM IS THE TEAM.

IT IS ESSENTIAL FOR THE SUCCESS OF THEPROGRAM THAT THE TEAM FOCUSES ONTHE SAME GOALS.

NASA Mission:To explore, use, and enable the development of

space for human enterprise

SSP GOALS• FLY SAFELY

• MEET THE MANIFEST• IMPROVE MISSION SUPPORTABILITY

• IMPROVE THE SYSTEM

HEDS Goal:To enable humans to live and work

permanently in space

HEDS Objectives:Provide safe, affordable, and improved

assess to space

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 6/68

3S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Space Shuttle Program

ReusableSolid Rocket Motor

Cordant Technologies – Thiokol Propulsion

Brigham City, Utah

 Alternate Landing SiteEdwards AFB,CA

Space ShuttleProgram Office• Vehicle Engineering• Systems Intergration•Mission Operations

 Johnson Space Center,TX

External TankLockheed Martin

Michoud Assembly FacilityNew Orleans, LA

SSME TestStennis Space Center

Bay St. Louis, MS

 Alternate TurbopumpsPratt & Whitney

West Palm Beach, FL

Solid Rocket Booster& Intergration

United States Alliance/USBIKennedy Space Center, FL

Kennedy Space CenteLaunch & Landing

Kennedy Space Center, FL

NASA HeadquarteWashington, DC

Palmdale,CABoeing ReuseableSpace System (BRSS)

Downey, CABRSS

Huntington Beach, CABRSS

Marshall Space Flight CenterSpace Shuttle Projects Office

Huntsville, AL

• SSME • SRB•ET •RSRM

Space Shuttle Program Major Sites

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 7/68

4S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Shuttle Flights to Date 

95 Total Flights70 Since Return to Flight

   N  u  m   b  e  r  o   f   F   l   i  g   h   t  s

93 88 12/04/98 –12/15/9889 89 1/22/98 – 1/31/9877 77 5/19/96 – 5/29/96

74 72 1/11/96 – 1/20/96

71 69 9/07/95 – 9/18/95

68 67 3/02/95 – 3/18/9565 68 9/30/94 – 10/11/9462 59 4/09/94 – 4/20/94

59 61 12/02/93 – 12/13/9356 57 6/21/93 – 7/01/9353 54 1/13/93 – 1/19/9350 47 9/12/92 – 9/20/92

47 49 5/07/92 – 5/16/92

EndeavourOV–105

Legend

Flt. STS-XX Launch – LandingNo. No. Date Date

After 51-LBefore 51-L(Flight-25)

30

28

26

2422

20

18

16

14

12

10

8

6

4

2

0

25 51–L 1/28/86

22 61–A 10/30/85–11/06/85

19 51–F 7/29/85 – 8/06/8517 51–B 4/29/85 – 5/06/8513 41–G 10/05/84 – 10/13/8411 41–C 4/06/84 – 4/13/8410 41–B 2/03/84 – 2/11/848 8 8/30/83 – 9/05/837 7 6/18/83 – 6/24/836 6 4/04/83 – 4/09/83

ChallengerOV–099

95 93 7/23/99 – 7/27/9990 90 4/17/98 – 5/03/98

88 87 11/19/97 – 12/05/9785 94 7/01/97 – 7/17/9783 83 4/04/97 – 4/08/97

80 80 11/19/96 – 12/07/96

78 78 6/20/96 – 7/07/9675 75 2/22/96 – 3/09/96

72 73 10/20/95 –11/05/9563 65 7/08/94 –7/23/9461 62 3/04/94 – 3/18/9458 58 10/18/93 – 11/01/93

55 55 4/26/93 – 5/06/ 9351 52 10/22/92 – 11/01/92

48 50 6/25/92 – 7/09/9241 40 6/05/91 – 6/14/9138 35 12/02/90 – 12/10/90

33 32 1/09/90 – 1/20/90

30 28 8/08/89 – 8/13/8924 61-C 1/12/86 – 1/18/869 41-C 1/28/83 – 12/08/835 5 11/11/82 – 11/16/82

4 4 6/27/82 – 7/04/823 3 3/22/82 – 3/30/822 2 11/12/81 – 11/14/811 1 4/12/81 – 4/14/81

ColumbiaOV-102

94 96 5/27/99 – 6/06/9992 95 10/29/98 – 11/07/98

91 91 6/02/97 – 6/12/9786 85 8/07/97 – 8/19/9782 82 2/11/97 – 2/21/97

70 70 7/13/95 – 7/22/95

67 63 2/03/95 – 2/11/9664 64 9/09/94 – 9/20/94

60 60 2/03/94 – 2/11/9457 51 9/12/93 – 9/22/9354 56 4/08/93 – 4/17/9352 53 12/02/92 – 12/09/92

45 42 1/22/92 – 1/30/9243 48 9/12/91 – 9/18/91

40 39 4/28/91 – 5/06/9136 41 10/06/90 – 10/10/9035 31 4/24/90 – 4/29/90

32 33 11/22/89 – 11/27/89

28 29 3/13/89 – 3/18/8926 26 9/29/88 – 10/03/8820 51-I 8/27/85 – 9/03/8518 51-G 6/17/85– 6/24/85

16 51-D 4/12/85 – 4/18/8515 51-C 1/24/85 – 1/27/8514 51-A 11/07/84 – 11/15/8412 41-D 8/30/84 – 9/04/84

DiscoveryOV-103

87 86 9/25/97 – 10/06/9784 84 5/15/97 – 5/24/97

81 81 1/12/97 – 1/22/9779 79 9/16/96 – 9/26/96

76 76 3/22/96 – 3/31/96

73 74 11/12/95 – 11/20/9569 71 6/27/95 – 7/07/9566 66 11/03/94 – 11/24/9449 46 7/31/92 – 8/08/92

46 45 3/24/92 – 4/02/9244 44 11/24/91 – 12/02/9142 43 8/02/91 – 8/11/91

39 37 4/05/91 – 4/11/9137 38 11/15/90 – 11/20/9034 36 2/28/90 – 3/04/9031 34 10/18/89 – 10/23/8929 30 5/04/89 – 5/08/8927 27 12/02/88 – 12/06/8823 61-B 11/26/85 – 12/03/8544 51-J 10/03/85 – 10/07/85

 AtlantisOV–104

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 8/68

Space Shuttle Hardware Flow 

5S PACE SHUTTLE P RO GRAM 1999 AN N U A L RE PO RT

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 9/68

6S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Organization and Personnel 

RONALD D. DITTEMORE, MANAGERSPACE SHUTTLE PROGRAM

Donald R. McMonagle, Manager

Launch Integration (KSC)

 William H. Gerstenmaier, Manager

Space Shuttle ProgramIntegration

 WilliamJ. Harris, Manager

Space Shuttle ProgramSafety and Mission Assurance

Elric McHenry, Manager

Space Shuttle ProgramDevelopment

M. D. Erminger, ManagerSpace Shuttle SR & QA

Office

 J. C. Boykin, Assistant ManagerSpace Flight OperationsContract (SFOC) COTR

D. A. Schaller, ManagerSpace Shuttle

Administrative Office

R. H. Heselmeyer, ManagerSpace Shuttle

Management Integration Office

 J. B. Costello, ManagerSpace Shuttle

Business Office

R. L. Segert, ManagerSpace Shuttle KSCIntegration Office

 A. A. McCool, ManagerSpace Shuttle

Projects Office (MSFC)

R. M. Swalin, ManagerSpace Shuttle

Customer and FlightIntegration Office

R. R. Roe, Jr., ManagerSpace Shuttle

Vehicle Engineering Office

Flight ManagersPayload

integration

Space ShuttleHeadquarters

Office

L. D. Austin, ManagerSpace Shuttle

Systems Integration Office

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 10/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 11/68

8S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

The SSP achievedsignificant costreductions since

1992. Costs are almost40% lower relative to thebuying power of a dollar in

1992. Program efficienciesand consolidations haveallowed 38% reduction ofthe contractor workforce.Civil serviceworkforcehas beenreduced50% since1992. Thefigures graphically depictthese substantial reductions.

While saving the taxpayersbillions of dollars, the SpaceShuttle Program has main-tained an enviable record ofsafe and on time launches.The Space Shuttle Programcosts were below the budgetagain in FY 1999; the first

 year that theProgram hasspent under

$3 billionsince earlydevelopmentdays. y

TotalProgram

Contractor Workforce

TotalBudget

FY92 $’s

TotalProgram

Civil Service Workforce

1999 Business Management 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 12/68

Space Flight Operations Contract 

9S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Background

The Space Flight Operations Contract (SFOC) is complet-ing its third year of successful performance since beingawarded to USA under a sole source determination bythe NASA Administrator. As a joint venture of Lockheed-Martin and Boeing, SFOC was initially formed through theconsolidation of 12 contracts previously performed by oneof these parent companies. The SFOC is a completion-form, performance-based, cost-plus incentive fee/awardfee contract. Included in the implementation of this consoli-dation of contracts is the transition of additional responsibil-ities and levels of accountability for the contractor asNASA strives to reduce the oversight of routine operations

and moves towards a role of insight. Fifteen other contractswere targeted for transition as the successof SFOC wasdemonstrated, and several of these were transitioned in thislast year. Overall, and as evidenced in the other portionsof this annual report where the functional areas aredescribed, USA has done a good job of consolidatingthe numerous contracts and continuing the high levels ofperformance as had been experienced under the previousindividual contracts.

Successful Performance of the Contract Requirements

SFOC technical requirements emphasize insight byNASA rather than oversight in the performance of theday-to-day, routine operations and production. Over thislast year, USA has continued to define and stabilize itsmanagement structure and its goals and objectives, andcontinued increases in its award fee evaluations demon-strate a very good level of satisfaction by NASA man-agement with its progress. Horizontal integration, inareas like business systems and functional areas likelogistics, continues to evolve and represents the realvalue of the consolidation of the contracts. While theShuttle manifest for this past year was limited by eventsoutside the control of SFOC, preparations and realtime mission execution by USA was excellent for thosemissions we were able to execute. Re-planning efforts tobest accommodate the ISS assembly manifest and theaddition of an expedited Hubble Space Telescope (HST)repair mission have demonstrated both commitment andflexibility on USA’s part, and continue to be a major taskfor both NASA and the contractor.

Basic Period of Performance: 10/1/96 to 9/30/02Original Contract Value: $ 6.949 BillionCurrent Contract Value: $8.4+ Billion

Phase II

Contract modifications this year have expanded the origi-nal scope to include the significant additions of the SRB,Primary Flight Software, and the Flight Equipment Process-ing contracts. These contracts were all incorporated intoSFOC in July 1998, and the transitions were handled verysmoothly, with high capture rates of the incumbent employ-ees, and no measurable functional disruption of the work inany of these areas. A decision to delay the transition of theET Project into SFOC in October of this year was made totake into account the expendable launch vehicle broadarea review and potential impacts on SSP processes andprocedures. The revised transition is projected for July of

FY 2000. Further transitions (the SSME and Reusable SolidRocket Motor (RSRM), or efforts) have also been delayedfor additional assessment, with July 2001 being targetedat this time.

Contract Administration Changes

The level-of-effort portion of SFOC, originally used toaccommodate the dynamic support requirements forthe ISS Program Office, has been recently converted tocompletion-form content in a mix of program provisioningand incentive requirements. The result of this conversion is

that the complete SFOC scope is now in completion-formformat.

A value engineering change proposal clause wasrecently developed and added to the contract. Thisclause provides additional incentives for USA to imple-ment cost improvements and efficiencies that reflect costpayback beyond the current contract end date ofSeptember 2002. Previously, the limited opportunity forrealizing a return on the implementation costs of suchactions could have resulted in USA business decisions tonot implement such improvements. This contract changewill better enable USA to continue developing initiativesthat provide benefits to the Program past the current con-tract period of performance.

A NASA and USA Change Process Improvement Teamactivity was completed this year with the development andimplementation of improved processes for the acquisitionand contract change management needs of SFOC. Theteam developed an approach based upon multidisciplinedpartnering whereby joint NASA and contractor experts

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 13/68

10S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Space Flight Operations Contract 

develop program requirements and determine thenecessary resources to support those requirements. This

new process reduced the number of approvals andconcurrences required for processing a change and hasresulted in significant improvements in the contractmanagement metrics for SFOC. The average time to definea change on SFOC has been reduced by one third (fromover 180 days to only 111 days) and continues todecrease. This reduces the change backlog and eliminatesmany potential proposal and re-proposal requirementswhich historically add costs and tie up manpowerassociated with such actions.

Performance Metrics

During FY99, USA has successfully received all of theperformance fee in conjunction with the four Shuttleflights. The metrics were established as an objectivemeasurement against specific criteria for each flight.

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 14/68

11S PACE SHUTTLE P RO GRAM 1999 AN N U A L RE PO RT

Space Shuttle Upgrade, Strategic Plan

T

he Space Shuttle Orbiter was designed for aservice life of 100 missions. Even with anticipat-

ed increases to the flight rate of today, theservice life of the Space Shuttle will extend well intothe next century. To ensure its continued viability, sys-tem upgrades will be needed to improve safety,avoid obsolescence problems, meet the manifest,improve supportability, and improve the overall sys-tem. The Space Shuttle Program Development Office(SSPDO) is currently developing a strategic and pro-active Upgrade Program that will keep the Shuttleflying safely and efficiently to 2012 and beyond,tomeet agency commitments and goals for humanaccess to space.

The Upgrade Program’s primary goal is to improvecrew flight safety and situational awareness, protectpeople both during flight and on the ground, andincrease the overall reliability of the Shuttle system. Toaccomplish this, a multi-Center, multi-contractor teamcarried out an in-depth assessment of safety-relatedupgrade candidates submitted by each SSP element.The upgrade portfolio was presented to the NASAAdministrator and the Office of Budget Management tosecure funding for the safety upgrades.

