CH13 ERP(1)

40
8/11/2019 CH13 ERP(1) http://slidepdf.com/reader/full/ch13-erp1 1/40 E4 E4-E5 (MANAGEMENT) E5 (MANAGEMENT) ERP Project ERP Project For internal circulation of BSNL only

Transcript of CH13 ERP(1)

Page 1: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 1/40

E4E4--E5 (MANAGEMENT)E5 (MANAGEMENT)

ERP ProjectERP Project

For internal circulation of BSNL only

Page 2: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 2/40

WELCOME

• This is a presentation for the E4-E5 Management

for all streams for the Topic:

ERP Project

• Eligibility: Those who have got the Upgradation

to from E4 to E5.

• This presentation is last updated on 15-3-2011.

• You can also visit the Digital Library of BSNL tosee this topic.

For internal circulation of BSNL only

Page 3: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 3/40

Agenda

i. What is ERP?

ii. Characteristics of ERP

iii. Why ERP?

iv. Implementation in BSNL

v. Some ERP Screens

For internal circulation of BSNL only

Page 4: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 4/40

For internal circulation of BSNL only

Page 5: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 5/40

What is ERP?

Enterprise Resource Planning Software

For internal circulation of BSNL only

Page 6: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 6/40

What is ERP?

ERP Software is a multi- module application

software that integrates activities across functional

departments/units.

Integration of different Processes and Data into

Single System

For internal circulation of BSNL only

Page 7: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 7/40

Historical System Architectures

• “Island of Automation”

• A hodge-podge of various systems that operated or

managed various divergent business processes.

• Systems were integrated with each other and

sometimes they weren't.

• Sometimes they were loosely interfaced and

sometimes they were more tightly interfaced

For internal circulation of BSNL only

Page 8: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 8/40

Key Characteristics of ERP

1. Integration:

Seamless integration of all the information

flowing through a company – financial and

accounting, human resource information, supply

chain information, and customer information

For internal circulation of BSNL only

Page 9: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 9/40

Key Characteristics of ERP

2. ERP Systems are not developed in-house:

• Mapping organizational requirements to theprocesses and terminology employed by the vendor

• Making informed choices about the parameter setting• Organizations that implement enterprise systems

enter into long-term relationships with vendors.

For internal circulation of BSNL only

Page 10: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 10/40

Key Characteristics of ERP

3. Best Practices

ERP vendors talk to many different businesses

within a given industry as well as academics to

determine the best and most efficient way of

accounting for various transactions and

managing different processes. The result is

claimed to be “Industry Best Practices”

For internal circulation of BSNL only

Page 11: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 11/40

Key Characteristics of ERP

4. Some Assembly Required

• Integration with various processes across

different modules and integration testing is

required

• Integration with other applications is also

required.

For internal circulation of BSNL only

Page 12: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 12/40

Why ERP?

• Technology

Transition of IT from Supporting Operational

entities to becoming Strategic Business Tool

For internal circulation of BSNL only

Page 13: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 13/40

Why ERP?

Corporate Initiative

• Strategic Initiative – Capability to Compete• Operational Initiative – foundation for

performance and cost improvement via

integration

• Organizational Initiative – To initiate major

organizational change within the company

For internal circulation of BSNL only

Page 14: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 14/40

Benefits of ERP

• Best Processes

• Reduced Inventories

• Integrated SCM

• Order Cycle Improvement

• Customer Service Improvement

• Reduced Working Capital

• ……………….. and so on.

For internal circulation of BSNL only

Page 15: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 15/40

ERP Project of BSNL

• Will be touching all the functions of organization

For internal circulation of BSNL only

Page 16: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 16/40

ERP

FICO

MM and

Inventory

Plant & EqptMaintenance

SCM

ProjectManagement

ProductionManagement

HRM

S&D

REM

BIS

QualityManagement

Enterprise Portal

BusinessIntelligence &

 Analysis

Enterprise

Strategy Mngt

For internal circulation of BSNL only

Page 17: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 17/40

ERP Implementation in BSNL

• SI – M/s HCL Infosystems Limited

• Application Provider : SAP

• BPR Consultant : M/s E&Y

For internal circulation of BSNL only

Page 18: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 18/40

Data Centres & Network

• CDR Data Centres at Kolkata and Hyderabad

• CDR Network to be used.

