Status report SOLEIL September 2006

22
ESRF: september 2006 Status report SOLEIL September 2006

description

Status report SOLEIL September 2006. Accelerator status. Storage ring is now operational First turns done on the 14th of May 2006 First beam stored the 1st of June 2006 8.35 mA during 10 minutes 4 weeks of continuous operation 24H/24H in June and July 2006 Up to 117 mA. - PowerPoint PPT Presentation

Transcript of Status report SOLEIL September 2006

Page 1: Status report SOLEIL  September 2006

ESRF: september 2006

Status reportSOLEIL

September 2006

Page 2: Status report SOLEIL  September 2006

ESRF: september 2006

Accelerator status

• Storage ring is now operational• First turns done on the 14th of May 2006• First beam stored the 1st of June 2006

• 8.35 mA during 10 minutes

• 4 weeks of continuous operation 24H/24H in June and July 2006

• Up to 117 mA

Page 3: Status report SOLEIL  September 2006

ESRF: september 2006

Accelerator status

• Still to be done : • New stuff to install and test

• Insertions devices • New diagnostics• Slow and fast orbit feedbacks• Top up operation

• Heavy work to be scheduled• On the cold water fluilds distribution network (for magnet

cooling system)

• 10 weeks of Storage Ring operation are scheduled before end of 2006

• Part of the time will be dedicated for beamlines commissioning

• Leaving the construction phase • Entering slowly the operation

phase

Page 4: Status report SOLEIL  September 2006

ESRF: september 2006

Beamlines status

• First beam on 2 beamlines is scheduled next week– DIFFABS: Diffraction and absorption beamline

• With last generation 6 circles Kappa diffractometer

– TEMPO : Time resolved Experiments on Materials with PhOtoelectron spectroscopy

• With SCIENTA detector

• 6 others beamlines should get beam before end of 2006

• Entering the commissioning phase

Page 5: Status report SOLEIL  September 2006

ESRF: september 2006

Control status

Page 6: Status report SOLEIL  September 2006

ESRF: september 2006

Control and Acquisition Electronics: current status on accelerators

In operation : • More than 100 PLC in

operation• 15 Control Systems• 60 CompactCPI crates• More that 3000 cables

connected to Control units

The timing system: • Installed in less than one

year between the call for tender and deployment

• A master system distributes software messages to about 20 local CPCI boards which generate clocks and pulses to equipments

T e s t Master

Slave board

Slave 2

176.101 Mhz 2.94 hz

Optical coupler

Optical fiber

Optical coupler

Page 7: Status report SOLEIL  September 2006

ESRF: september 2006

The Ethernet network is now fully operational 1 main node 21 secondary nodes distributed around the Machine Up to 900 ethernet connections are cabled and operational Wifi network will be installed this summer (used only during

shutdown periods)

Network & Computers infrastructure is ready for exploitation phase

About 40 linux rack mounted servers are operational and provide:

•Required network services (DNS, DHCP, LDAP, NTP, ..)

•Tango Services (configuration, archiving, etc ..)

•Support for GlobalSCREEN Applications

•Support for high level Tango DeviceServers (calculations, etc ..)

A filer provides 1 Terabyte of storage space

•its backup solution is also operational

About 30 operator stations are operational

TX

Page 8: Status report SOLEIL  September 2006

ESRF: september 2006

The DeviceServers

Status of the Control System

Page 9: Status report SOLEIL  September 2006

ESRF: september 2006

0

50

100

150

200

250

Nu

mb

er o

f Dev

iceS

erve

rs r

equ

ired

for

co

mm

issi

on

ing

an

d fi

rst 6

mo

nth

s o

f op

erat

ion

Todo

In progress

Completed

Insertion devices, new Diags Insertion devices, new Diags, BL Front ends, RF complements

TANGO Device Server status (in june !!)

Page 10: Status report SOLEIL  September 2006

ESRF: september 2006

Today on accelerators

Page 11: Status report SOLEIL  September 2006

ESRF: september 2006

On beamlines

• DIFFABS

• TEMPO– First Device deployment scheduled on Friday !!