The portfolio of safety upgrades presented to theAdministrator includes: an EAPU which will eliminate

hazards due to hydrazine leakage or fires; an SSMEAdvanced Heath Monitoring System which will be capa-ble of real-time vibration monitoring and optical plumemonitoring; avionics and cockpit upgrades which willimprove crew situational awareness during routine oper-ations and contingency modes; and more durable ther-mal protection which will reduce damage in criticalareas. In addition to the flight hardware upgrades, sev-eral studies were also proposed. These studies includeevaluating crew escape options, evaluating changes tothe Main Landing Gear tires, and evaluating methods to

improve safety and efficiency of the Self-ContainedAtmospheric Protection Ensemble suits used duringhazardous ground operations.

The candidate safety upgrades were evaluated andprioritized using a set of metrics established by the multi-Center, multi-contractor team. To determine the effect ofeach upgrade on the overall loss of vehicle and loss ofcrew risk of the Shuttle, a probabilistic risk assessment wasperformed for each upgrade candidate. The following

chart illustrates the loss of vehicle risk for the ascentphase of the mission.

After implementing the Phase I upgrades, the ascentloss of vehicle risk decreased from 1 in 248 to 1 in 483.The Phase I upgrades included the new Block II SSMElarge throat main combustion chamber and high-pressureturbo pumps, the Super Lightweight ET (SLWT), and theOrbiter Multifunction Electronic Display Subsystem(MEDS) cockpit upgrade. Implementing the current safe-

ty upgrade portfolio would further decrease the loss ofvehicle risk to 1 in 735.

In parallel to developing a safety upgrades portfolio,SSPDO is also evaluating upgrades that will significantlyreduce supportability problems and combat obsolescence.A multi-Center, multi-contractor team is currently assessingand refining the SSP’s supportability and obsolescenceforecasts for flight hardware and ground infrastructure.The team’s major focus will be on determining near-termvulnerabilities and hazards, with a minor focus on strategiclong-term investments. A plan outlining the high-priority

supportability and obsolescence issues and the fundingrequirements necessary to mitigate substantialsupportability threats to the manifest through 2012 willbe presented to the NASA Administrator in FY2000.

The primary goal of the SSPDO is to ensure that theShuttle be the safest and most capable human-ratedspacecraft possible. Upgrades that support this goal andthe goals and objectives of the Shuttle Program will bethe cornerstone of that achievement.

Space Shuttle Upgrade Strategic Plan

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 15/68

12S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Space Shuttle Upgrade Strategic Plan

Space Shuttle Development ConferenceThe first Space Shuttle Development Conference, a

national conference sponsored by USA and hosted byNASA, was held in July 1999. Over 700 people fromNASA, industry, academia, and the media attended the

conference which was held in the enormous blimphangar at Moffett Field and the surrounding facilities atthe Ames Research Center. The conference provided theopportunity for industry, academia, andgovernment research and design facilitiesto present emerging technologies and sys-tem concepts as candidates for futureupgrades to the Space Shuttle.

The conference featured new technolo-gy demonstrations, technical sessions, andpanel presentations. Technical papers werepresented in the areas of space vehicle pro-cessing, flight operations, propulsion,avionics, advanced shuttle first stage, cock-pit, power systems, thermal protection sys-tems, and information technology. NASAmanagement and industry executives partic-ipated in panel discussions on the SpaceShuttle of the 21st Century and spacecommercialization. The Space ShuttleDevelopment Conference offered an excel-lent opportunity for the SSP to interface withacademia, industry, and other government

agencies to discuss new and often revolu-tionary ideas for future upgrades that wouldimprove safety, reliability, and performancewhile reducing operating costs for theShuttle. The Conference was an overwhelming successin creating an awareness of the on-going ShuttleUpgrades activities and encouraging industry andacademia to get involved in the Upgrades Program.

Space Shuttle UpgradesThe SSPDOapproved approximately $95 million for

Shuttle upgrade activities in FY99. Of the $95 million,

over $18 million was approved for new flight hardwareupgrade projects. The SRB Altitude Switch Assembly,Display Driver Unit, and Mass Memory Unit projectswere approved to resolve obsolescence problemsencountered due to aging hardware. The old hardware,which was becoming increasingly difficult to maintainand repair, will be replaced with new hardware thatwill improve maintainability by incorporating new

state-of-the-art technology into the designs. An SSMEAdvanced Health Monitoring system will provide real-timemonitoring of vibrations within the SSMEs and will increasesafety by approximately 6%. The current fuel cells, whichmust be removed and overhauled after 2400 hours of

operation, will be upgraded to a new long life alkaline fuelcell which will have an operational life of 5000 hours.Finally, a battery powered EAPU prototype is under

development, and if successful, may replace the currenthydrazine driven APUs. By eliminating the hydrazine andhigh speed, gas-driven turbines, the electric APU couldincrease the safety of the Shuttle by approximately 18%.

Approximately $65 million of the total SSPDO budgetwas approved for continuation of the following flight andground hardware upgrade projects: SRB Composite NoseCap, RSRM Nozzle to Case J-Joint Insulation Redesign,

Radiator and Wing Leading Edge MMOD, SIGI, SSMEPlume Prediction, Integration Structures Verfication LoadsAnalysis (VLA) Process Improvement, Chechout and LaunchControl System (CLCS), and System Engineering Simulator(SES) Image Generator (IG) Enhancement. An additional$10 million was approved for HEDS Technology Demon-strator (HTD) projects, advanced technology studies andprototype demonstrations, and support activities.

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 16/68

13S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Space Shuttle Upgrade Strategic Plan

Integrated Vehicle Health Management (IVHM)HTD-1, flown on STS-95, and HTD-2, flown on STS-96,demonstrated the capability of integrating competingmodern, off-the-shelf sensing technologies and operatingthem in a space environment. The experience and data

captured from the IVHM HTDs will assist in makinginformed design decisions for incorporation of an IVHMsystem on the Shuttle. In addition to the IVHM HTDs, afiber optic HTD was flown on STS-95 and a (NanoMEMS)mid-deck test bed HTD was flown on STS-93. The FiberOptic Flight Experiment captured telemetry data using afiber optic communication pathway. The fiber optic datawere then compared to telemetry data captured from theHST Orbital Systems (HOST) Test Platform via standardShuttle avionics. Postflight comparison of the two sourcesof data was used to assess the viability of using fiber optic

communication pathways onboard the Orbiter. No issueswere identified that would preclude using fiber opticsystems on the Orbiter. The Nano-Micro-ElectricalMechanical System HTD utilized low weight, low volume,low power, and highly reliable submicron andsubmillimeter- scale sensors to measure acceleration, tem-perature, and pressure in the crew module environment.Data collected by the NanoMEMS sensors matched datacurrently collected by other Orbiter systems.

Two HTDs, the Laser Dynamic Range Imager (LDRI)and Wireless Sensor, have been approved and will bemanifested on future Shuttle missions. The LDI HTD,

which is manifested for STS-97, will measure loadsduring critical ISS assembly tasks and will be an integralpart of the Space Vision System(SVS). The WirelessSensor HTD will install several wireless temperaturesensors in the Orbiter crew module and docking mod-ule. Transmitters attached to the sensors will transmitdata to a receiver connected to the Portable GeneralSupport Computer (PGSC). The Wireless Sensor HTD willdemonstrate the ability to use wireless sensors in a spaceenvironment. Wireless sensors could eliminate the needfor long wire runs, which are susceptible to wear andtear damage.

In addition to the HED‘s TD projects, SSPDO hasalso funded several advanced technology developmentprojects. These projects typically have a low technologyreadiness level and need further development to supportthe Shuttle and next-generation launch vehicles. Theadvance technology projects include the ProtonExchange Membrane Fuel Cell, NonToxic Orbital

Maneuvering Subsystem/Reactive Control Subsystem(OMS/RCS), and various flight and ground operationsprojects.

The SSPDO will continuously evaluate potentialupgrade projects. As upgrades are approved and imple-mented, the Shuttle will become a safer and more reliablevehicle capable of fulfilling the goals and objectives of the

SSP and the Agency. y

SSMEAdvanced Health Monotoring

Block 3 EngineNew Nozzle

Ground SupportAutomated Hypergolic Pad ServicingSCAPE Suit Improvement

Improved APUNose CapModify Fuel Geometry of Fwd Segment

Power and PropulsionElectric APULong Life Fuel Cell

Structures and MechanismsCrew Escape System (study)Main Landing Gear Tire ImprovementsWindow Cavity Conditioning System

Thermal Protection SystemMore Durable Lower Surface Tile

Payload andSystem Integration

Orbiter AvionicsCockpit: Enhanced Caution and Warning

Crew Situation Awareness DisplaysAFD Switch Panel Upgrade

Data Processing: Mission Management Computer

SRB/RSRM

Advanced Technology

Shuttle Upgrades Technical Content Summary (highlighting safety-specific improvements) 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 17/68

14S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Space Shuttle Program Mission Summeries 

STS-95

Discovery was successfullylaunched from Kennedy SpaceCenter (KSC) at 1:19 p.m.

CST on October 29, 1998.Discovery carried nearly3 dozen life sciences,microgravity sciences, andadvanced technology experi-

ments sponsored by NASA,the Japanese Space Agency

(NASDA), the European SpaceAgency (ESA) and commercial entities.

The crew completed all planned mission operations.The primary objectives included conducting a

variety of science experiments in the pressurizedSpaceHab module, the deployment and retrieval of the

SPARTAN free-flyer payload, and operations with theHOST and the International Extreme Ultraviolet Hitchhiker(IEH) payloads carried in the payload bay.

For STS-95, a single-module SpaceHab was locatedin the forward portion of Discovery’s payload bay. Avariety of experiments sponsored by NASA, NASDA andESA focused on life sciences, microgravity sciences, andadvanced technology during the flight.

The Spartan 201 free-flyer designed to investigatephysical conditions and processes of the hot outer layersof the Sun’s atmosphere, or solar corona, was deployedand retrieved using the Shuttle’s mechanical arm. Informa-tion collected during this mission will lead to a much betterunderstanding of the solar winds that directly influencetelevision and phone communications, orbiting satellites,and weather conditions on Earth. SPARTAN downlinkedover 500 solar coronal images from the Goddard SpaceFlight Center (GSFC) White Light Coronograph (WLC).An additional 600 WLC images and 300 SmithsonianAstrophysical Observatory Ultraviolet CoronalSpectrometer spectra were stored on the onboardrecorders and retrieved after the flight. The mission wasan outstanding scientific success.

The HOST platform carried experiments to validatecomponents planned for installation during the thirdHST servicing mission and to evaluate new technologiesin an earth orbiting environment. There were fourexperiments on the HOST platform:

(1) The NICMOS Cooling System, a zero-g verification of a Reverse Turbo Brayton Cycle Coolerdesigned to replace the current dewar system

(2) The HST 486 computer, designed to identify anyradiation-susceptible parts in the DF-224replacement and demonstrate hardware andsoftware responses to single event upsets (SEU’s)

(3) Solid State Recorder, designed to compare on-

orbit operation of the flight spare solid staterecorder with the current HST unit

(4) Fiber Optic Line Test, designed to capture thesame 4 kbps data stream that is sent to theOrbiter’s Payload Data Interrogator via afiber optic system routed to a laptop computerfor postflight comparison. The HOST Platformexperiments were highly successful.

The IEH payload involved six different experimentsmounted on a support structure carried in Discovery’spayload bay. The IEH-3 payload was the third in a

series of five flights dedicated to the investigation of theabsolute solar extreme ultraviolet (EUV) and far ultravio-let (FUV) flux emitted by the plasma torus system around

 Jupiter and stellar objects. The payloads also studied theEarth’s thermosphere, ionosphere, and mesosphere.

The IEH-3 payload consisted of five prime experi-ments plus two get-away special (GAS) canisterscontaining educational experiments:

(1) Solar Extreme Ultraviolet Hitchhiker (SEH),managed by University of Southern California,that obtained EUV and FUV fluxes required when

studying the Earth’s upper atmosphere(2) Ultraviolet Spectrograph Telescope for Astronomi-cal Research (UVSTAR), managed by Universityof Arizona, designed to measure EUV fluxeswhich can be used to form images of extendedplasma sources (Jupiter, hot stars, etc.)

(3) Space Telescope for Astronomical Researchmanaged by the University of Arizona, whichmade observations of extended and diffusedastrophysical targets

(4) Solar Constant Experiment (SOLCON), managedby the Royal Meteorological Institute of Belgium,dual-channeled radiometer viewed the Sun

during 11dedicated solar periods and during7 non-dedicated solar periods, acquiring over17 hours of data

(5) Petite Amateur Navy Satellite (PANSAT), man-aged by the Department of Defense Space TestProgram and involving a small deployablesatellite that stored and transmitted digitalcommunications to PANSAT ground stations

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 18/68

15S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Space Shuttle Program Mission Summaries 

(6) Two GAS payloads:(a) GAS G-238, sponsored by the AmericanInstitute of Aeronautics and AstronauticsNational Capital Section and managed byDuVal High School, Prince GeorgeCounty,

Maryland contained two biological experiments(b) GAS payload G-764, sponsored by theUniversity of Bremen, Germany, and ZARM(Zentrum fur Ange wandte Raumfahrttech-nologie und Mikrogravitation), whoseobjective was to simulate dust aggregationand the dynamics of dust clouds of the earlysolar system

The IEH-3 mission was by far the most successfulflight of the IEH initiative, as evidenced by theunprecedented achievements of the UVSTAR, SEHand SOLCON experiments.

Two additional GAS payloads were aboard theSTS-95 mission. The purpose of the G-467 GAS payloadwas to demonstrate in space the working principle andperformance of a two-phase capillary pumped loop withtwo advanced evaporators, a two-phase vapor qualitysensor with two condensers in parallel, and a controlreservoir. The G-467 GAS payload was sponsored bythe ESA, Paris, France. G-779, or Hearts in Space, wasdeveloped by researchers at Bellarmine College inLouisville, Kentucky. The purpose of the payload is toexamine the role of gravitational-dependent hydrostatic

pressure effects on the adaptation of the cardiovascularsystem to the microgravity environment of spaceflight. Thepayload consists of a fluid circuit simulator of the heart andmock circulation system, the instrumentation to automati-cally conduct the experiment protocol and record data,and batteries to power the experiment.

