Generador Nave Industrial

download Generador Nave Industrial

of 4

Transcript of Generador Nave Industrial

  • 7/27/2019 Generador Nave Industrial

    1/4

    CLAVE CONCEPTO

    EJE TRAMO

    LOSA DE CIMENTACION

    CIMENTACION

    ZAPATAS (CIMENTACION)

    EXCAVACION B, C 1-2 Y 3 1.50 1.50 1.50 6 20.25 M3 ZAPATAS

    PLANTILLA DE F'C=100 KG/CM2 DE 6CM DE ESP. B, C 1-2 Y 3 1.50 1.50 6 13.50 M2 ZAPATAS

    CIMBRADO Y DESCIMBRADO 1.30 0.15 24 4.68 M2 CIMENTACION ZAPATA

    CIMBRADO Y DESCIMBRADO 0.40 1.29 12 6.19 M2 DADO

    0.40 1.29 12 6.19 M2 DADO

    17.06 M2

    ACERO DEL # 4 @ 15 CM. AMBOS LADOS 1.42 0.993 120 169.21 KG PARRILLAS

    ACERO DEL # 4 @ ( VERTICALES ) 2.00 0.993 48 95.33 KG DADOS

    264.54 KG

    ACERO DEL # 2 @ 15 CM. ESTRIBOS. 1.72 0.248 66 28.15 KG ESTRIBOS DEL DADO

    CONCRETO DE F'C= 200 KG/CM2 1.30 1.30 0.15 6 1.52 M3 CIMENTACION ZAPATA

    0.40 0.40 1.29 6 0.96 M3 DADO

    2.48 M3

    VOL. EXC. - VOL. CONCR.

    RELLENO 20.25 - 2.48 17.77 M3 ZAPATA DADO

    MURETE DE ENRACE ( CIMENTACION )EXCAVACION A 1 - 3 18.00 0.70 1.00 1 12.60 M3

    3 A - C 11.00 0.70 1.00 1 7.70 M3

    MAS CASTILLOS DE 15 X 15 CMS 0.20 0.20 0.30 9 0.11 M3

    20.41 M3 EXCAVACION

    PLANTILLA DE F'C=100 KG/CM2 DE 6CM DE ESP. A 18.00 0.70 1 12.60 M2

    3 11.00 0.70 1 7.70 M2

    20.30 M2

    MURETE DE ENRACE CON BLOCK ( CIMENTACION ) A 1 - 3 18.00 1.00 1 18.00 M2

    3 A - C 11.00 1.00 1 11.00 M2CASTILLOS 0.15 1.00 -9 -1.35 M2 ( - )

    OBSERVACIONESLOCALIZACION

    NUMEROS GENERADORES

    OBRA:

    MUNICIPIO:

    LOCALIDAD:

    FECHA:

    RESULTADOLARGO

    ( m )

    ESPESOR

    ( m )UNIDADPZAS

    ANCHO

    ( m )

    ALTO

    ( m )

    ACERO

    ( KG/ML )

  • 7/27/2019 Generador Nave Industrial

    2/4

    27.65 M2 MURETE

    VOL. EXC. - VOL. MURO

    RELLENO EN ZANJAS DE MURETE 20.41 - 4.35 16.06 M3 MURETE DE ENRACE (CIM.)

    CASTILLOS 15X15 CMS.

    CIMBRAS EN CASTILLOS A 1 - 3 0.15 1.00 12 1.80 M23 A - C 0.15 1.00 6 0.90 M2

    2.70 M2

    ACERO No. 2 ESTRIBOS @ 15 CMS. 0.72 0.248 72 12.86 KG

    12.86 KG

    ACERO No. 3 VERTICALES 1.30 0.559 36 26.16 KG

    26.16 KG

    CONCRETO DE F'C= 200 KG/CM2 0.15 0.15 1.00 9 0.20 M3 CASTILLOS EN MURETE0.20 M3

    CADENA DE DESPLANTE O CONTRATRABESCADENA DE DESPLANTE O CONTRATRABES

    CIMBRADO Y DESCIMBRADO A 1 - 3 18.00 0.20 1 3.60 M2

    3 A - C 11.00 0.20 1 2.20 M2

    5.80 M2

    LONG. DESARR.

    ACERO DEL # 2 ( ALAMBRON ) ANILLETAS A 1 - 3 18.00 0.74 0.248 121 22.21 KG CADENA DE DESPLANTE

    ACERO DEL # 2 ( ALAMBRON ) ANILLETAS 3 A - C 11.00 0.74 0.248 74 13.64 KG CADENA DE DESPLANTE

    35.85 KG

    ACERO DEL # 3 (VARILLA RECTA) A 1 - 3 18.15 0.559 4 40.58 KG CADENA DE DESPLANTE

    ACERO DEL # 3 (VARILLA RECTA) 3 A - C 11.15 0.559 4 24.93 KG CADENA DE DESPLANTE

    65.51 KG

    CONCRETO DE F'C= 200 KG/CM2 A 1 - 3 18.00 0.15 0.20 1 0.54 M3 CADENA DE DESPLANTE

    3 A - C 11.00 0.15 0.20 1 0.33 M3 CADENA DE DESPLANTE

    0.87 M3

    PISO FIRME DE CONCRETO DE F'C=250 KG/CM2PISO FIRME DE CONCRETO DE F'C=250 KG/CM2LIMPIA TRAZO Y NIVELACION A - C 1 - 3 18.00 11.00 1 198.00 M3

    198.00 M3

    DESPALME DE ESTRUCTURA A - C 1 - 3 18.00 8.00 0.40 1 57.60 M3

    57.60 M3

    RELLENO EN PLATAFORMA DE CIMENTACION A - C 1 - 3 18.00 8.00 0.38 1 54.72 M3

    54.72 M3

  • 7/27/2019 Generador Nave Industrial

    3/4

    CIMBRA FRONTALES A 1 - 3 18.00 0.15 1 2.70 M2

    3 A - C 11.00 0.15 1 1.65 M2

    4.35 M2

    PISO FIRME DE 15 CM DE ESPESOR. PULIDO FINO A - C 1 - 3 18.00 11.00 0.15 1 29.70 M329.70 M3

    MALLA LAC 6 - 6/4 - 4 A - C 1 - 3 18.00 11.00 1 198.00 M2

    6.45 M2 TRASLAPES

    204.45 M2

  • 7/27/2019 Generador Nave Industrial

    4/4

    CLAVE CONCEPTO

    EJE TRAMOPZAS RESULTADO UNIDAD OBSERVACIONES

    NUMEROS GENERADORES

    OBRA:

    MUNICIPIO:

    LOCALIDAD:

    FECHA:

    LOCALIZACION LARGO( m )

    ANCHO

    ( m )

    ALTO

    ( m )

    ESPESOR

    ( m )

    ACERO

    ( KG/ML )