Page 12: Status report SOLEIL  September 2006

ESRF: september 2006

The Supervision layer

Status of the Control System

Page 13: Status report SOLEIL  September 2006

ESRF: september 2006

Present state for supervision applications

• PSS• TL1• Booster

– General application– RF

• TL2

• Storage ring– Vacuum system– Power supplies– Machine Interlocks– RF system– Diagnostics– BL Front end – ID control (to come)

More than 10 GlobalSCREEN applications in full operation

Page 14: Status report SOLEIL  September 2006

ESRF: september 2006

Booster RF GlobalSCREEN Application

Page 15: Status report SOLEIL  September 2006

ESRF: september 2006

SR Power Supply GlobalSCREEN Application

Page 16: Status report SOLEIL  September 2006

ESRF: september 2006

4 Labview Applications : Tune measurement, MRSV, Pinhole

Tune measurement

•H plane•Vplane

Sources

•Spectrum analyser•Turn By turn signal

Output

•Publish into TANGO•Tune meas. device

Excitation

•Shaker magnet•striplines

H-tune V-tune

H-tuneZoom

V-tuneZoom

Auto-tracking

Page 17: Status report SOLEIL  September 2006

ESRF: september 2006

Other applications

•Archiving and Setpoint management•MAMBO java application for

HDB and TDB systems•Bensikin application

•Machine Status•Heavy use of Tango Generic applications

• (ATKPanel, DeviceTree, ATKTrend, etc ..)

Page 18: Status report SOLEIL  September 2006

ESRF: september 2006

On beamlines

• DIFFABS– First version of GlobalScreen application in

operation– First acquisition process sequences done

by scientists with the PASSERELLE software

Page 19: Status report SOLEIL  September 2006

ESRF: september 2006

Project Management facts

• We are leaving the pic load period– Software :

• 10 people in the software group with 6 additional subcontractors are

– Hardware : About 12 people are working on the electronics installation

• A constant job is to follow up priorities and requirements from our internal customers

– Sources– Experiments

• A list of DeviceServers has been setup with associate dates for delivery

– For Machine– And the first 10 beamlines

• A subcontractor is working fulltime with us on this matter

0

50

100

150

200

250

300

Spécif

icatio

n G

énér

ique

Spécif

icatio

n M

achi

ne

Spécif

icatio

n Tra

nsve

rseL

igne

s

Spécif

icatio

n DIF

FABS

Spécif

icatio

n SAM

BA

Spécif

icatio

n O

DE

Spécif

icatio

n CASSIO

PEE

Réalis

atio

n Gén

ériq

ue

Réalis

atio

n M

achin

e

Réalis

atio

n Tr

ansv

erse

Ligne

s

Réalis

atio

n DIF

FABS

Réalis

atio

n SAM

BA

Réalis

atio

n ODE

Réalis

atio

n CASSIO

PEE

Insta

llatio

n Gén

ériq

ue

Insta

llatio

n M

achi

ne

Insta

llatio

n Tr

ansv

erse

Ligne

s

Insta

llatio

n DIF

FABS

Insta

llatio

n SAM

BA

Insta

llatio

n ODE

Insta

llatio

n CASSIO

PEE

Valida

tion

Génér

ique

Valida

tion

Mac

hine

Valida

tion

Tran

sver

seLi

gnes

Valida

tion

DIFFABS

Valida

tion

SAMBA

Valida

tion

ODE

Valida

tion

CASSIOPEE

Nombre total de livrables ICA

à faire

blocages

en cours

achevés à 100%

Page 20: Status report SOLEIL  September 2006

ESRF: september 2006

Conclusion

Status of the Control System

Page 21: Status report SOLEIL  September 2006

ESRF: september 2006

Some Successful outcomes to date

Software integration of all subsystems of the storage ring has been done within less than 2 weeks

Software has (till now !!) never delayed Machine tests

Tango Devices provide also high level services (level 2 and 3 device servers)

up to calculations applications (like tune measurement), process management, state and attribute composers, equipment monitoring, etc ..

and is not limited to simple I/O distribution on the network ..

Software quality is satisfactory thanks to good software engineering practices

Versioning management (also adopted by Source division for GlobalSCREEN applications)

Large internal and external use of a Bug tracker system

Continuously updated Report Boards

About 4 calls during the nights during the first 4 weeks of operation

Page 22: Status report SOLEIL  September 2006

ESRF: september 2006

Next steps

Installation of Full TANGO Control systems on SOLEIL Beamlines

Transition to exploitation for the Accelerators