Cryogenic Thermal Storage Unit (CRYOTSU)was fifth in a series of cryogenic test bed flights. TheCRYOTSU payload and avionics were attached to anadapter beam mounted on the sidewall of the Orbiter.The CRYOTSU payload was a compilation of fourcryogenic experiments: A 60K Thermal Storage Unit

(TSU); a Cryogenic Capillary Pumped Loop (CCPL); aCryogenic Thermal Switch (CTSW); and a PhaseChange Upper End Plate (PCUEP). The 60K TSU, CCPL,and CTSW benefit future integrated cryogenic bus sys-tems. The PCUEP will benefit future cryogenic test bedmissions and spacecraft requiring load-leveling forpower-dissipating components.

CRYOTSU completed approximately 90 hours ofoperation that included 23 full melt cycles and 18

partial melt cycles at various heat loads. The unit per-formed as expected and correlated very well to testsconducted on the ground. CRYOTSU successfullyachieved more than 200% of the minimum missionobjectives, and over 100% of its nominal mission

science objectives.The Biological Research in Canisters (BRIC) investiga-

tion was contained in 3 canisters with a passive cooler inone mid-deck locker in the crew compartment. Thispayload, managed by KSC, contributed to researchers’understanding of how the weightlessness of space affectsthe development of plants. The implications are importantfor the crews of future long-duration spaceflights becausethey will depend on plants grown in space for food, water,and oxygen.

Electronic Nose (ENOSE) was located in amid-deck locker and the objective was to flight test anenvironmental monitoring instrument that would detectand identify a wide range of organic and inorganicmolecules down to the parts per million level. The instru-ment was designed to monitor changes in the atmos-phere to which it is exposed and consists of an arrayof thin film polymer sensors dispersed with carbon.All ENOSE operations were nominal and all dailyobjectives were met.

The Protein Crystal Growth-Single Locker ThermalEnclosure System (PCG-STES) payload was designed toconduct experiments which supply information on the sci-

entific methods and dynamics of growing largehigh-quality protein crystals in microgravity. The PCG-STESwas installed and operated in the Orbiter mid-deck.

Since the aging process and a spaceflightexperience share a number of similar physiologicalresponses, a series of experiments sponsored by NASAand the National Institute on Aging were conductedduring the STS-95 mission. The investigations gatheredinformation that may provide a model system to helpscientists interested in understanding aging. Some ofthese similarities included bone and muscle loss,balance disorders and sleep disturbances. All experi-

ments were performed and the data downloaded forpostflight analysis. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 19/68

16S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Space Shuttle Program Mission Summeries 

STS-88

The launch of Endeavour , with fiveAmericans and one Russianonboard, from KSC at 2:36

a.m. CST on December 4,1998, began the largest coop-erative space construction proj-

ect inhistory; the building of the ISS.

After rendezvous and berthing of theRussian-built Zarya control module (FGB) to Node 1 (Unity),three space walks were successful in connecting electrical andcommunication lines between the Unity and Zarya. During thetwo days of open hatch operations, assembly and checkout ofthe early S-band communications system were completed andapproximately 1200 lbs. of hardware was transferred to and

335 lbs. from, Unity/Zarya (Stage 2 of the ISS). Afterundocking from the ISS and successfully deploying two smallsatellites, the crew of six landed at KSC.

In addition to accomplishing all 23 of the ISS flightobjectives, 3 Zarya repair/maintenance tasks were complet-ed. The tasks were the replacement of a battery charging unitinside Zarya, the deploying of two TORO antennas that failedto deploy after Zarya reached orbit, and the configuring ofthe Komplast experiment located outside of Zarya.

On Flight Day 11, the crew successfully deployedthe SAC-A satellite, a small non-recoverable satellite built bythe Argentinean National Commission of Space

Activities. This marked the first deployment of an Argen-tinean satellite. The ejection altitude showed a predictedlifetime of 6-9 months. During this time, SAC-A will testvarious new technologies including a differential globalpositioning System, a charge-coupled Device camera,silicon solar cells, a whale tracker, and a magnetometer.

On Flight Day 12, the crew successfully deployedthe MightySat-01 satellite. The MightySat-01 team willdemonstrate four advanced technologies during the life ofthe satellite: composite structure, advanced solar cells,advanced electronics, and a shock device.

Approximately 67% of the IMAX Cargo Bay Cameraobjectives planned for the flight were successfully accom-plished. The camera accomplished execution of all scenesduring Node grapple and installation.

Gas payload G-093R, the Vortex Ring TransitExperiment, successfully operated for approximately 9.5hours. The objective of this experiment was to investigatethe propagation of a vortex ring through a liquid-gasinterface in microgravity. The G-093R GAS is sponsoredby the University of Michigan.

The Space Experiment Module (SEM-07) flight projectis one of a number of educational initiatives being pursuedby the NASA Shuttle Small Payloads Project to increase

educational access to space by means of Space Shuttlesmall payloads and associated activities. TheSEM-07 on STS-88 utilized an existing 5 cubic-foot GAScanister with a GSFC-provided internal support structure.The canister housed various passive experiments fromschools ranging from the kindergarten to the universitylevel. Seven modules were provided by teachers andtheir schools participating in the NEWMAST – NASAEducational Workshop for Mathematics, Science andTechnology Teachers.

The Shuttle Ionospheric Modification with Pulsed LocalExhaust (SIMPLEX) experiment is sponsored by the United

States Air Force Space and Missile Center for the NavalResearch Laboratory. The purpose of the experiment was todetermine the source of the very-high-frequency radar echoescaused by the Orbiter and its OMS engine firings. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 20/68

17S PACE SHUTTLE PRO GRAM 1999 AN N U A L RE PO RT

Space Shuttle Program Mission Summaries 

STS-96

The STS-96 (ISS-2A.1 Logistics) mission onDiscovery , with five Americans, one

Russian, and one Canadian onboard, was initiated with anon-time KSC liftoff on May 27,1999 at 5:49:42 a.m. CDT,

and began the second U.S. mis-sion to the ISS. Following ren-

dezvous and the first directdocking with the ISS Pressur-

ized Motoring Adapter-2, one space walk was completedto transfer the U.S. Orbital Replacement Unit TransferDevice and Russian Strela cranes as well as the transfer ofextravehicular activity (EVA) pre-positioning hardware to

be used for subsequent ISS assembly tasks. This missionalso highlighted the maiden voyage of the SpaceHabIntegrated Cargo Carrier, which consists of anUnpressurized Cargo Pallet mounted on a Keel Assemblyand was used for the mounting of external transfer items.

During the Flight Day 5 to Flight Day 9 dockedoperations all preflight-planned on-orbit task prioritieswere completed as well as over 4000 lb. of EVA andintravehicular activity (IVA) transfers. Additionally,seven more on-orbit inspection tasks were requestedand completed.

Other payloads on STS-96 were the Student TrackedAtmospheric Research Satellite for Heuristic InternationalNetworking Equipment (STARSHINE), the Shuttle VibrationForces Experiment (SVF) and the IVHM HTD.

The STARSHINE was a Rocky Mountain NASA SpaceGrant Consortium/Utah State University-sponsoredejectable satellite. The purpose of the mission was to traininternational student volunteer observers to visually trackthis optically reflective spacecraft during morning andevening twilight intervals for several months, calculateits orbit from shared observations, and derive atmos-pheric density from drag-induced changes in its orbit

over time. Following undocking from the ISS, the crewsuccessfully deployed the STARSHINE satellite at analtitude of 205 n.mi.

STS-96 was the second flight of the SVF experiment.The SVF experiment activated automatically by the Orbiterlift-off vibration and operated for approximately 240seconds. This was accomplished by using commerciallyavailable triaxial force tranducers and three wide-bandstand-alone acceleration measurement devices that were

built by JSC and funded by the Jet Propulsion Laboratoryfor this application. This experiment provided flight

measurements of the vibratory forces acting between anaerospace payload and its mounting structure.The HTD-1402 and the IVHM was activated approx-

imately one hour daily during pre-sleep to capture dataduring power reactant storage and distribution valvecycling. The IVHM is an evolution of a traditional vehicleinstrumentation system that consisted of sensor, wiring,signal conditioning devices, multiplexing devices, andrecording devices. IVHM also provids the capability toprocess the data versus merely recording the data. Thepurpose of this HEDS experiment was to demonstratecompeting modern, off-the-shelf technologies in an

operational environment to determine its use for futureOrbiter upgrades. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 21/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 22/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 23/68

CONTENTS

S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

PART 2Detai led Techn ica l Ac t iv i t ies and Accompl i shments

Marshall Space Flight CenterExternal Tank ....pages1-4

y Super Lightweight External Tank Performance

y Delivery of the 100th External Tank

y Progress on Enhancing Weld Processes

for Aluminum Lithium

Reuseable Solid Rocket Motor...pages 5 -17y Project Performance Highlights

y Test Accomplishments Flight Support Motor (FSM)

y MNASA Motor

y 24-inch Solid Rocket Test Motor (SRTM)

y Obsolescence Mitigation

y Operational Pressure Transducer

y EPDM Insulation Reformulation

y Ozone Depleting Chemical Elimination

y Nozzle Rayon Replacement

y Nozzle Structural Adhesive Replacement

y Knowledge Enhancements/

Technical Resolution

y Enhanced Sustaining Engineering Project

y Nozzle-to-Case (N/C) Joint Process

Enhancements

y Nozzle Structural Test Bed (NSTB)

y Case Buckling Capability

y Process Enhancements Nozzle-to-Case Joint

 J-Leg Configuration

y Mix Room Modernization

y Cell Plating

Solid Rocket Booster....pages18 -19y 100th Booster Set Flown

y ET Observation Camera

.Space Shuttle Main Engine....pages 20-22

y HPFT Certification Status

y Final Production Build of HPOT

y SSME Processing Facility

 Johnson Space CenterVehicle Engineering....pages 23-32

y Orbiter Modifications

y Orbiter Upgrades

y Orbiter Remote Manipulator Subsystem

y Orbiter Space Vision System

y Flight Crew Equipment Upgrade

y Avionics and Software

Customer and Flight Integration....page 33y Flight Production Template Success

System Integration....pages 33-38y Intergration Hazard Reports

y Vehicle Standardization

y Reductions in Thermal and Structural Cargo

Verification Analysis Cycles

y SES Scene Generation Upgrade

y Ascent Postflight Reconstruction and Flight-Derived

Dispersion Update

y Ascent Performance Enhancements Flight Summary

Mission Operations....pages 39- 40y Flight OperationsReinvention

y Mission Control Center Command Servers

Kennedy Space CenterShuttle Processing....pages 41- 43

y Checkout and Launch Control System Progress

y Y2K Compliance and Certification Test

y Environmental Improvements

y Implementation of Ablative Insulation for

SSME Nozzles

y Study and Strategy for Advanced Health

Monitoring System

y Process Control Improvements inManufacturing Capability

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 24/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 25/68

2S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – External Tank 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 26/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 27/68

Progress on Enhancing Weld Processes

for Aluminum Lithium

During welding, unlike AL 2219, the new alloy

(AL 2195) is very sensitive to contamination. Thispresented several significant challenges. The

immediate solution to the contamination issue was resolvedusing a traveling purge box, which provided an inertatmosphere during welding. Subsequently, an ingenioussolution to the problem was developed. Instead of using atraveling purgebox, a staticpurge chamberwas developedthat provides aninert atmosphere

throughout theentire length.This eliminatedall the movingparts that werejamming andprovided a moreconsistent deliv-ery of the purge gas.

Weld repairs have become a significantchallenge for production of SLWTs. To resolve this

challenge the ET project has developed a new weldrepair technique. The new procedure is an industryfirst and and vastly simplifies weld repairs. The newprocess called friction plug repair, works very simi-larly to a forging process, where the metal is notmelted, and thus the tensile properties are notadversely affected.

Another new technology is being developed toaddress the initial welds,known as friction stir weld-ing. This technique overcomes many of the currentprocess challenges such as torch control, heat sink,and purge gas. Additionally this new method

changes the welding of aluminum into a machiningprocess, which is less labor intensive, less technicallycomplex and easier to control, and providessuperior-strength welds.

The welding technologies being implemented andthose being investigated will allow the ET Project toprovide the SSP a more reliable ET that is less expensiveto build. y

4S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – External Tank 

Friction Plug Welding Repair 

Heating Phase Forging Phase

Rotate Plug at 6500 RPM and Forceinto Hole with 10,000lb Load

Stop Rotation and Forge Weld with 10,000lb Load

 Aluminium Plug

 Aluminium Plate

Steel Backing Plate

 Weld Flash

Extrusion

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 28/68

5S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Reusable Solid Rocket Motor 

RSRM Project Performance Highlights

R

SRM thrust performance was right on thepredicted target for each of the four Space

Shuttle launches in GFY99. No significantanomalies were identified either during ascent orduring subsequent postflight disassembly and inspectionof the recovered motors.

All RSRM segments for GFY99 were delivered onschedule, making this the ninth consecutive year ofon-schedule RSRM deliveries to KSC.Safety continues tobe a principal focus in the manufacture of the RSRM andis reflected in the job-related accident frequency rates atThiokol Propulsion, which have been well below therates for similar industries as published by the Bureauof Labor Statistics.

