Overview of RegionalSurvey Results
Full Cost Recovery (FCR)
in Southeast Asia
Hanoi, Vietnam7 June 2005
Laila SuryodipuroUS-AEP/PADCO
The views expressed in this paper are the views of the authors and do not necessarily reflect the views or policies of theAsian Development Bank (ADB), or its Board of Directors, or the governments they represent. ADB does not guaranteethe accuracy of the data included in this paper and accepts no responsibility for any consequences of their use.Terminology used may not necessarily be consistent with ADB official terms.
2
Presentation Outline
FCR overview and principal challenges
Survey methodology
Highlights of institutional arrangements and tariff setting in 5 countries
Key statistics and performance indicators for surveyed utilities
Important factors enabling FCR
Important actions taken to improve FCR
Preliminary considerations for promoting FCR

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 2/18
FCR Overview andPrincipal Challenges
4
Full Cost Recovery Definition
Revenue for O&M, depreciation, debt service, andexpansion for the most part, come from billing/user charges
Measuring cost recovery: The smaller the ratio, thebetter
O&M Coverage (working ratio) RatioO&M (excluding depreciation & interest)
Water-related Revenues
FCR RatioTotal expenses (including depreciation & interest)
Water-related RevenuesBased on Accrual / Utility Method of tariff setting

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 3/18
5
Why Cost Recovery Matters
Enables expanded coverage Increasing access to water is a global priority
Government cannot afford to subsidize
Improves water quality and quantity
Determines and reduces true cost of water –increases efficiency (in production andconsumption)
Promotes rational consumption
Promotes equitable pricing to customers Frees up government resources
6
The Vicious Cycle of Weak Cost Recovery
Weak cost recovery
Inefficient operations
Low investmentPoor skills development
Customer dissatisfaction
Poor service
Low willingness to pay

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 4/18
7
Principal Challenges to
Achieving FCR
1. Revenue/Tariff
2. Personnel
3. Operations & Maintenance
4. General & Administrative
5. Government Commitment and Relations
8
Survey Methodology
US-AEP, in partnership with SEAWUN andnational water associations, conducted survey
15 utilities selected based on cost recoveryratios
Self-assessment of key factors and actions
Key factors—conditions/tools that enable utilities totake certain actions to achieve FCR (humanresources, relationship with local government,customer service)
Key actions—direct actions by utilities that directlyreduce costs and increase revenue (billing, metering,tariff increase, reduction of NRW)

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 5/18
Highlights of InstitutionalArrangements and Tariff Setting
10
Role of Government Level of government responsibility for water supply
varies across the region
Municipal: Indonesia, Philippines Province/state: Malaysia, Vietnam National: Thailand
Degree of government support for capital
expenditure varies No support: Philippine utilities, MWA, Johore
(private) Some support: Indonesia, PWA, Vietnam Significant support: Malaysian utilities (except
privatized utilities)

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 6/18
11
Water Supply Coverage
Average service coverage in the 5 countries (notin the surveyed utilities) ranges between 35-70%, except for Malaysia which has universalcoverage.
The percentage of population served in theregion, particularly for the Philippines andIndonesia, is low even among strong utilities.
12
Tariff Setting
Tariff adjustment is difficult and political in all 5countries, except Philippines
Not difficult
Done by LWUA, a national, technical agency
YesPhilippines
Difficult
Half of utilities with no increase in 10 years
NoMalaysia
Difficult
Increase only every 5-6 years is common
YesIndonesia
Previously difficult Yes, new
policy
Vietnam
DifficultNoThailand
Tariff AdjustmentFCR PolicyCountry

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 7/18
13
Average Tariff Price
Average residential tariff of $0.40/m3 isstill affordable for any large Asian city(based on 5% household income ceiling-- ADB study);
Average tariff in surveyed utilities isbetween $0.15 - 0.30/m3, except for Philippine utilities
Key Statistics and PerformanceIndicators of Surveyed Utilities

