FM Cell 13 TPM

download FM Cell 13 TPM

of 2

Transcript of FM Cell 13 TPM

  • 7/28/2019 FM Cell 13 TPM

    1/2

    Improvement

    Activity

    TPM

    Total Productive Maintenance

    Peter Rogers

    Senior Consultant

    Company

    Federal Mogul

    (Ferodo)

    Richard Hollister

    Senior Production Manager

    Kaizen Case Study

    Company Background

    Federal Mogul Friction Products based in Chapel-en-le-Frith manufactures Brake Pads

    for supply into automotive and transportation market sectors.

    The site is undertaking a lean transformation consolidating its operations from the

    current two sites into one Building. The vision for the one building project is of a plant

    running at high efficiency using Just in Time methodology positioning itself as a world-class first tier supplier.

    The main focus of the improvement activity is to understand and to implement TPM

    (Total Productive Maintenance) methodology to increase machine performance, output,

    on time delivery and inventory reduction.

    Kaizen Activities Deployed

    An improvement project utilising a cross function team was undertaken on cell 13. Cell 13is one of 6 cells that converts raw mixture into formed brake pads.

    Improvement activities undertaken included :-

    Operator lean awareness

    Development and deployment of daily OEE

    5S

    TPM resulting in routine asset care to ensure

    machine performance

    www.uk.kaizen.com

    Results

    OEE increase from baseline of 60% to 85% after 12 weeks following the activity

    Improvement of workplace organisation and reduced health and safety incidents

    Increased understanding, accountability and responsibility of the cell by the operating staff

    Asset care routines established for by operating and maintaining staff

    Improved data collection routines and visual management

    26% increase in capacity resulting in 8,500 extra brake pads per week Further defined and agreed plan to increase the OEE to 95% thorough further Kaizen activity

    Page 1 of 2

  • 7/28/2019 FM Cell 13 TPM

    2/2

    Improvement

    Activity

    TPM

    Total Productive Maintenance

    Peter Rogers

    Senior Consultant

    Company

    Federal Mogul

    (Ferodo)

    Richard Hollister

    Senior Production Manager

    Kaizen Case Study

    www.uk.kaizen.com

    Page 2 of 2

    0

    10

    2030

    40

    50

    60

    70

    80

    90

    W46

    W47

    W48

    W49

    W50

    W51

    W 1 W 2 W 3 W4 W5

    Cell 13 Weekly OEE OEE Data Collection

    Availability from 67% to 90%

    Performance from 86% to 90%

    Quality consistently at 99%

    OEE(Overall Equipment Effectiveness)

    from 60% to 85% in a 12 week period

    5S

    5S workshop completed

    Improved health, safety and ergonomics Increased operator value add

    Visual standard on the cell showing hour

    by hour line standard

    Improved operator ownership

    Audit mechanism in place

    1st level machine refurbishment

    TPM

    Increased understanding of the asset

    using criticality assessment methodology

    2nd level machine refurbishment following

    condition appraisal path

    Asset care routines defined by operator

    and tradesman resource

    Critical spare parts established

    Reduction of fire-fighting activity Consistent machine output