Because of its low accident rates, Thiokol Propulsionreceived the following recognition this past year:

• National Safety Council Perfect Record Awardfor operating 1,965,694 hours without anoccupational injury or illness involving days awayfrom work (May-September 1999)

• Labor Commission of Utah Award for safetyexcellence in the manufacturing sector based onlow workers’ compensation costs

• National Safety Council Safe Driver Awardspresented to designated company vehicleoperators

The RSRM project continued to expand employeesafety awareness, developing several safety initiativesthroughout the year:

• Instituted “Safety Start-up Day” after returningfrom holiday shutdowns (special safetyinspections and meetings were conducted byemployees throughout the plant)

• Designated June as “Safety Month,” with specialsafety activities that included several energetic

material demonstrations shown to employees to promoteexplosive handling safety awareness

• Implemented a new “Safety Website” thatprovides employees with real-time access to theGeneral Safety and Health Manual, safety videolistings (e.g. Dupont’s “Take Two” program),recent developments in safety/ performancegoals, and Safety and Environmental Boardsafety communiqués

In-flight Anomaly Summary 

RSRM OSHA Recordable Case Incidence Rate (PER 200,000 HOURS WORKED) 

RSRM Lost Time Cases Incidence Rate (PER 200,000 HOURS WORKED) 

u Manufacturing

u Private Industry

u Similar Industries

u Thiokol Propulsion

* Rates not yetavailable fromBureau of Laborstatistics

u Manufacturing

u Private Industry

u Similar Industries

u Thiokol Propulsion

* Rates not yetavailable fromBureau of Laborstatistics

2.8

2.5*

2.0*

1.5*

1.0*

1.0*

0.0*

0.15

0.60.8

0.18 0.180.15 0.21

2.5

1.0

3.0

2 *

0 *

8 *

6 *

4 *

2*

0*

4

2.5

2.22.1

2.4

CY95 CY96 CY97 CY98* CY98YTD

11.6

2.52

3.4 3.22.55 2.612.75 2.4

8.1

4.0

10.6

7.4 7.1

10.3

CY95 CY96 CY97 CY98* CY98YTD

   N  u  m   b  e  r  o   f   I   F   A  s

8

7

6

5

4

3

2

1

0

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 29/68

6S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Reusable Solid Rocket Motor 

• Implemented a new Hazard CommunicationWebsite to provide employees easieraccess to hazardous materials information.

The RSRM program has progressively improvedproductivity and quality over the last decade. Quality

conformance for each motor exceeds 99.999 %.RSRM manufacturing nonconformances have leveledoff at a low rate. A new discrepancy reduction focuswas recently initiated across all areas of the RSRMprogram, including suppliers.

Manufacturing touch labor hours required toproduce a motor have been cut in half over thelast decade while in the same period the cost ofproduction scrap, rework, and repair per motorhas been reduced a dramatic 90 %.

In May 1999, Thiokol Propulsion cast the

1,000th solid propellant motor segment for theSSP. This brought the total to 277 million lb ofpropellant cast in support of the SSP.

In recognition of its commitment to excellence,Thiokol Propulsion was awarded the 1999 MSFCContractor of the Year Award and the 1999George M. Low Award for Quality andExcellence. y

RSRM Nonconformances by Flight Set 

Manufacturing Touch Labor Hours per RSRM

Scrap, Rework, Repair Costs per RSRM

   D

  o   l   l  a  r  s

   H  o  u  r  s

700,000

600,000

500,000

400,000

300,000

200,000

100,000

100,000

90,000

80,000

70,000

60,000

50,000

40,000

30,000

20,000

10,000

0

GFY89 GFY99

   N  e  w    N  o  n  c  o  n   f  o  r  m  a

  n  c  e  s

500

450

400

350

300

250

200

150

100

50

0

RSRM Build Sequence (1-75)

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 30/68

7S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Reusable Solid Rocket Motor 

RSRM Test Accomplishments

 Flight Support Motor (FSM)

 Full-scale RSRM static test motors are periodically

tested to confirm the performance and safety ofRSRM systems, components, materials, and

processes. FSMs also provide the opportunity to evalu-ate, demonstrate, and/or certify design, process, andmaterial changes. Health monitoring of RSRM hardwareis enhanced through the utilization of specialized instru-mentation. The capability to meet the program goal tostatic test every change was greatly enhanced by therecent program decision to fund annual full-scale statictests (versus 18-month intervals prior). The next FSM testfiring (FSM-8) is scheduled for January 2000. Themanufacture of FSM-8 has been largely completed

during this government fiscal year and includes thefollowing significant test objectives (and many other lesssignificant objectives):

y Certify the performance of the nozzle throatfabricated using a new 120-in. phenolictape-wrapper

y Certify the performance of replacement nozzlestructural adhesives

y Certify the performance ofa replacement operationalpressure transducer (OPT)

y Obtain performance dataon asbestos-free internalinsulation

y Obtain forward-facinginhibitor erosion data

y Obtain field jointinsulation temperature andmotion data

y Obtain nozzle Joint 2strain, pressure, andtemperature data

yObtain nozzle boot cavity(Joint 5) temperature data

y Obtain performance dataon components cleaned with Ozone -depletingchemical free cleaners

y Obtain performance data on aluminum cellplating repair technique for sealing surfaces y

RSRM Flight Support Motor Firing 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 31/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 32/68

9S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Reusable Solid Rocket Motor 

RSRM Obsolescence Mitigation

T

he uninterrupted supply of unchangedcomponents and materials is often challenged

by factors such as state and federal regulationchanges (including environmental, health, and safety),continued supplier and subtier supplier availability,supplier and subtier supplier process enhancements,and equipment and facilities aging/replacement. TheRSRM program has made early identification andresolution of obsolescence threats part of its dailyculture. All identified threats, however minor, areformally tracked and communicated in a bi-monthlyobsolescence status report that identifies programprotection steps (like stockpiling) to ensure continuedRSRM production while resolution and verification

plans are being worked. The following figureidentifies all open RSRM obsolescence threats as ofSeptember 1999.

This chart provides status on key items (identified onthe “RSRM obsolescence threats” chart by an arrow).

Operational Pressure TransducerThe RSRM program is evaluating and qualifying a

new flight motor OPT. The current pressure transducer(used to monitor in-flight ballistics performance and toprovide booster separation information to the SpaceShuttle Orbiter) is no longer manufactured. Followingthe evaluation of numerous replacement designs andsuppliers, a Stellar Technologies bonded strain gagepressure transducer was selected for final verification.A CDR was successfully held in August 1999. Thesereplacement OPTs will be included on the FSM-8full-scale static test motor in January 2000, with flightimplementation projected for fall 2000. OPTs arerefurbished and reused, and a sufficient quantity

of the current OPT exists to support the SSP wellbeyond 2000. y

RSRM Obsolescence Threats 

Replacement RSRM Operational Pressure Transducer 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 33/68

10S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Reusable Solid Rocket Motor 

EPDM Insulation Reformulation

S

ilica-filled ethylene propylene diene monomer(SF-EPDM) and carbon-fiber-filled ethylene

propylene diene monomer (CF-EPDM) are twoprincipal insulation materials used on the RSRM. TheSF-EPDM is used for external thermal protectionapplications such as the factory joints and the systemstunnel. The CF-EPDM is the primary internal insulation inthe aft dome region and is the only elastomeric materialknown that withstands the RSRM aft dome environmentwith acceptable ablation and erosion rates. CF-EPDM isalso used on the center segments under the split flaps.

In 1998, a subtier supplier of two of the constituentsused in SF-EPDM and CF-EPDM formulations announceda discontinuation due to declining market demand.

Stockpiling of quantities of the current constituentssufficient to last beyond 2005 was completed thisgovernment fiscal year before the subtier supplier’sproduction shutdown. Extensive laboratory re-formula-tion effort in GFY99, including numerous subscale testmotor firings, produced several promising candidateEPDM formulations. Three of these formulations weretested on an MNASA motor in August 1999 (MNASA-10), and three more have been selected for the nextMNASA firing in early GFY2000. Culmination of theEPDM reformulation program is planned in 2003following three full-scale static test firings. y

RSRM EPDM Insulation

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 34/68

11S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Reusable Solid Rocket Motor 

Ozone Depleting Chemical Elimination

M

ethyl chloroform (TCA) production has beenbanned for emissive uses, such as thoseemployed to manufacture the RSRM.

Aggressive testing and investment in leading-edgetechnology has enabled the RSRM program to redirectthe manufacturing process and reduce the use of TCAby over 1.1 million lb. per year.

The RSRM program is currently in the final phase of itsODC elimination program. The current effort is dedicatedto eliminating the remaining 10 % of TCAusage involved in the hand cleaning of surfacesfor bonding and assembly, as well as rubberactivation. Extensive GFY99 laboratory testingled to the down-selection of five cleaner

candidates (August 1999) that perform equalto or better than TCA in cleaning performanceand bond properties. Full-scale process simula-tion articles have been initiated that will lead tothe selection of a cleaner for a full-scale statictest on FSM-9. y

Nozzle Rayon Replacement

T

he RSRM program is developing areplacement for rayon yarn, a

precursor material in the manufactureof carbon cloth phenolic (CCP) ablatives forthe RSRM nozzle (see figure). The previousrayon yarn supplier discontinued productionin September 1997. Prior to the shutdown, theRSRM program procured a stockpile that willsupport RSRM production through 2005.

Replacement fiber candidate screeningactivities began in February 1999. Eachcandidate was evaluated on the ease oftransformation from a cellulose fiber intoresin-impregnated carbon cloth, the mechanical

performance of the phenolic compositemanufactured from the carbon cloth, and theperformance of the phenolic composite in anoperational rocket motor environment. Fourteenof 22 fiber candidates have completed thescreening tests, with the remaining eightcandidates to complete testing in November1999. Six candidates were also tested on MNASA-9and -10: all six demonstrated ablative characteristics

comparable to the current rayon-based carbon clothphenolic ablative. Ultimately, the best fiber candidate willbe selected in early 2002 and tested in three full-scalestatic test motors before use in a production RSRM nozzle.The first production nozzle made with the replacementfiber candidate is targeted for the spring of 2005. y

RSRM ODC Elimination ProgramTCA Usage and Stockpile Balance 

RSRM Nozzle 

   T   C   A   U  s  a  g  e   (   M   I   B   )  :   I  s  s  u  e   d   Q  u  a   l   i   t  y

   T   C   A   (   0   1  -   3   8   6   0   0   0   )   S   t  o  c   k   P   i   l  e

   B  a   l  a  n  c  e   (   k   l   b   )

1.6

1.4

1.2

1.0

0.8

0.6

0.4

0.2

0.0

700

600

500

400

300

200

100

0

654

348

206

76.832 9.5

1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001

1.4

1.2

1.0 1.0

0.78

0.58

0.32

0.14 0.13

0.62

PHASE 0 PHASE lPHASE ll

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 35/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 36/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 37/68

14S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Reusable Solid Rocket Motor 

RSRM Nozzle-to-Case (N/C)Joint

Process Enhancements (“bump”)

T

he RSRM N/C joint is assembled with a polysul-fide adhesive that functions as part of the joint

thermal barrier system.Historically, the N/C joint assembly process has resultedin a small percentage of assemblies with one of twomutually exclusive polysulfide issues. Either gas pathsare created through the polysulfide due to entrapped air(13 out of 140 joint assemblies), allowing hot gas toreach the wiper ring, or polysulfide is extruded aft to thepoint of contacting the primary O-ring seal (2 out of140 joint assemblies). While neither of these observedconditions are a flight safety issue, they are undesirable.A process improvement team developed process andassembly configuration enhancements, which, in

extensive full-scale testing, have proven successful insignificantly reducing both the potential for gas pathformation and the potential for extrusion of polysulfidetoward the primary O-ring.

Although there are numerous process step refine-ments, the primary feature is the incorporation of apre-cured polysulfide bead (bump). The bump is appliednear the insulation step and provides fullcircumference interference between the nozzle and aftdome insulation during the final stage of assembly. Thebump has demonstrated its capability to ”nip“ off the

formation of gas paths in a full-scale assembly test setupthat reliably produced gas paths using the currentassembly process. These process enhancements,including the pre-cured bump, successfully completedfull-scale assembly and disassembly verification testingin GFY99 and were incorporated into flight productionbeginning with RSRM-80 (June 1999), which is currentlyassigned to STS-105. y

Nozzle-to-Case Joint ”Bump Configuration“ 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 38/68

15S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Reusable Solid Rocket Motor 

Nozzle Structural Test Bed (NSTB)

T

o date, the only test bed to evaluate themechanical behavior of nozzle internal joints

has been a full-scale RSRM static test motor.The NSTB was conceived to evaluate the mechanicalbehavior of a full-scale RSRM nozzle in a laboratory-type setting. The NSTB is designed to simulate the RSRMpressure rise at motor ignition. It also possesses nozzlevectoring capability. The arrangement allows forextensive instrumentation to measure nozzle structuralresponse, including the bolted joint regions. Design andfabrication were completed in GFY99, with assembly ofthe NSTB planned for late CY99. y

RSRM Case Buckling Capability

Each Space Shuttle launch is subject to hundredsof constraints designed to ensure flight safety.Wind speed is one constraint critical to the

RSRM, as it affects the structural loads on the RSRMcases. The RSRM cases support the entire vehicle on thelaunch pad. As the orbiter’s main engines start, theSpace Shuttle vehicle bends over approximately threefeet at the top of the ET. Wind loading can obviously

add to this bending, especially southerly winds. TheRSRM cases must resist this bending(called buckling capability) before thevehicle springs back to vertical and theRSRMs are ignited for launch. Bucklingis analogous to the force on a sodacan that can cause it to crumple. It is aprincipal design consideration in theaft segment stiffener cylinders. RSRManalyses currently include a largeknockdown factor to account foruncertainties in loading and environ-

mental conditions, manufacturing andinspection processes, modeling, etc. Thisanalytical approach results in relativelylow allowable wind speeds (15 knotsfrom the south). Such wind speeds havethe potential to delay a launch.

A full-scale RSRM case buckling testprogram was conducted to validate the

buckling analysis with full-scale test data and determinehow much conservatism could be removed and still guar-antee the margins of safety at higher wind speeds. The testwas conducted by selecting full-scale stiffener cylindersand characterizing their configuration: wall thickness,imperfections in straightness, etc. A specific analysis was

performed to predict each cylinder’s buckling capability.The stiffener was installed in aspecial tooling arrangement(see figure) designed torepresent flight prelaunchloading conditions andcapable of applying 4.3million lb. of load to thecylinder. Each stiffener washeavily instrumented tomeasure strain during testing.Force was applied to each

stiffener until bucklingoccurred. Ten tests wereconducted, all in GFY98.