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 8/18
15
O&M and FCR Ratios
I n d - B o g o r
I n d - M a k a s s a r
I n d - M a l a n g
I n d - M e d
a n
M a l - J o h o r
M a l - P e n a n g
M a l - S i b u
P h i - D i p o l o g
P h i - M a r i l a o
P h i - L e y t e
T h a - M W A
T h a - P W A
V i e - H a i P h o n g
V i e - T T H u e
V i e - B R V u n g T a u
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
O&M ratio
FCR ratio
WB
recommendations
(0.68), based on
25% top performing
utilities in developing
countries
16
NRW and Accounts Receivables
Non-revenue-water (NRW) Varies between 15% and 46%
Correlation between NRW and achievementof FCR – the lower the NRW, the better theFCR
Accounts Receivables Varies between 10 and 99 days. All, except
one, are below WB’s recommended 90 days
Positive correlation between AccountsReceivables and achievement of FCR

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 9/18
Key Factors Enabling FCR
18
Relative Importance of Key Factors
7%Development of benchmarking/KPI
system
6
7%Accuracy of record keeping,
accounting and IT
5
8%Existence of medium-term plan4
13%Customer-oriented service3
16%Attitudes and background of personnel2
20%Government Relations (local or central)1
ImportanceKey Factor/Enabling ConditionNo.

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 10/18
19
Government Relations (local or central)
Primarily: Government (local/central) approves
tariff increases. Secondarily: Government (local/central)
provides grant funding Challenging factor as it is outside utility’s control Consistent with ADB’s “Asian Water Supplies”
(2004) conclusion:“It is the reluctance of elected officials to increase
tariffs that has, more than any other single factor,constrained water supply development in terms of
quality of service and coverage.”
Case study: Medan, Makassar
20
Attitudes and Professional Background
Quality of management and staff critical tosuccess of organization, and its ability toeffectively communicate with government
Case studies: Hai Phong, Penang, Dipolog

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 11/18
21
Customer-Oriented Service
Good service will create good reputation,reduce customer objections to tariff increases, and attract new customers
Utility efforts to improve customer serviceinclude creating a call center and anavailable rapid response team
Case study: Hai Phong
22
Existence of Medium-term Plan
Helps identify priority projects andtimeframe; allows basis for establishingfuture cost and revenue drivers
Resulting tariff increase also becomes
more acceptable

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 12/18
23
Accuracy in Recordkeeping,Accounting, and IT
Allows management to better identifyproblems, evaluate cost centers andrevenues, and make sound decisions
IT enables faster decision-making
Case study: Penang
24
Development of a Benchmarking/KPISystem and Targets
Allows comparison of performance withinand between utilities
Quantitative targets (and rewards) createincentives to perform; targets are set for
the lowest level of the organization
Case study: MWA

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 13/18
Key Actions to Improve FCR
26
Relative Importance of Key Actions
9%Improvement in billing (Invoicing,
collection, payment methods)
6
12%Aggressive increase in the number of
connections
5
12%Increase in tariff 4
17%Improvement in metering (reading,
replacement, and repair)
3
19%Improvements in operational efficiency
(reducing power, labor, chemical costs)
2
22%Reduction in physical losses1
ImportanceKey ActionNo

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 14/18

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 15/18
29
Improvements in Metering
Replace meters automatically after 5-8years of service (many surveyed utilities)
Outsource meter reading to third parties(Makassar and PWA)
Centralize meters by grouping between 2-10 meters in one location (Dipolog)
30
Tariff Increase
Public education campaigns first
Timing
Minimal increases for the poor
Use the unserved population to supportincrease (Makassar)
Staggered increases approved in oneprocess (Philippine utilities)

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 16/18
31
Increase in Number of Connections
Focus on large consumers, such asindustrial and large businesses (PWA)
Allow customers to pay for new connectionfees on credit (Medan)
Implement campaign programs inunserved areas (many surveyed utilities)
32
Billing and Collection Practices
Field inspection on customer classification(Makassar)
Strict disconnection policy for non-payment (Vietnam and Philippine utilities)
Outsourcing (PWA, Makassar), jointcollection (many)

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 17/18
Preliminary Considerationsfor Promoting FCR
34
Preliminary Considerations
National Level
Adopt a national FCR policy
Establish an independent regulatory body
Local Government Level
Develop quantitative and realisticperformance targets to evaluate utilityperformance

8/6/2019 Full Cost Recovery (Laila)
http://slidepdf.com/reader/full/full-cost-recovery-laila 18/18
35
Preliminary Considerations
Utility Level Improve tariff application process
Maintain regular communication with localgovernment on state of services
Stakeholder education campaign on FCR
Attract and retain high quality personnel
Develop customer-oriented services
Establish medium-term business plan Improve operational efficiency