FM Cell 13 TPM
-
Upload
anurag-srivastava -
Category
Documents
-
view
220 -
download
0
Transcript of FM Cell 13 TPM
-
7/28/2019 FM Cell 13 TPM
1/2
Improvement
Activity
TPM
Total Productive Maintenance
Peter Rogers
Senior Consultant
Company
Federal Mogul
(Ferodo)
Richard Hollister
Senior Production Manager
Kaizen Case Study
Company Background
Federal Mogul Friction Products based in Chapel-en-le-Frith manufactures Brake Pads
for supply into automotive and transportation market sectors.
The site is undertaking a lean transformation consolidating its operations from the
current two sites into one Building. The vision for the one building project is of a plant
running at high efficiency using Just in Time methodology positioning itself as a world-class first tier supplier.
The main focus of the improvement activity is to understand and to implement TPM
(Total Productive Maintenance) methodology to increase machine performance, output,
on time delivery and inventory reduction.
Kaizen Activities Deployed
An improvement project utilising a cross function team was undertaken on cell 13. Cell 13is one of 6 cells that converts raw mixture into formed brake pads.
Improvement activities undertaken included :-
Operator lean awareness
Development and deployment of daily OEE
5S
TPM resulting in routine asset care to ensure
machine performance
www.uk.kaizen.com
Results
OEE increase from baseline of 60% to 85% after 12 weeks following the activity
Improvement of workplace organisation and reduced health and safety incidents
Increased understanding, accountability and responsibility of the cell by the operating staff
Asset care routines established for by operating and maintaining staff
Improved data collection routines and visual management
26% increase in capacity resulting in 8,500 extra brake pads per week Further defined and agreed plan to increase the OEE to 95% thorough further Kaizen activity
Page 1 of 2
-
7/28/2019 FM Cell 13 TPM
2/2
Improvement
Activity
TPM
Total Productive Maintenance
Peter Rogers
Senior Consultant
Company
Federal Mogul
(Ferodo)
Richard Hollister
Senior Production Manager
Kaizen Case Study
www.uk.kaizen.com
Page 2 of 2
0
10
2030
40
50
60
70
80
90
W46
W47
W48
W49
W50
W51
W 1 W 2 W 3 W4 W5
Cell 13 Weekly OEE OEE Data Collection
Availability from 67% to 90%
Performance from 86% to 90%
Quality consistently at 99%
OEE(Overall Equipment Effectiveness)
from 60% to 85% in a 12 week period
5S
5S workshop completed
Improved health, safety and ergonomics Increased operator value add
Visual standard on the cell showing hour
by hour line standard
Improved operator ownership
Audit mechanism in place
1st level machine refurbishment
TPM
Increased understanding of the asset
using criticality assessment methodology
2nd level machine refurbishment following
condition appraisal path
Asset care routines defined by operator
and tradesman resource
Critical spare parts established
Reduction of fire-fighting activity Consistent machine output