Nozzle Structural Test Bed 

RSRM Case Buckling Test 

 Actuator

UpperBuckling

Ring TangSpool

ForceFrame

ClevisSpool

RSMRStiffenerTest

 Article

Pinned Joints

ForceBeam

Upper Buckling Beam

Lower Buckling Beam

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 39/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 40/68

17S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Reusable Solid Rocket Motor 

Cell Plating

T

he RSRM program, with the helpof the Rocketdyne Division ofBoeing, has applied cell-plating

technology to repair small defects of sealsurfaces on RSRM reusable aluminumnozzle housings.

Following splashdown, the RSRMboosters are towed back to Hangar AFand lifted out of the salt water. Thenozzles are removed from the boosters atHangar AF and shipped to Clearfield,Utah, for complete disassembly. By thetime the nozzles are disassembled(approximately three weeks after flight),

metal surfaces exposed to the seawater have had plentyof opportunity to corrode. If the corrosion is severeenough, it can render a nozzle metal housing unfit forfurther use. Although small corrosion pits do not causestructural concerns on the robust 0.5-in.-thick housings,they can have a detrimental affect on seal surfaces.Instead of selling housings with unacceptable sealsurface defects to the local scrap yard at pennies on thedollar, NASA and Thiokol Propulsion teamed with Rock-etdyne to apply cell-plating technology to the repairingof these defects. Rocketdyne has used the technique torepair similar defects on SSME components.

The technique involves fabricating a local platingcell around a defect. The surface is first cleanedto remove any contamination. The area is then electro-plated with copper and nickel. The defect is overfilledand then machined level with the surrounding material.The plating blends smoothly into the surroundingsurfaces until the surface finishes are identical.

The cell-plating process for RSRM aluminum nozzlehousings completed its laboratory verification in GFY99.A corrosion-related defect in an RSRM nose inlet housing(0.018 in. deep) has been repaired. The housing is

scheduled for full-scale static testing on FSM-8 in January2000. Flight implementation will follow a successfulpost-static test assessment. y

RSRM Mix Room Electronic Weighting and Data Handling 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 41/68

18S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Solid Rocket Booster 

SRB Develops ET Observation Camera

V

iewers who were watching the on-orbitactivities of the STS-95 flight on NASA TV

during the afternoon of Saturday, October 31,1998 were treated to a recorded view of the SpaceShuttle during its ascent to orbit that had never beenseen before. A close-up vista of the heat-discoloredinsulation on the side of the Shuttle’s ET was quicklyfollowed by a broader panorama of SRB separation.The ET and Orbiter rapidly moved out of the field ofview as a SRB appeared by itself, twisting, turning, andspraying out hot embers as it disappeared into thedistance against the blackness of space. The view thenslowly changed to random scenes of white specks ofcloud covering the broad expanse of the Atlantic Ocean

far below. These clouds appeared ever closer and soonthe scenes of space were replaced by close-up views ofsplashing water and parachute lines. The viewer hadjust experienced a “booster’s eye view” of SRBseparation, coast to altitude, atmospheric reentry,and splashdown.

How were these unique views of the Shuttlecaptured and for what purpose? Following the Orbiter

NASA Takes Delivery of 100th Set of

Shuttle Solid Rocket Booster FlightHardware

NASA’s Space Shuttle SRB program has markedthe flight of its 100th set of booster hardwarewith this year’s flight of the STS-96 mission.

The mission flew with the 100th assembly built ofreusable booster hardware. The 100th Shuttle missionwon’t lift off until next year. But when the Shuttleprogram needed a cylindrical forward skirt modified tocarry video equipment for filming the ET during launch,the next available hardware was the right forwardbooster section originally assigned to the 100th mission.The MSFC manages Space Shuttle main propulsion,

including the boosters, liquid fuel main engines, and ET.USA manufactures the SRBs at NASA KSC facilities.The Shuttle boosters designed to be reused are the

largest solid propellant rockets flown on a pilotedspacecraft and the largest objects ever to be recoveredby parachute. y

Columbia’s landing at NASA’s KSC at the conclusion ofSTS-87, significant superficial damage was discovered onthe protective heat shield tiles. Exhaustive analytical mod-eling and experimental testing by NASA’s MSFC and JSCindicated that the most likely cause of the tile damage was

high-speed impact of small particles of the ET’s spray-onfoam thermal insulation. Although the damage did notpose a safety of flight concern, it was imperative to quicklypinpoint and understand exactly how this ET Thermal Pro-tection System material was breaking loose. A high-fidelityascent videotape of the suspect area of the ET wouldprovide exactly the needed data.

Time was of the essence! The SSP Office challengedMarshall’s ET and SRB Projects to design, develop, qualifyand implement an ET observation camera as quickly aspossible. They allotted a maximum of 12 months for com-

pletion of the task. Preliminary assessments by the SRBTeam indicated it would be feasible to mount a miniaturevideo camera into a purpose-built aluminum canister with aheat-resistant window. This canister could be positioned tolook out the side of the SRB Forward Skirt (through anunused connector cover) where it would have the idealvantage point to view the suspect ET insulation.

To expedite the development process, the SRB Teamelected to adapt an existing video recording systemwhich had been flown in the forward skirt for several

 years. This existing system consisted of a miniaturevideo cassette recorder (VCR) and a camera that looked

straight up out of the top of the SRB forward skirt to filmthe deployment of the booster parachutes. For the ETObservation Camera System, the existing VCR was leftin place and re-wired to connect to the new side-lookingcamera. The system would be activated by a built-in “Gswitch” that senses the motion of the Shuttle as it lifts offthe launch pad.

Design, development, and qualification testing ofthe new portions of this camera system proceeded at afever pitch. In addition to doing all the design work,USBI Company also built all the interconnecting cables.The camera canister was fabricated by Benton Machine,

a small fabrication shop in Jacksonville, Florida, and thespecial window was built by the Corning Glass Worksin New York. Vibration and electrical testing wasperformed at MSFC. Final flight certification was com-pleted in early October 1999 and the first flight of thenew system occurred on STS-95 on October 29,1999...start to finish in half the allotted time.

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 42/68

19S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Solid Rocket Booster 

Photo from ET Observation Camera 

The camera system has now flown on 3 flights andwill fly on at least 2 more. Although several of thesehave been night launches, the system has providedexcellent video with the ET illuminated only by ambientlight from the rocket exhaust plumes.

The close-up ascent imagery of the External Tankthat this camera system continues to provide hasproven critical to identifying and understanding thecauses of Thermal Protection System loss. Actionsintended to correct the insulation problem are currentlybeing implemented by the ET Project. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 43/68

20S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Marshall – Space Shuttle Main Engine 

High-Pressure Fuel Turbopump

Development/Certification Status

The certification of the alternate HPFTP was

initiated in July 1998. Testing was suspended inOctober 1998 due to an assembly problem.During this period turbine housing cracks were identi-fied in previously tested development units. Investiga-tion identified hydrogen embrittlement of the IN 100material as the cause of the cracking, and design ofmodifications to eliminate cracking were completed. Thefirst unit tested with all the changes exhibited an out-of-family mode of vibration. An investigation determinedthat some of the modifications to the housing joint werethe most likely cause of the high vibration, and the config-uration was changed to eliminate these, while leaving a

barrier-coating to the housing for protection againstthe hydrogen effects. These modifications have beeninstalled, and certification testing will resume in October1999. Certification is scheduled for completion in May2000 with first flight capability in August 2000. y

Space Shuttle Main Engine Processing Facility (SSMEPF)

 Funding for the new SSMEPFwas approved in

1994, and construction began in 1996 and wascompleted on June 26, 1998. This facility is a

34,600 square foot addition to Orbiter ProcessingFacility (OPF) No. 3. The SSME processing activity wasmoved from Vertical Assembly Building (VAB) in July 1998.The first engines processed through this facility poweredEndeavour on the first assembly flight for the InternationalSpace Station, STS-88, December 4, 1998.

This facility addition provides space to increase thecapacity and efficiency of SSME Operations. Within theSSMEPF there is a low bay with 6 vertical engine stands,a 10-ton crane and full capability of fluids, pneumaticsand avionics to test and check out the SSMEs. It also has ahigh bay with a 15-ton crane, drying cells, pump room,ground support equipment (GSE) storage and workshop.

The three SSMEs generate approximately 375,000lb. of thrust each during liftoff of the Space Shuttle, pro-viding about 20 % of the power needed to boost thespace vehicle into low Earth orbit. They are the onlyreusable liquid-fueled rocket engines inexistence and undergo prelaunch preparation in theMain Engine shop before their installation into theShuttle Orbiters in the OPF. y

 Final Production Build of Pratt & WhitneyHigh-Pressure Oxidizer Turbopump/ Alternate Turbopump (HPOTP/AT)

The last production build HPOTP/AT, unit 8031,was successfully acceptance tested on 5/27/99.This milestone marks the 20th

successfully delivered HPOTP/AT into theSSME Program. HPOTP/AT unit 8031 isscheduled to be flown on STS-103 inDecember 1999 in support of the HubbleSpace Telescope Maintenance mission. TheHPOTP/AT incorporated numerous flightsafety enhancements and a 10-flightinterval between rebuilds. Over 20,000

seconds of flight time have already beenaccumulated by the HPOTP/AT. y

Processing Facility 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 44/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 45/68

22S PACE SH U T T L E PRO GRAM 1999 AN N U AL RE PO RT

Marshall – Space Shuttle Main Engine 

Manufacturing Process Control

Improvements

Rocketdyne has several ongoing initiatives thatfocus on improving the process control of the fabricationand assembly of its products. Data collection on the vari-ous machining processes and material types is beingconducted using Quantum so that the process capabilitycan be quantified and shared with the design communi-ty. Upper and lower control limits are being establishedfor each of these processes and the data is monitored bythe work centers on run charts so that process drift andout-of-family data points can be identified andcorrected as part of the normal operations.

Integrated process management has been adoptedas the methodology for process improvement at

qualify the accelerometer signals and reliably determinethe health of the turbomachinery. A second technologyto be demonstrated is the on-engine examination ofplume constituents using spectroscopy for the purposesof determining engine wear, erosion, and/or breakage.

The third technology to be demonstrated is onboard,real-time SSME performance modeling as a diagnostic,and in the future, a prognostic tool.

An integrated product team was formed in 1997to develop the architecture and implementationapproach for the system. Given the current highreliability and projected life of the Block II controllerand the desire to provide flexibility for future advance-ments in health monitoring in a cost-effective manner, theteam recommended a two-phased approach and distrib-uting the functions.

The first phase involves a one-time upgrade of thecurrent controller to incorporate the synchronous redlinemonitoring portion of the RTVMS and a high- speedinterface to allow external communication.Additionally, us advanced technology, to design,develop, and certify a low-cost, upgradeable healthmanagement computer that would contain an advancedRTVMS, an engine plume analysis capability, and areal-time engine modeling capability. This approachprovides the flexibility to evaluate and utilize advancedalgorithms, instrumentation and monitoring systemswith-out requiring expensive on-engine ground test certi-

fication of the avionics. y

Rocketdyne. It consists of a series of 21 steps thatbegin with flow-charting the process and understandingthe key characteristics of the process. Once the processhas been defined, the subsequent steps help identifyareas for improvement and provide a tool box

containing various process improvement tools. Atthe completion of these steps, the process will undergoa validation review, where the revised process islocked in place.

To facilitate the use of the IPM approach, a steeringcommittee, working-level advisory team, and facilitatorshave been established.

Another critical area for process control is hardwarecleanliness and the elimination of potential sources ofFOD and contamination. Rocketdyne has continued itscommitment to a FOD-free work environment with the

completion of the stack and braze (Whiteroom) workcenter upgrade. In addition, the SSME pump room isundergoing a complete facelift, with new flooring,ceiling, a mezzanine for larger tool storage, new workstations, and new cabinets with all tools and hardwarenested. A renewed focus on production support materialcontrol will further improve our process control in thearea of hardware cleanliness. A new web-basedsystem has been developed to provide visibility to theproduction support materials (PSMS) that have beentested and approved for use on our hardware. All PSMswill be labeled to identify that it has been tested and any

restrictions will be clearly stated on the label, as well asin the new web-based system. Centralized distributionand ordering of PSMs will further enhance the controlover these materials. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 46/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 47/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 48/68

25S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –Vehicle Engineering 

Orbiter Upgrades

Eight radiator panels located inside

the payload bay doorsperform the Space Shuttle Orbiteron-orbit heat rejection. Each panel isapproximately 15.1ft. by 10.5ft. construct-ed of 0.011-in. 2024-T81 aluminum

face-sheets and 3.1-lb/ft 3 5056-H39aluminum honeycomb core. The tubes are6061-T6 aluminum and the panel surfacesare coated with silver-Teflon tape.

System upgrades have been implement-ed to minimize the chance of an impactcausing damage to a cooling tube and potentially

impacting mission success. This upgrade consisted ofredesigning the radiators to include radiatorcooling tube shielding, aluminum stripsbonded on the radiator directly over thecooling tubes, thereby increasing the resist-ance of the radiators to impacts. To allow theOrbiter to have a radiatorpuncture, but limit-ed loss of cooling capability, radiator panelisolation was evaluated and implemented. Inthe event of a puncture, isolation valves andcheck valves have been added to allow the

crew to isolate the leaking radiator from therest of the cooling loop. This allows contin-ued operation of that cooling loop for theother heat rejection systems the Orbiter hasfor on-orbit operation and entry. A leak is annunciatedwhen a drop in the cooling loopaccumulator quantity sensor is detectedand the crew closes the bay 12 checkvalve that isolates the downstream coolingloop from the leak.