• New N/W for non-CDR Circles

For internal circulation of BSNL only

Page 19: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 19/40

ERP in BSNL

• Phase I – To be implemented in Seven Circles

(being prepared for implementation)

• Phase II – To be implemented by March 2011.

For internal circulation of BSNL only

Page 20: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 20/40

POC Circles

1. ALTTC

2. BSNL Corporate Office

3. Karnataka TC

4. MH TC

5. STR

6. WTP7. Telecom Factory Mumbai

For internal circulation of BSNL only

Page 21: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 21/40

ERP Implementation Approach

BPR Exercise

• Document Existing Processes

• Decide on “To Be” Processes

SRS Documentation• Documentation of requirements

 Application Validation

• Testing of Each & EveryProcesses

Implementation

• Integration• Data Populating

• Training

For internal circulation of BSNL only

Page 22: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 22/40

ERP Implementation

• Infrastructure

• Data Collection

 – Master Data in Templates

 – Decide SPOC Officers for Data Collection

 – Transaction Data During Pre-Go-Live

Stage

For internal circulation of BSNL only

Page 23: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 23/40

ERP Implementation Formation

• Core Team

• Power Users

• End Users

• ESS Users

For internal circulation of BSNL only

Page 24: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 24/40

Role of Core Team

• BPP Phase – Design of ERP System

 – To ensure implementation of BPR

Recommendations

• Realization Phase: Formation of Data MigrationStrategy, Templates, Testing Strategy, Test

Cases• Imparting Training

• Final Phase: Cut-over and MigrationFor internal circulation of BSNL only

Page 25: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 25/40

Power User Teams

• To be formed before the POC Go-Live

• Levels

I. Unit Power Users- L1

II. Circle Level Power Users – L2

III. Central Level Power Users – L3

For internal circulation of BSNL only

Page 26: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 26/40

Unit Level Power Users(L1)

• Owner – SSA

• Number – Minimum 2

• Responsibilities

 – SAP GUI Installation

 – Hardware Availability/Compatibility/Installation – Liaison for SAP User Management

 – General Hand-holding

 – Resolution of Module Specific Queries of End Users – Act as ESS Trainers for the unit

 – Liaison for Change of Work Flow

For internal circulation of BSNL only

Page 27: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 27/40

Page 28: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 28/40

Circle Level Power Users(L2)

• Responsibilities

 – Assess and Recommend in Change of Work Flow

 – Train Power Users of Circle

 – Implement New Functional Requirements

 – Test and Validate before final release in the system

 – Look for Improvement areas/ change

For internal circulation of BSNL only

Page 29: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 29/40

ERP Implementation

• Right mix of People, Process and Technology

For internal circulation of BSNL only

Page 30: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 30/40

Major Issues

• Integration with Existing Diverse Applications

• Large Organization

• Many Processes

• Non-uniform Processes

• Resistance to Change and Adopt New Processes

• Data Preparation

For internal circulation of BSNL only

Page 31: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 31/40

SAP ERP Screen Shots

For internal circulation of BSNL only

Page 32: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 32/40

Logon Screen

Page 33: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 33/40

For internal circulation of BSNL only

Page 34: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 34/40

For internal circulation of BSNL only

Page 35: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 35/40

BackExit Cancel

New Session

Short Cut

For internal circulation of BSNL only

Page 36: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 36/40

Page 37: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 37/40

For internal circulation of BSNL only

Page 38: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 38/40

For internal circulation of BSNL only

C l di R k

Page 39: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 39/40

Concluding Remarks

• Technology is an enabler, not the driver

• It is a means to an end, not the end.

For internal circulation of BSNL only

Page 40: CH13 ERP(1)

8/11/2019 CH13 ERP(1)

http://slidepdf.com/reader/full/ch13-erp1 40/40

For internal circulation of BSNL only