The radiator isolation and shieldingmodifications are complete on OV-104, will

be complete in early CY2000 on OV-105,and will be implemented during the nextmaintenance down periods for OV-102and OV-103.

Another safety improvement the SSP implemented wasadditional thermal wing leading edge protection to preventwing structure over temperature/failure and potential loss ofvehicle due to a hole in the wing leading edge. Currentwing leading edge capabilities permit a 1in. hole on the

Typical Radiator Panel Physical Characteristics 

8 Panels per Vehicle 

Radiator Shielding Modification

Radiator Isolation Modification

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 49/68

26S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –Vehicle Engineering 

solid state storage,, and ground-based advanced controlroom equipment and applications.

This flight demonstration successfully demonstrated theability to perform real-time vibration monitoring of SSMEturbopumps, skin temperature measurements as a potential

replacement for intrusive gaseous oxygen probes, use offiber optic sensing for the detection of hydrogen, strainand temperature, use of solid state hydrogen detection,and the use of galvanic cell oxygen detection in a flightenvironment. STS-96 was also the first successful flight use

of X-33 remote health nodes, and the FDDI interface forSpace Shuttle applications.

Additional information on this experiment as well ascontinuing work is available at:http://www.ksc.nasa.gov/shuttle/upgrades/ksc/ivhm /data_depot/ivhmhome.htm

upper surface of any panel. But on the lower surface, nopenetrations are allowed on the lower surface of panels5-13. In these locations, a hole generated by orbital debriswould allow heat from the plasma flow during entry toquickly erode the 0.004-in. thick Inconel foil of the

“Incoflex”insulators. This will cause a loss of insulatingproperties and exposing the leading edge attach fittingsand wing front spar to direct “blast” from the hot plasma.The upgrade to include additional insulation would allowsingle entry with a penetration of up to 0.25 in. diameterin the lower surface of reinforced carbon-carbonpanels 9 through 12 and up to one inch onpanels 5 through 8 and panel 13.

The design team evaluated require-ments for meeting the 0.25 in. requirement.A variety of design requirements also

considered during the evaluation includingminimum weight with no additional post-flight inspections. The implemented designsolution after analysis and testing werecomplete was to add high-temperatureNextel 440 fabric to the Incoflex insulatorswith one layer for panels 5 through 7 and11 through 13 and two fabric layers forpanels 8, 9 and10 (highest heating envi-ronments). Overall weight increase to theorbiter was 53 lb. This hardware is current-ly implemented on OV-103, OV-104 and

OV-105 and OV-102 during the mainte-nance down period.

The IVHM HTD-2 was successfullydeveloped and flown on STS-95 and STS-96. The purposeof these flight demonstrations was the advancing of thedevelopment of selected IVHM technologies in a flight envi-ronment and to demonstrate the potential for reusable vehi-cle ground processing savings.

The focus of the experiment is real-time systemhealth determination of selected Orbiter systems includ-ing the Orbiter’s main propulsion system, SSME and theOrbiter’s power reactants storage and distribution

system. The technologies to be demonstrated includedthe Fiber Bragg-grating photonic sensors for hydrogen,strain, and temperature sensing; smart sensors forhydrogen, oxygen, and pressure sensing; distributeddata acquisition using X-33 remote health nodes, fiberdata distributed interface (FDDI) communication; real-time information processing of SSME pump vibration;

Wing Leading Edge 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 50/68

27S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –Vehicle Engineering 

IVHM Sensor 

Another area of concern for the SSP is theincreased supportability issue with the tape-drivendata storage devices. A project called the modularmemory unit (MMU), was initiated to replace thefunctions of the existing space shuttle mass memo-

ry units, operational (Ops) recorders, and payloadrecorders and integrate these three functions into asingle unit. In addition, an option will be madeavailable to replace the modular auxiliary datasystem recorder function.

The MMU will provide data storage andretrieval capability for flight-critical software,which includes the primary avionics systemsoftware and backup flight system; operationaldata and main engine data (previous OpsRecorder function), and payload data (previous

payload recorder function).The goals for this new development are toincrease performance; eliminate mechanicalmoving parts to increase reliability; reduce unitcount, weight, and power consumption; utilizeoff-the-shelf systems and open systems standardsas applicable, and create a modular design toallow ease of repair and future upgrade.

This upgrade program is a pilot program forfuture consideration of an open architectureavionics design. The MMU is a Versa ModuleEurocard-based open architecture system with

standard modular building blocks, and growthcapacity for future avionics upgrades. Thesebuilding blocks will be considered for use infuture avionics upgrades. y

IVHM HTD Chassis 

IVHM RHN 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 51/68

28S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –Vehicle Engineering 

Orbiter Remote Manipulator

Subsystem (RMS)

There are four RMSs in service and all have now been

upgraded with digital SPAs. Three RMSs were flown inFY1999 with new digital SPAs: STS-95 for the deploy-ment and retrieval of SPARTAN, STS-88/2A for theassembly of the first ISS elements, Zarya and Unity, andon STS-96/2A.1 for EVA support.

The new digital SPA is a microprocessor-baseddesign. The digital SPA upgrade addressedimprovements in safety by eliminating all 21 Criticality1/1 items (loss of life or vehicle) associated with the oldanalog SPAs. This was accomplished by incorporatingextensive self-checking features known as built-in testequipment. Additionally, selectable control loop gain

parameters were added to improve RMS controllabilityof large mass payloads under low-speed conditions.The new design provides increased joint/motor torqueat low commanded speeds for improved operatorcommand authority. This stabilizes the motor control foroperations with heavy Space Station-sized payloadsand allows RMSs with new digital SPAs to handlepayloads up to 586,000 lb (ISS size) as compared tothe analog SPA maximum payload limit of 65,000 lb.

The RMS checkout performed during each RMS mis-sion provides a good benchmark for comparing RMSperformance from mission to mission. The best indica-tion of the overall RMS tracking improvements can beseen in a comparison of analog versus digital SPA linetracking during a standard automatic sequence check-out (where coordinated tracking of all six joints isrequired). Note the improvements in performance, as isseen in the figure.

With the deployment and retrieval of SPARTAN,STS-95 provided a good basis for assessing the impactof the digital SPA upgrades on RMS handling perform-ance with small payloads. As this was a re-flight ofSTS-87, which flew with analog SPAs, it offers a

good comparison of analog versus digital SPA RMS per-formance. During SPARTAN unberth (2945 lb) from thecargo bay, a 70% reduction in the positional payloadtracking error with respect to the operator commandswas observed with the digital SPAs. Position errorsreached 1in. on STS-87 with the analog SPAs and only0.3 in. on STS-95 with the digital SPAs.

STS-88 used the RMS to assemble the first two elements

of the ISS, Unity and Zarya and presented a gooddemonstration of the upgraded RMSs ability to handlemedium and large-sized payloads. At 25,475 lb. theUnity module represented a medium sized payloadwith a large payload center of mass offset. During theUnity unberth there was approximately 1in. of clearancefrom structure. Review of RMS data from flight indicatesthat the RMS tracked very accurately with respect tooperator commands throughout Unity unberth withtracking errors less than 0.3 in. and attitude errors lessthan 0.1 degrees.

At 42,637 lb. Zarya is the heaviest payload ever

handled by the RMS, also with the largest center ofmass offset. Flight data shows that the RMS trackedvery accurately with respect to operator commandsthroughout the FGB capture to pre-install maneuver withtracking errors less than 0.7 in. and attitude errors lessthan 0.2 degrees. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 52/68

29S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –Vehicle Engineering 

STS-88/2A in support of the FGB installation. OnSTS-96/2A.1, camcorder views out the overhead windowsimilar to those required for STS-92/3A were recordedand evaluated postflight.

FY1999 included preparations for two additional

flights, STS-103 (HST) and STS-101/2A.2, to verify

SVS performance in a number of development areas.Mission planning and crew training began for ISS

Flights 3A, 4A, 5A, and 5A.1. In addition, trainingsupport has been provided to ISS increment crews.Three flight loads of SVS software were released

in FY99. Version 4.1.1, flown on STS-88/2A, andVersions 4.2 and 5.0. Since STS-88/2A, there have beenengineering releases 5A through 5G. 5G was producedto verify the data logging and SEU capabilities of SVSduring the STS-103 (HST) flight and will be run in an

Orbiter Space Vision System (SVS)

T

he SVS has seen significant development activitythis past year. The beginning of the fiscal year

saw a tremendous effort to prepare SVS tosupport STS-88/2A. Post STS-88/2A, a number ofnew concepts have been investigated and are beingimplemented in the software to address systemdeficiencies in the areas of operability, robustness, andaccuracy. Because of the short time before operationalneed on STS-92/3A and subsequent assembly flights, thedecision was made not to change cameras or SVS hard-ware, but to work to fully understand the existing hardwareand to mitigate hardware deficiencies with software.

The important features of the development work include:1) Completing the SVS downlink capability,

developing real-time SVS data logging andvideo frame grabbing.

2) Understanding the hardware, from thecameras used as sensors to the inner work-ings of the SVS box itself, including develop-ment of engineering tools for troubleshootingand analysis.

3) Implementing an efficient engineeringsoftware process.

4) Improving system performance and robustness.

5) Radically simplifying the user operationsconcept by using the specifics of eachoperation to automate the procedures.

6) Using the accuracy of the SVS to calibratethe position of the RMS, then using the highprecision of the RMS to continue operationsthrough periods of adverse lighting whenSVS may not be ableto generate anaccurate solution.

The SVS team supportedthree flights in FY1999. STS-95 was the final detailed testobjective (DTO) flight prior toSTS-88/2A and SVS was runduring the SPARTANunberthing and berthing. Asshown in the photo, SVSwas used operationally on

SVS Targets used to dock the FGB to the Node on STS-88 

SRMS-SVS Absolute Co-plots Z SRMS-SVS Absolute Co-plots Y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 53/68

30S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –Vehicle Engineering 

 Flight Crew Equipment Upgrades

The SSP is investigating the integration ofcommercial, off-the-shelf digital televisiontechnology into the Orbiter to support a NASA

initiative to convert NASA operational vehicles to digitaltelevision in the near future. The SSVEO has procureddigital camcorders from several vendors of whom onewas selected and flown on STS-93 andsupported a live downlink from the

Orbiter to ground stations. Furtherevaluations and flight demonstrationswill be performed before fullimplementation into the Orbiter.

A high-definition camcorder,supporting high-definition television,flew as a demonstration on STS-93. Thecamcorder recorded mission highlightsand was used for public affair eventsand crew interviews. This video streamis compressed to a bandwidth that theOrbiter can downlink to the ground.On the ground, the video stream isexpanded to the original format forstorage or distribution. This hardwareis currently in development and willbe ready in FY2000. y

High Definition Camcorder 

unattended mode. The next flight load, Version 10, isexpected to support STS-92/3A.

The last four of the Orbiter SVS hardware units weredelivered. An additional SVS unit was delivered to theISS. A program to upgrade all vision units is nearing

completion. This upgrade included modifications to thevideo-input card to correct accuracy problems identifiedduring ground certification testing.

The graphs above show the performance of the SVSduring STS-88/2A, as analyzed postflight using flightparameters with flight video. The dropouts in SVSsolutions seen in the graphs are directly attributable topoor lighting. A concept of calibrating the RMSdigital position using SVS information has beendeveloped utilizing the measured offset between theRMS and SVS. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 54/68

31S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –Vehicle Engineering 

Avionics and Software

G

eneral-purpose computer (GPS) softwareupgrades during the last year have supportednumerous SSP requirements and operational

improvements. Operational Increments (OI)-26B andOI-27 were developed to support the programís integra-tion of the Global Positioning System (GPS) as a Shuttlenavigation aid to relieve the dependency on the TACANsystem. Both OI’s were flown this year and supporteddetailed test objectives and other GPS/Shuttle systemsengineering and integration activities. STS-96, which wasflown with OI-27 software, demonstrated that the GPCsoftware could support a single-string GPS operationalcapability. OI-27 software is designed to support three-string GPS capability when the GPS system is certified.

The OI-28 software system was developed andverified this year. The system is being configured tosupport first usage in June 2000, on STS-102. Upgrades inOI-28 also support numerous SSP requirements includingsafety, operational improvements, manifesting flexibility,contingency abort upgrades, and support of ISS Programrequirements. The following items are included in OI-28:

ISS Reboost: Adds capabilities to perform either VRCSor PRCS reboost in auto closed-loop mode. Maximizesreboost within load/timing constraints and maintains atti-tude control without crew interaction.

Center of gravity (CG) relief during glide return to

landing system (GRTLS): Provides up to 3 in. CG reliefduring GRTLS to allow payload manifesting flexibility,reduce landing weights, and use OMS propellant ballastrather than lead ballast.

Contingency Abort Upgrades: Automates complexguidance procedures for the entry portion of East Coastabort landings which will decrease vehicle loadings andincrease capability/probability of reaching landingsites. Also modifies the flight control system to preventrolloff during loss of second engine while in high Qportion of RTLS flyback cases where there is sufficientenergy to reach a runway if control is retained. The lossof control scenarios were exacerbated by the additionof the SLWT to the program. Also added was the abilityto uplink additional landing sites and navaid informa-tion during OPS 1,3, and 6 to support abort scenarios.

Uplink of Mass-Related I-Loads: Provides capabilityto uplink mass-related I-Loads to support late manifestingflexibility in terms of CG adjustments and maximizing

performance without rebuilding software mass memories orgenerating and applying patches late in the flows.

On-Orbit Upgrades: Automates -X RCS maneuvers toreduce ground and crew workload. Provides for singleforward jet for -X translation to minimize plume on ISS

arrays and add redundancy to system. Provides capabilityto execute RCS maneuvers in target track to reduce propel-lant usage and decrease dispersions during rendezvous.

Expanded TDRSS Usage Capability: Increases capabil-ity to use up to 4 TDRSS vectors instead of 2 to allow morecontinuous coverage for ISS operations and support.

 Variable Throttle for Aborts: Allows remaining atnominal throttle levels in abort regions that do not benefitfrom increased thrust levels. Improves thermal conditionsand improves abort boundaries for TAL and ATO.

Orbiter Window Protection: Protects forward

and middle window panes against hazing which resultsfrom booster separation motor exhaust plumes duringSRB separation by firing forward up-firing RCS jetsduring separation.

 Ascent Flight Control Upgrades: Expands flightcontrol envelope for heavy, forward payloads in combina-tion with the SLWT. Reduces flight to flight analysis activity.

RMS Precision Improvement: Allows independ-ent calibration of the RMS point of resolution(POR) with theSVS by increasing the precision of the POR specification.

Requirements for OI-29 were baselined this year.Significant items included in OI-29 are support of the

flight operations reinvention activity, support of the FICSthat is a part of the Orbiter Propellant Transfer System(OPTS) being developed, upgrades to the On-OrbitFlight Control System to support automatic ISS reboostthrough station assembly complete, and modifying theinterface between the GPCs and the MEDS system toallow the MEDS system to have access to more data insupport of cockpit upgrade activities. OI-29 is expectedto support launches starting in September of 2001.

Planning for OI-30 also began this year. Softwareto support the OPTS is being assessed at this time. Theavionics upgrade and cockpit council team activities are

being supported to ensure appropriate software supportis provided.

The MEDS provides the human-machine interfacebetween the crew and the Orbiter Data Processing Systemvia 11 graphical displays. MEDS is a state-of-the-art inte-grated glass cockpit system, which utilizes large color flatpanel, Liquid Crystal Display (LCD) multifunction displays.

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 55/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 56/68

33S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –Customer and Flight Integration

Johnson Space Center –System Integration

 Flight Preparation Template Reduction

T

he SSP is striving to reduce the flight prepara-tion time from flight baseline to launch for

standard type missions to 12-months or less.Currently, the flight preparation activities for the STS-99,STS-102, STS-104, and STS-107 missions are beingexecuted on a schedule consistent with a 12-monthTemplate. To date, SSP organizational elementshave been able to maintain their respective schedulessupporting these missions. Further potential reduction in theSSP preparation template is possible. Organizationalagreements and process changes necessary to executemission preparation activities within an 11-month

Systems Safety Update of Integration

Hazard Reports

In 1998, USA undertook an initiative to updateall Integration Hazard Reports (IHRs) to meet thecurrent Program requirements of NSTS 22254,

“Methodology for Conduct of Space Shuttle ProgramHazard Analyses.” Theserequirements were revised

in 1991 and 1993,requiring that all 78 IHRsbe revised to be compli-ant. However, budgetaryrestrictions imposed onthe Program at that timenecessitated the updatingof the IHRs on an opportu-nity-only basis, such thatIHR updates were onlyperformed as other Pro-gram changes required.

The result of this policywas that only 19% of theIHRs were updated toNSTS 22254 complianceover a 6-year period.(See Figure at right.)

Integration Hazard Report Update History 

template is known and understood. However, at this timethe SSP has chosen to further demonstrate its ability to

successfully execute the 12-month template. This will betterensure process maturity and stability before additionalschedule reductions are attempted. A further mitigatingfactor toward successful demonstration of the 12-monthtemplate has been a shift in launch dates resulting fromexternal factors. There have been limited opportunities forthe SSP to execute our preparation templates without someexternal factor changing a launch date, thus extending thepreparation template. Template reduction is an ongoingactivity and will continue when appropriate. y

Within 5 months of the beginning of the USAinitiative, 24 additional IHRs were updated to thecurrent requirements, bringing the compliance rate to50 %. An additional 4 IHRs were updated in the next 3

100

90

80

70

60

50

40

30

20

10

0

DATE

   C  u  m .   %

  o   f   I   H   R  s   C  o  m  p   l  e  t  e

   J  a  n -   9

   2

   J  a  n -   9

   3

   J  a  n -   9

   4

   J  a  n -   9

   5

   J  a  n -   9

   6

   J  a  n -   9

   7

   J  a  n -   9

   8

   J  a  n -   9

   9

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 57/68

34S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –System Integration

Vehicle Standardization

The PRCB approved a short-term strategy to stan-dardize the payload interfaces on ISS assemblyflight vehicles, OV-103, OV-104 and OV-105.

By constraining modifications, secondary payloads(including DTOs, and vehicle changes that impactreconfiguration engineering products, swapping ofthe ISS assembly flights can be decoupled from theengineering products and not result in launch delays oradditional costs.

This eliminates the need to produce new engineer-ing and hardware that incorporates vehicle differences,

and the generation of new KSC work authorizing docu-ments. Benefits resulting from a standardized aft flightdeck and payload bay configurations include manifestflexibility, simplified training, predictable ground pro-cessing, and vehicle swap cost reduction. Drawbacksinclude constraints to some orbiter modifications thatimpact to reconfiguration products, a diminished mani-festing flexibility for DTOs, DSOs and secondary pay-loads that are incompatible with Orbiter standardservices and a diminished flexibility in weight andC.G. “get well” capability. y

Reductions in Thermal and Structural Cargo

Verification Analysis Cycles

As part of the continuing efforts of implementingSSP initiatives, several improvements andenhancements have been realized in the

thermal and structural analytical verification processes.These enhancements along with the many other improve-ments in work by other Program elements are evidenceof the SSPs commitment to continuous improvements tobetter serve Shuttle customers and NASA.In the thermal

analysis area, a number of improvements in the analysisprocess have been developed and implemented to enablethe analysis cycle time to be reduced from a 12-month tem-plate to a 9-month template, effective October 1999. Oneimprovement has been the implementation of more formal-ized coordination between the SSP and all the payloadcustomers through the pre-verification thermal analysisreview. This early meeting in the thermal analysis cycleestablishes clear lines of communication and ensuresunderstanding of what is expected of all parties and theschedules and milestones for all subsequent activities.

Additional process improvements have included the acqui-sition of latest workstation hardware which provides a fac-tor of approximately 7 reduction in the execution time forthe important analysis tool, the Thermal Synthesizer Systemand its routines. In addition, the latest version of the SINDAthermal analyzer has been installed and reviewed for com-patibility with the local host hardware. In this process, inef-ficiencies were identified and corrected, resulting inimproved compilation and execution times.

Numerous efficiencies have been developed andintroduced in the area of software tools. Many aspects ofthermal analysis were formerly extremely manpower

intensive. Software has been developed to automate taskssuch as preparing graphical representations of the verydetailed math models for inclusion in model documenta-tion, screening large volumes of prediction data againstthe known payload system thermal limits and flagging thelimit violations, and organizing analysis output directly intothe formats needed for the verification documentation.Perhaps the most important parameter and variable inmission verification thermal analysis is the on-orbit attitudesequence. Software has also been developed to use theelectronic versions of on-orbit attitude timelines to maketimeline comparisons and to automatically create the input

data to drive the TRASYS models (the math models used togenerate the transient heating rates for the thermalmodels). Each of these recently automated tasks waspreviously very tedious and time-consuming for thethermal analyst, which contributed significantly to thelength of the thermal analysis template. An addedbenefit of these efficiencies is the improvement in thequality and usefulness of the analysis product.

months, for 55 % compliance. The remaining 35 IHRswere completed within 8 months, bringing all 78 IHRsinto compliance with NSTS 22254 by April 1999. Thecontents of the updated IHRs were also thoroughlyrevised to enhance the level of technical detail provided,

and to capture the Program hardware, software, or opera-tional changes that had occurred since return-to-flight, suchas the Performance Enhancements. The performance ofthis effort was on a non-interference basis with all otherSafety related tasks. These updated IHRs contribute to agreatly improved Program safety risk baseline, enablingUSA to more quickly assess safety risk for future changes inthe Space Shuttle configuration and operation. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 58/68

35S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –System Integration

reducing the report preparation time. The VLA datadump procedure was improved by placing the data ona public server, rather than individual transmittals.Sidewall payload model generation was improvedfrom days to hours by development of an automated

coupling program.The above enhancements and improvement have

allowed a further reduction in the VLA cycle time to beimplemented this year. The L-10 cargo element mathmodel delivery date has now been changed to L-8.5 forthe generic VLA template. This represents a 19% cycletime reduction in the 8 months of the generic template thatis directly attributable to the structural analysis requirement.

As with the process improvements already adoptedand currently being incorporated, a major objective offuture improvements will be the maintenance or improve-

ment in the quality of the SSP thermal and loads analysisproducts as a contribution to continued SSP success. y

Other improvements in the thermal analysis processare ongoing, with the objective of further reducing theverification analysis template from 9 months to 7 months,effective October 2000. In view of the number of jointShuttle/Station missions in the near future and the complex-

ity of the hardware elements and operational scenariosinvolved in those missions, achieving compatible thermalanalysis methods and products is an important goal forimproving overall efficiency for NASA.

Several structures process/product improvementswere implemented in FY99 which provided a structuralanalysis cycle time reduction and provided increasedmanifest flexibility. The most notable process improve-ment was the incorporation of the Manifest UncertaintyFactor (MUF) into the VLA. This process applies a smalluncertainty factor to all VLA first cycle results which the

Orbiter, payload integration hardware, and cargo ele-ments analysts must verify to. Should a second VLA analy-sis be required, as a result of a manifest orpayload change, a comparison table is developed thatcompares the second cycle results to the first cycle resultswhich includes the MUF. The table is provided to eachcargo element analyst and only the items which increasedare required to be further analyzed. This significantlyreduces analysis time for all parties. This approach wassuccessfully implemented for STS-95, STS-96 and STS-101.With the similarity between the STS-96 and STS-101 cargobay manifests, a variation of the above-described two-

cycle VLA process is being used. The final STS-96 VLAresults will be used in place of the normal first-cycleSTS-101 results. This permits a single VLA cycle to beperformed for STS-101 starting at L-4.5.

Other notable items include the increased staffexperience with the ADVANS automation tool. KeyADVANS-related enhancements included rehost of theQuasi-Static Deflection program to a local workstation;creating a library of modular inputs for ADVANS jobdevelopment; and the ADVANS/MFCP program nowautomates the Performance Enhancement Orbitercapability assessments, eliminating a hand-off for

detailed stress analysis. Shuttle math model develop-ment was improved by developing a standard approachfor main engine and ballast weight incorporation.

Bridge/Latch/GAS Beam stress analysis automationhas been implemented that now creates output that isdirectly insertable into the VLA report. In addition, theVLA report is now in technical memorandum format,

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 59/68

36S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –System Integration

SES Scene Generation Upgrades

T

he SSP has upgraded its visual scene imagegenerating capability for crew training andengineering studies to better support ISS assembly

requirements. In March 1999, the SSP agreed to theconcept of hardware standardization to support commonsoftware compatibility, and training commonality andcontinuity within the major engineering and crew trainingsimulation facilities. The SSP is replacing its aging IGs thathave a 3K-polygon capability with Silicon Graphics Inc.(SGI) IGs that have a 50K-polygon capability. The addedpolygon capability allows very detailed real world visualscenes to be displayed during crew training simulationsand engineering studies. The SSP and USA have commit-ted to upgrading the IGs in the SES, the Shuttle Mission

Simulator (SMS), and the SAIL. The upgraded IGs allowthe SSP to take further advantage of the software capabili-ty in the Virtual Reality Laboratory (VRL). Over the pastthree years, the VRL has developed the renderingsoftware and modeling tool software that support verydetailed on-orbit visual models that are required tosupport Space Shuttle and ISS on-orbit EVAs. The VRLrendering software and modeling tool software will beinstalled in each new SGI IG, that will allow visual sceneloads to be shared between the VRL, the SES, the SMS,and SAIL, and used in desktop simulation trainers. TheSES Dome IG upgrade was completed in September

1999. The SAIL IG upgrade will be completed in October1999. The SMS Aft Guidance and Navigation SimulatorIG upgrade will be completed in December 1999, in timeto support the STS-92 (ISS-3A) crew training activities. TheSMS IG upgrade to the Aft Fixed-Base Simulator will becompleted in the third quarter of FY2000. In addition, theIG upgrade in the SMS will permit EVA simulations fromeither the VRL or the Neutral Buoyancy Laboratory to beadded to joint integrated simulations. The SSP alsopresented this upgrade to the ISS Program, and since theSMS and Space Station Training Facility perform

combined training, the ISS Program initiated activities this year to also upgrade their Space Station Training FacilityIG to an SGI to maintain system compatibility with theSMS and the SSP. The SSP has made a significantupgrade that greatly improves crew training for ISSassembly missions, ensures safer Shuttle missions, andimproves mission success capability. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 60/68

37S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –System Integration

Ascent Postflight Reconstruction and

 Flight-Derived Dispersion Update

 Flight-derived dispersions were updated for the

Space Shuttle during 1999. This postflightreconstruction product updates uncertainties used in

performance calculations for Shuttle missions. Updateswere made to trajectory parameters such as angle ofattack and dynamic pressure. The 1999 flight-deriveddispersion updates were based on 68 Shuttle missions.

Flight-derived dispersions are typically less than thespecification dispersions that were originally used inShuttle performance calculations. As a result, flightperformance reserve (FPR) has reduced 1200 lb. Thischange is equivalent to approximately 1200 lb improve-ment in payload to orbit. A significant reduction indynamic pressure dispersion during ascent supersonicflight, shown in the attached figure, has been baselined,resulting in enhanced launch probability underday-of-launch conditions. y

1999 Flight-Derived Dispersion Update Reduces Q Uncertainty 

55

50

45

40

35

30

25

20

15

10

5

0   D  y

  n  a  m   i  c   P  r  e  s  s  u  r  e   (   Q   )   U  n  c  e  r  t  a   i  n  t  y   (  p  s  t   )

0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 2.2 2.4

1997

1999

Mach 

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 61/68

38S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center –System Integration

Ascent Performance Enhancements

 Flight Summary

T

he primary objective of performanceenhancement upgrades was to provide 13,000

lb of additional payload capability for ISSmissions. This objective was driven by the need toprovide the ISS Program with a total of 35,000 lb ofpayload capability for Space Station missions at a51.6-degree inclination. To achieve this goal, the entireSSP embarked on performance enhancement upgradesto the Shuttle System. Following appropriate studies, Pro-gram reviews resulted in approval of enhancements con-sisting of hardware modifications, software changes, flightdesign updates, and consumables budget optimizations.Altogether the performance enhancements provide inexcess of 17,000 lb of additional payload capability

for the Orbiter. Exceeding the original performancegoal set forth in 1994 has allowed the SSP to increaseits commitment to the ISS Program from 35,000 lbto 36,200 lb. y

 Ascent Performance Enhancements Flight Summary 

NormalPerformance STS-95 STS-88 STS-96 STS-93Increase* (lb)

Date 29-Oct-98 4-Dec-98 27-May-99 23-July-99

Orbiter 103 105 103 102Inclination/Altitude

H ARDWARE/CONFIGURATION CHANGESSLWT 7500 98 97 100 99SSMEs: Phase 2 – E1,2,3

Block 1A – E3Block IIA (104.5%) 500 E1,2,3 E1,2 E 1,2,3

FLIGHT DESIGN

FCS Filters – X X X XSRB Sep Yaw Gain/Constant Pitch 50 X X X XOnboard DEL PSI 500 X X1st & 2nd Stage Gimbal Change 395 X X X XRoll-to-Heads-up – X X X XSRB Sep Timer Optimization 60 X X X XMECO alt-52 nm 740 X X

OMS Assist 250 X XHigh-Q Mission 800-1300 X X X

* 17,000 pound commitment (PRCB 4/7/98) also includes enhancements to Orbiter, crew & cargo equipment, and consumables budgeting.

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 62/68

39S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Johnson Space Center–Mission Operations 

 Flight Operations Reinvention

A major new initiative by theMission Operations Directorateand USA was initiated inSeptember 1998. This initiative,

called Flight Operations Reinven-tion, is intended to restructure and

streamline the flight preparation, flightcrew training, and flight execution processes. This restruc-ture effort will transform our current legacy processes intomodern production-oriented processes. The primary bene-fits will be more effective and efficient operations, atreduced costs, and significantly reduced manifest templatelengths. This restructure effort will provide the SSP

increased flexibility in making manifesting decisionssignificantly later than the current manifest template. Inaddition, this effort will enable flight operations to be moreflexible in responding to Program manifest changes.

Flight Operations Reinvention will enableopportunities to shorten the SSP flight preparation templatefrom 12-months to approximately 7-months. Additionalchanges will facilitate more effective crew training andflight controller certification capabilities. In addition, thecapability to conduct mission operations support activitiesfrom locations remote from the Mission Control Centerwill be demonstrated. These increased process efficiencies

will reduce the required infrastructure necessary to sustainthe capability for flight operations to plan missions, andtrain flight crews.

The implementation of Flight Operations Reinvention isdependent upon several key enablers and projects. Threemajor reinvention themes define the primary reinventioninitiatives. The themes are a major restructuring of howpayloads are supported in the flight preparation processesand in the onboard computer systems, a quicker and moreflexible flight design capability, and new crew trainingprocesses that rely less on detailed mission specific

training and more on generic distributed training.The primary enabler for Reinvention is the eliminationof payload software and payload data processing fromthe current onboard systems management GPC. Reinven-tion will implement an independent cargo computer(Cargo PC) which provides payload data display andpayload command control capability to the crew. Thissystem will allow a quicker preflight reconfigurationprocess and minimize the impact of payload changes to

the critical GPCs. A new Payload Operations SupportTeam (POST) will be responsible for interfacing with thepayload customer and support the development of theCargo PC products required to support flight production,crew training, and actual mission execution. This

POST activity will be critical to meeting the 7-monthtemplate goal.

 Just-in-time flight design implements changes inthe flight preparation processes that will enable theflight-specific design to be generated late in the produc-tion process. This will ensure that only one missiondesign cycle will be required per flight. Just-in-timeflight design will have increased day of launch uplinkcapability and will relying more on standard missiondesigns for repeat missions such as the ISS missions.

Training for Shuttle missions will be streamlined by

the utilization of generic flight software builds, the imple-mentation of the Cargo PC system, the delivery of pay-load models for training by the customer via the POSTteam, and through generic ascent/entry training.

A detailed program-wide system requirementsreview was conducted in September 1999 toformally review the integrated operations concept andthe system integration plan. This review was supportedby all the various Program elements and stakeholders.Completion of the SRR review provided the technicalbaseline required for formal authority to proceed withfull-scale implementation of the Flight Operations

Reinvention initiative. Mission baselines utilizing thereduced template and reinvention processes areprojected for July 2002. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 63/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 64/68

41S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Kennedy Space Center– Shuttle Processing 

Checkout and Launch Control

System Progress

One of the primary Shuttle upgrades and major

KSC projects supporting the SSP is the CLCS.CLCS is currently under development at KSC toreplace the Launch Processing System, which has beenused for Space Shuttle checkout and launch supportsince the 1970s. CLCS will essentially replace all thecontrol room computers and software with state-of-the-arthardware and software. Five other sets will also bereplaced, including one at the SAIL at JSC, the set usedfor OMS pod checkout at KSC, a payload processingset at KSC, a monitor-only set at Dryden, and a set usedfor main engine processing at KSC.

The CLCS will feature several major improvements

over the Launch Processing System, including thecapability to monitor more than one Orbiter from thesame control room. A single engineer will be able tomonitor multiple vehicle subsystems from one console.The engineer on console will have electronic access toa variety of data and tools, which will enhance theengineer’s capability to perform a job, includingdrawings, advisory tools, problem reports, trendingdata, and work control information. The system willalso provide the capability for an engineer to issuecommands to the Orbiter remotely rather than onlyfrom the control room.

Benefits of the CLCS include reduction in amount ofhardware and software that must be maintained,reduction in the facility space required, increasedreliability of the hardware, and more efficient use ofoperations and process engineering personnel.

and, therefore, has high ozone depletion potential. It is

no longer legal to produce R114, and phasing it out ofuse began on January 1, 1996.USA Ground Operations CFC Reduction Plan had

dramatically reduced the consumption of CFCs since1994, and it was planned to replace CFCs with anon-CFC refrigerant (R124) by 2001. However, existingreserves of R114 would not last through the current

 year, and procurement of additional R114 was costprohibitive. Through the efforts of a team of NASA andUSA engineers, the replacement project was completed2 years ahead of schedule in 1999. The team replaced24,000 lb of refrigerant at 12 sites, in 32 end items,

during available windows of opportunity,while continuing to support routine operations and main-tenance tasks. Additionally, steps were initiatedfor the resale of the recovered R114, which has resultedin a $60,000 credit, to date, toward the futureprocurement of R124. As a result of this project, CFCshave been eliminated from all ground coolingprocessing operations at KSC.

Orbiter Onboard Cooling SystemsKSC is also exploring replacements for the onboard

Freon-21 (a CFC) and R22 (a hydrochlorofluorocarbon,

which are used in our ground cooling and purge unitchillers. The replacements will be hydrofluorocarbons,which do not contain chlorine atoms.

FacilitiesSpace Shuttle Main Engine Processing Facility :

The 34,600-square-foot SSMEPF became fully opera-tional in FY99. This new facility, built adjacent to theOPF 3, is contributing to improved efficiency of engineoperations as well as significantly reducing safety riskby moving main engine processing out of the VAB. Thisstate-of-the-art facility provides substantially increased

capability along with safety and operational improve-ments for the SSP, including the following:

• Upgrades the Facility and GSE Systems tosupport Block II engines.

• Reduces distance traveled by SSMEbetween engine/Orbiter removal andinstallation (OPF to VAB).

Environmental Improvements

Orbiter Ground Cooling SystemsR114, a chlorofluorocarbon (CFC)-type refrigerant

used to provide Orbiter ground cooling at all Orbiterground processing sites, has become a target forenvironmental improvement. The ozone layer of thestratosphere is very thin and susceptible to damagefrom chlorine atoms. R114 contains chlorine, fluorine,and carbon, which combine to become a very stablemolecule that cannot break down without exposure tovery high ultraviolet radiation found in the stratosphere

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 65/68

42S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Kennedy Space Center– Shuttle Processing 

Fixed Service Structure elevators were replaced. Thisincluded rebuilding and replacing the cableway andshaft, as well as installing new cars (cabs) and theelevator controls.

The Payload Changeout Room (PCR) walls were

repaired, and the PCR ceiling was modified into anopen plenum to support the heating, ventilating, and airconditioning system. Three new pressure-sealing doorswere added to facilitate access to the HEPAfilters that help purify the air as it enters the PCR.

Safe HavenThe Safe Haven project maximizes the protection of

Shuttle flight hardware by providing short-term storagecapability for a partially or fully stacked vehicle in HighBay 2 of the VAB. This effort will also increase operationaland manifest flexibility, especially during the hurricane

season, by giving KSC managers the option of rolling afully stacked Space Shuttle vehicle into the VAB High Bay2. Historically, High Bay 2 has been used only for ETcheckout and storage and offered no access to theCrawler Transporter/MLP.

The Safe Haven project will enable vertical flighthardware processing operations to simultaneouslyproceed on all three MLPs at any given time. Currentlyduring hurricane season, vertical processing issignificantly restricted to only allowing two full stacks tobe completed. The third stacking operation is restrictedto only the two aft segments.

Implementation of the internal VAB and externalCrawlerway components of this project is beingperformed under two separate contracts. Constructionfor the external Crawlerway effort began in August1999, and construction for the internal VAB work isexpected to begin in October. Work under bothcontracts and an operational checkout of VAB HighBays 2 and 4 are expected to be completed before thebeginning of the year 2000 hurricane season. y

• Provides six vertical engine stands toenhance parallel processing andeliminate OSHA concerns.

• Provides major SSME maintenance off line.• Provides engine drying area with oxygen

monitors and installs all controls in a separatecontrol/monitoring room.

• Equips each vertical stand with upgraded GSEto decrease system pressure losses and incorporates safety lockout devices on valves.

• Provides separate engine lower-head leak testarea with heating, ventilating, and air condition-ing system that reduces GSE background duringencapsulation testing.

Launch Complex 39ADuring the 8-month period from December 14, 1998,

through August 3, 1999, Pad A underwent a downperiod to implement many significant upgrades andimprovements.

The hypergolic oxidizer lines THAT support the orbiterOMS/RCS systems were replaced. These are4-in., stainless steel lines that carry oxidizer from theoxidizer storage facility up to the Pad Fixed ServiceStructure and Rotating Service Structure to service thevehicle. The old lines first had to be decontaminated,then cut apart. New lines were pressure tested, thencleaned and decontaminated. The system was flushedwith nitric acid to remove any free iron, then drainedand dried. The final demonstration of system integrityand readiness was accomplished through a “hot flow”in which oxidizer was actually flowed through the newlyinstalled lines.

The 9099 interface tower walls were replaced. The9099 interface provides the electrical connections to theMobile Launch Platform (MLP) when it is located at thePad. All four walls of the 9099 interface tower werereplaced because of corrosion issues with the old walls.The new walls are composed of prestressed concrete.The steel structure of the 9099 tower was also rebuilt,

repaired, and repainted.The Pad surface underwent major repairs. The more

than 100 panels that make up the Crawler Transporterpath on the Pad surface were removed, stripped, andrepainted. This was an extraordinary effort since eachpanel weighs approximately 16 tons. The area underthe panels was rehabbed with a new, flowable fill, andnumerous small cracks in the supporting substructurewere filled with a pressure-applied epoxy grout.

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 66/68

43

S PACE SH U T T L E P RO GRAM 1999 AN N U AL RE PO RT

Kennedy Space Center– Shuttle Processing 

Y2K Compliance and Certification Test

T

he Space Shuttle Program (SSP) formed a Year2000 (Y2K) Working Group (WG) in August

1998 to bring a program focus to the myriad ofactivities necessary to ensure Y2K compliance for allflight and supporting systems. Over twenty-five teammembers from Shuttle projects, elements, and majorsupport contractors from across the Agency as well aspersonnel from Station and SOMO participated inweekly teleconferences to share status information andcoordinate Program-related Y2K activities. Theseactivities included providing a complete inventory, cate-gorization, and certification of all systems to NASAHeadquarters and Office of Management and Budget.The thousands of individual software, hardware and

firmware items which support the SSP were document-ed, assessed, and run through rigorous Y2K certificationtests. These lower level subsystems were rolled up intohigher-level inventory items for reporting certificationofcompliance by the various project and element manage-ment levels by March 31, 1999. Y2K contingency plansand zero day strategies for the Y2K rollover have alsobeen developed and reviewed by SSPY2KWG mem-bers. Follow-on activities include continuing to ensurethat new systems introduced into the infrastructure meetY2K compliance requirements and that “new finds” are

reported and appropriate actions are taken to bringthese systems into compliance.On October 20, 1999, the SSP Manager requested

a fully integrated end-to-end (ETE) testing of pre-flight, real-time, and post-flight support systems and networks in orderto verify integrated Y2K compatible operation. TheSSPY2KWG members and other technical systems expertshave actively participated in defining the scope and partic-ipating systems for the post-certification Y2K integratedETE simulations. The culmination of these tests is an inte-grated Launch Day simulation with an orbiter on the pad.A Test Readiness Review will be scheduled one week prior

to the implementation of the test. This test is currently inte-grated into the STS-99 pad flow. If OV 105 does notarrive at the pad in time for testing prior to the end of the

 year, the Y2K ETE test will be run with the first mission Ter-minal Countdown Demonstration Test in the year 2000.

The extensive amount of Y2K testing and the focuson configuration management and controls are helping toensure that the SSP and all its supporting projects andelements are flight ready for the Year 2000. y

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 67/68

8/8/2019 1999 Shuttle Ar

http://slidepdf.com/reader/full/1999-shuttle-ar 68/68